up_reraStatus: Completed
CASE ID: 0901126001192019

Appellant / Complainant

S.V.P. Builders India Limited

VS

Respondent

Neha Jain

Developer Firm

s.v.p. builders india limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

20 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126001192019 by S.V.P. Builders India Limited against Neha Jain before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 127/09/2021

Compliance of section 43(5)

The Tribunal dismissed four appeals filed by M/s S. V. P. Builders India Ltd. due to non-compliance with the mandatory pre-deposit requirements of Section 43(5) of the RERA Act, and directed that partially deposited amounts be transferred to the UPRERA account.

3
Stage 221/09/2021

Exchange of pleadings

The Tribunal granted the appellant a final three-day extension to comply with Section 43(5) of the Act, warning that failure to do so will result in the dismissal of the appeal.

4
Stage 308/09/2021

Hearing

The Tribunal granted a request for adjournment made by the respondent's counsel and rescheduled the hearing to 21.09.2021.

5
Stage 426/04/2021

Hearing

No text available.

6
Stage 501/04/2021

Compliance of section 43(5)

No text available.

7
Stage 612/03/2021

Compliance of section 43(5)

No text available.

8
Stage 702/03/2021

Compliance of section 43(5)

The Tribunal directed the appellant to ensure complete compliance with Section 43(5) of the Act, 2016 by the next hearing, warning that failure to comply will result in the dismissal of the appeal.

9
Stage 818/02/2021

For Order

The Tribunal adjourned the matter to 02.03.2021 and directed the appellant to ensure complete compliance with Section 43(5) of the Act before the next hearing.

10
Stage 928/01/2021

For Order

No text available.

11
Stage 1027/01/2021

For Order

The Tribunal granted the appellant a one-week extension to comply with Section 43(5) of the Act, 2016, warning that failure to achieve complete compliance by the next hearing will result in dismissal of the appeal.

12
Stage 1112/01/2021

Hearing

No text available.

13
Stage 1210/12/2020

Hearing

No text available.

14
Stage 1319/11/2020

Hearing

No text available.

15
Stage 14Interim Order

Tribunal Order #0901126001192019-21-09-2021

The Tribunal granted the appellant a final three-day extension to comply with Section 43(5) of the Act, warning that failure to do so will result in the dismissal of the appeal.

16
Stage 15Interim Order

Tribunal Order #0901126001192019-02-03-2021

The Tribunal directed the appellant to ensure complete compliance with Section 43(5) of the Act, 2016 by the next hearing, warning that failure to comply will result in the dismissal of the appeal.

17
Stage 16Interim Order

Tribunal Order #0901126001192019-18-02-2021

The Tribunal adjourned the matter to 02.03.2021 and directed the appellant to ensure complete compliance with Section 43(5) of the Act before the next hearing.

18
Stage 17Final Ruling Order

Tribunal Order #0901126001192019-27-09-2021

The Tribunal dismissed four appeals filed by M/s S. V. P. Builders India Ltd. due to non-compliance with the mandatory pre-deposit requirements of Section 43(5) of the RERA Act, and directed that partially deposited amounts be transferred to the UPRERA account.

19
Stage 18Interim Order

Tribunal Order #0901126001192019-27-01-2021

The Tribunal granted the appellant a one-week extension to comply with Section 43(5) of the Act, 2016, warning that failure to achieve complete compliance by the next hearing will result in dismissal of the appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed four appeals filed by M/s S. V. P. Builders India Ltd. due to non-compliance with the mandatory pre-deposit requirements of Section 43(5) of the RERA Act, and directed that partially deposited amounts be transferred to the UPRERA account. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed four appeals filed by M/s S. V. P. Builders India Ltd. due to non-compliance with the mandatory pre-deposit requirements of Section 43(5) of the RERA Act, and directed that partially deposited amounts be transferred to the UPRERA account.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.05.2016 till the date of obtaining OC/CC or offer of possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 43(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Azhar Ikram
  • Manish Singh

Respondent Advocate(s)

  • Pradeep Tiwari

Official RERA Tribunal Orders (5)

INTERIM_ORDEROrder ID: 0901126001192019-21-09-2021

The Tribunal granted the appellant a final three-day extension to comply with Section 43(5) of the Act, warning that failure to do so will result in the dismissal of the appeal.

INTERIM_ORDEROrder ID: 0901126001192019-02-03-2021

The Tribunal directed the appellant to ensure complete compliance with Section 43(5) of the Act, 2016 by the next hearing, warning that failure to comply will result in the dismissal of the appeal.

INTERIM_ORDEROrder ID: 0901126001192019-18-02-2021

The Tribunal adjourned the matter to 02.03.2021 and directed the appellant to ensure complete compliance with Section 43(5) of the Act before the next hearing.

FINAL_ORDEROrder ID: 0901126001192019-27-09-2021

The Tribunal dismissed four appeals filed by M/s S. V. P. Builders India Ltd. due to non-compliance with the mandatory pre-deposit requirements of Section 43(5) of the RERA Act, and directed that partially deposited amounts be transferred to the UPRERA account.

INTERIM_ORDEROrder ID: 0901126001192019-27-01-2021

The Tribunal granted the appellant a one-week extension to comply with Section 43(5) of the Act, 2016, warning that failure to achieve complete compliance by the next hearing will result in dismissal of the appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for s.v.p. builders india limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →