Appellant / Complainant
Deepika Agrawal, Amit Agrawal
Respondent
Intellect Projects Pvt. Ltd.
intellect projects pvt. ltd.
₹5,00,000
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126000062018 by Deepika Agrawal, Amit Agrawal against Intellect Projects Pvt. Ltd. before up_rera.
for delivery of Judgment/Order
The Tribunal partially allowed the appeal, modifying the previous order to grant the appellants interest at the rate of MCLR+1% per annum for delayed possession from 15.04.2016 until the offer of possession following receipt of completion/occupancy certificates.
Hearing
The Tribunal heard arguments from the counsel for both parties, after which the judgment was reserved.
Hearing
The Tribunal granted the respondent one final opportunity to file a reply to the grounds of appeal within 15 days and directed them to serve a copy to the appellant via email.
Hearing
The court granted a request for adjournment as requested by the counsel for the appellant to seek an alternative hearing date.
Hearing on Appeal
The Tribunal adjourned the matter due to the respondent's absence and granted the respondent two weeks to file objections to the grounds of appeal, with subsequent timelines set for replies and filing.
Tribunal Order #0901126000062018-23-03-2022
The Tribunal partially allowed the appeal, modifying the previous order to grant the appellants interest at the rate of MCLR+1% per annum for delayed possession from 15.04.2016 until the offer of possession following receipt of completion/occupancy certificates.
Tribunal Disposal & Final Award Ruling
The Tribunal partially allowed the appeal, modifying the previous order to grant the appellants interest at the rate of MCLR+1% per annum for delayed possession from 15.04.2016 until the offer of possession following receipt of completion/occupancy certificates. Awarded in favor of Partial. Awarded interest rate: MCLR + 1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal partially allowed the appeal, modifying the previous order to grant the appellants interest at the rate of MCLR+1% per annum for delayed possession from 15.04.2016 until the offer of possession following receipt of completion/occupancy certificates.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR + 1%
Interest Period
from 15.04.2016 till offer of possession after receipt of CC/OC from the Competent Authority
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rajnish Kumar Srivastava
Respondent Advocate(s)
- Rajesh Chadha
Official RERA Tribunal Orders (1)
The Tribunal partially allowed the appeal, modifying the previous order to grant the appellants interest at the rate of MCLR+1% per annum for delayed possession from 15.04.2016 until the offer of possession following receipt of completion/occupancy certificates.
Need to research all rulings for intellect projects pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.