up_reraStatus: Completed
CASE ID: 0901126000112019

Appellant / Complainant

Om Prakash Verma

VS

Respondent

Greenbay Infrastructure Pvt. Ltd.

Developer Firm

greenbay infrastructure pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

13 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126000112019 by Om Prakash Verma against Greenbay Infrastructure Pvt. Ltd. before up_rera.

2
Stage 108/10/2021

Hearing

The parties have reached an out-of-court settlement, and the appellant has requested to discontinue the proceedings accordingly.

3
Stage 211/09/2021

Hearing

No text available.

4
Stage 309/09/2021

Hearing

The Tribunal adjourned the matter due to the absence of the appellant and directed that the case be listed in 'Lok Adalat' on 11.09.2021 following a reported settlement between the parties.

5
Stage 405/05/2021

Hearing

No text available.

6
Stage 508/04/2021

Hearing

No text available.

7
Stage 615/03/2021

Hearing

No text available.

8
Stage 712/02/2021

Hearing

The Tribunal noted that the parties have almost settled the matter and granted a short adjournment to complete formalities, rescheduling the hearing for 15.03.2021.

9
Stage 804/02/2021

Hearing

The Tribunal directed the respondent to pay the outstanding amount in six installments via RTGS, with the first two installments due by 28.02.2021, and ordered both parties to file a formal settlement deed by 12.02.2021.

10
Stage 925/08/2020

Hearing

No text available.

11
Stage 10Final Ruling Order

Tribunal Order #0901126000112019-08-10-2021

The parties have reached an out-of-court settlement, and the appellant has requested to discontinue the proceedings accordingly.

12
Stage 11Interim Order

Tribunal Order #0901126000112019-04-02-2021

The Tribunal directed the respondent to pay the outstanding amount in six installments via RTGS, with the first two installments due by 28.02.2021, and ordered both parties to file a formal settlement deed by 12.02.2021.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The parties have reached an out-of-court settlement, and the appellant has requested to discontinue the proceedings accordingly. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The parties have reached an out-of-court settlement, and the appellant has requested to discontinue the proceedings accordingly.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kailash Prashad Pandey

Respondent Advocate(s)

  • Himanshu Hemant Gupta
  • Sarvesh Tiwari

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126000112019-08-10-2021

The parties have reached an out-of-court settlement, and the appellant has requested to discontinue the proceedings accordingly.

INTERIM_ORDEROrder ID: 0901126000112019-04-02-2021

The Tribunal directed the respondent to pay the outstanding amount in six installments via RTGS, with the first two installments due by 28.02.2021, and ordered both parties to file a formal settlement deed by 12.02.2021.

TathyaGrid RERA Intelligence AI

Need to research all rulings for greenbay infrastructure pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →