up_reraStatus: Completed
CASE ID: 0901126000972019

Appellant / Complainant

Hawelia Builders Pvt. Ltd.

VS

Respondent

Harish Bhalla, J.K. Bhalla

Developer Firm

hawelia builders pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

19 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126000972019 by Hawelia Builders Pvt. Ltd. against Harish Bhalla, J.K. Bhalla before up_rera.

2
Stage 105/01/2022

Exchange of pleadings

The case was dismissed for want of prosecution due to the applicant's failure to appear and their continued non-compliance with the provisions of Section 43(5) of the Act.

3
Stage 202/12/2021

Further Order

The order records a procedural update where the case was called and noted that the list has been revised.

4
Stage 312/11/2021

Hearing

The Tribunal directed the parties to attempt a settlement regarding the disputed amounts between the builder and the allottee and ordered them to appear with a complete proposal on 02.12.2021.

5
Stage 422/09/2021

Hearing

The Tribunal directed the respondents to appear in person (physically or via video conferencing) and scheduled the matter for 12.11.2021 to hear arguments regarding compliance with Section 43(5) of the Act.

6
Stage 506/09/2021

Hearing

The Tribunal directed the appellant to deposit any deficient amount required under Section 43(5) of the Act before the next hearing date.

7
Stage 630/04/2021

Hearing

No text available.

8
Stage 705/04/2021

Delay condonation

No text available.

9
Stage 815/03/2021

Delay condonation

The Tribunal granted a final opportunity to the applicant to deposit any balance amount required under Section 43(5) of the Act following an adjournment request due to illness.

10
Stage 923/02/2021

Compliance of section 43(5)

The Tribunal adjourned the matter to 15.03.2021 to allow the respondent's counsel to argue regarding compliance with Section 43(5) of the Act.

11
Stage 1015/02/2021

Compliance of section 43(5)

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the case for hearing on 23.02.2021 regarding the application for condonation of delay.

12
Stage 1103/02/2021

Rest deposit Amount under 43(5) of the Act

The Tribunal directed the Registry to place the respondent's objection regarding the Section 43(5) deposit on record and scheduled the matter for further orders on 15.02.2021.

13
Stage 1211/12/2020

Rest deposit Amount under 43(5) of the Act

No text available.

14
Stage 1304/11/2020

Rest deposit Amount under 43(5) of the Act

No text available.

15
Stage 14Final Ruling Order

Tribunal Order #0901126000972019-05-01-2022

The case was dismissed for want of prosecution due to the applicant's failure to appear and their continued non-compliance with the provisions of Section 43(5) of the Act.

16
Stage 15Interim Order

Tribunal Order #0901126000972019-12-11-2021

The Tribunal directed the parties to attempt a settlement regarding the disputed amounts between the builder and the allottee and ordered them to appear with a complete proposal on 02.12.2021.

17
Stage 16Interim Order

Tribunal Order #0901126000972019-06-09-2021

The Tribunal directed the appellant to deposit any deficient amount required under Section 43(5) of the Act before the next hearing date.

18
Stage 17Interim Order

Tribunal Order #0901126000972019-15-03-2021

The Tribunal granted a final opportunity to the applicant to deposit any balance amount required under Section 43(5) of the Act following an adjournment request due to illness.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The case was dismissed for want of prosecution due to the applicant's failure to appear and their continued non-compliance with the provisions of Section 43(5) of the Act. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The case was dismissed for want of prosecution due to the applicant's failure to appear and their continued non-compliance with the provisions of Section 43(5) of the Act.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 43(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Yash Tandon
  • Tushar Bahadur

Respondent Advocate(s)

  • Nirmit Srivastava

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126000972019-05-01-2022

The case was dismissed for want of prosecution due to the applicant's failure to appear and their continued non-compliance with the provisions of Section 43(5) of the Act.

INTERIM_ORDEROrder ID: 0901126000972019-12-11-2021

The Tribunal directed the parties to attempt a settlement regarding the disputed amounts between the builder and the allottee and ordered them to appear with a complete proposal on 02.12.2021.

INTERIM_ORDEROrder ID: 0901126000972019-06-09-2021

The Tribunal directed the appellant to deposit any deficient amount required under Section 43(5) of the Act before the next hearing date.

INTERIM_ORDEROrder ID: 0901126000972019-15-03-2021

The Tribunal granted a final opportunity to the applicant to deposit any balance amount required under Section 43(5) of the Act following an adjournment request due to illness.

TathyaGrid RERA Intelligence AI