up_reraStatus: Completed
CASE ID: 0901126002092022

Appellant / Complainant

Shruti

VS

Respondent

Mr Proview Realtech Private Limited

Developer Firm

mr proview realtech private limited

Disputed Amount

1,00,000

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferMaintenance & Utility Disputes

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

37 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126002092022 by Shruti against Mr Proview Realtech Private Limited before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferMaintenance & Utility Disputes
2
Stage 109/07/2025

for delivery of Judgment/Order

The Tribunal dismissed the appeal, ruling that the subsequent allottees' rights and possession timelines are governed by the fresh allotment agreement dated 07.05.2014 rather than the original agreement, thereby confirming the validity of the UPRERA rectification order.

3
Stage 203/03/2025

Hearing

The Tribunal heard arguments from both parties regarding the appeal, but has reserved the judgment for a later date.

4
Stage 306/02/2025

Hearing

The Tribunal has scheduled the case for orders or hearing on March 3, 2025.

5
Stage 416/01/2025

Hearing

The Tribunal granted the parties time to prepare their briefs for final arguments and scheduled the appeal for a final hearing on February 6, 2025.

6
Stage 510/12/2024

Hearing

The Tribunal granted the appellant time to file objections to the computation chart submitted by the respondent and scheduled the next hearing for January 16, 2025.

7
Stage 624/10/2024

Hearing

The Tribunal recorded the parties' submissions regarding payments made and outstanding dues for Flat No. D-206 and adjourned the matter to 10-12-2024 upon joint request.

8
Stage 713/09/2024

Hearing

The Tribunal noted the appellant's compliance with a previous order and granted an adjournment requested by the respondent, scheduling the matter for hearing/orders on 24.10.2024.

9
Stage 808/08/2024

Hearing

The Tribunal directed the appellant to file an application with the Registry to delete previously uploaded annexures so that new ones can be uploaded in compliance with a prior order.

10
Stage 911/07/2024

Hearing

The Tribunal granted the appellant ten days to file necessary annexures to the appeal and scheduled the matter for hearing on August 8, 2024.

11
Stage 1014/05/2024

Hearing

The Tribunal denied permission for Sri Sunil Kumar to argue the case as he was not listed as an appellant and adjourned the proceedings to 11.07.2024 following a request from the appellant's counsel.

12
Stage 1116/04/2024

Hearing

The Tribunal granted an adjournment requested by the appellant to allow them time to engage legal counsel and rescheduled the hearing for 14.05.2024.

13
Stage 1212/03/2024

Hearing

The Tribunal directed the appellant to re-upload all documents with proper descriptions and page numbers, and to coordinate with the Registry to delete undocumented annexures within one week.

14
Stage 1309/02/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal hearing for March 12, 2024.

15
Stage 1409/10/2023

Hearing

No text available.

16
Stage 1529/08/2023

Hearing

No text available.

17
Stage 1611/07/2023

Hearing

No text available.

18
Stage 1701/05/2023

Hearing

No text available.

19
Stage 1810/04/2023

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel to prepare the brief and upload annexures, rescheduling the hearing for May 1, 2023.

20
Stage 1924/03/2023

Hearing

The Tribunal granted the appellant one week to rectify and upload descriptions, dates, and page numbers for all filed annexures. The matter is scheduled for orders on 10.04.2023.

21
Stage 2015/02/2023

Exchange of pleadings

The Tribunal granted the respondent's counsel one week to file a Vakalatnama and adjourned the matter to 24.03.2023.

22
Stage 2113/01/2023

Exchange of pleadings

No text available.

23
Stage 2208/12/2022

Exchange of pleadings

This is a procedural entry recording the commencement of the hearing for Appeal-74/2022 before the Division Bench, noting the presence of the parties and counsel.

24
Stage 2314/11/2022

Exchange of pleadings

No text available.

25
Stage 2414/10/2022

Exchange of pleadings

No text available.

26
Stage 2512/09/2022

Exchange of pleadings

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the matter for hearing on 14.10.2022.

27
Stage 2611/08/2022

Hearing

The Tribunal scheduled the case for hearing on 12.09.2022 and directed the appellant's counsel to send the appeal via email.

28
Stage 2725/07/2022

Further Order

The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objections and directed the counsel to register on the e-portal for future cause list inclusion, scheduling the next hearing for 11.08.2022.

29
Stage 2813/05/2022

Further Order

The Tribunal permitted the appellant's husband to appear as a co-applicant and directed the respondent to file a reply within two weeks, with subsequent timelines set for replication and electronic filing.

30
Stage 2908/04/2022

Delay condonation

The Tribunal condoned a 130-day delay in filing the appeal due to the COVID-19 pandemic relaxation, registered the defective appeal as a Regular Appeal, and permitted co-allottee Mr. Suneel Kumar to attend future proceedings.

31
Stage 3029/03/2022

Delay condonation

The Tribunal adjourned the matter to 08.04.2022 and directed the applicant to file an affidavit of service regarding notice sent to the respondent.

32
Stage 3114/03/2022

Delay condonation

No text available.

33
Stage 3215/02/2022

Defect Removal

The Tribunal directed the appellant to rectify registry defects and issued notice to the respondent regarding an appeal that appears to have been filed beyond the limitation period.

34
Stage 33Interim Order

Tribunal Order #0901126002092022-08-04-2022

The Tribunal condoned a 130-day delay in filing the appeal due to the COVID-19 pandemic relaxation, registered the defective appeal as a Regular Appeal, and permitted co-allottee Mr. Suneel Kumar to attend future proceedings.

35
Stage 34Final Ruling Order

Tribunal Order #0901126002092022-09-07-2025

The Tribunal dismissed the appeal, ruling that the subsequent allottees' rights and possession timelines are governed by the fresh allotment agreement dated 07.05.2014 rather than the original agreement, thereby confirming the validity of the UPRERA rectification order.

36
Stage 35Interim Order

Tribunal Order #0901126002092022-12-03-2024

The Tribunal directed the appellant to re-upload all documents with proper descriptions and page numbers, and to coordinate with the Registry to delete undocumented annexures within one week.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal, ruling that the subsequent allottees' rights and possession timelines are governed by the fresh allotment agreement dated 07.05.2014 rather than the original agreement, thereby confirming the validity of the UPRERA rectification order. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1% per annum.

Disposal Winner: RespondentInterest Rate: MCLR + 1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal, ruling that the subsequent allottees' rights and possession timelines are governed by the fresh allotment agreement dated 07.05.2014 rather than the original agreement, thereby confirming the validity of the UPRERA rectification order.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1% per annum

Interest Period

w.e.f 07.11.2017 till obtaining of OC/CC by the promoter or till date of offer of possession, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 11(4)(d)Section 19(6)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Applicant/Appellant In-Person
  • Santosh Singh

Respondent Advocate(s)

  • Abhishek Shukla

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126002092022-08-04-2022

The Tribunal condoned a 130-day delay in filing the appeal due to the COVID-19 pandemic relaxation, registered the defective appeal as a Regular Appeal, and permitted co-allottee Mr. Suneel Kumar to attend future proceedings.

FINAL_ORDEROrder ID: 0901126002092022-09-07-2025

The Tribunal dismissed the appeal, ruling that the subsequent allottees' rights and possession timelines are governed by the fresh allotment agreement dated 07.05.2014 rather than the original agreement, thereby confirming the validity of the UPRERA rectification order.

INTERIM_ORDEROrder ID: 0901126002092022-12-03-2024

The Tribunal directed the appellant to re-upload all documents with proper descriptions and page numbers, and to coordinate with the Registry to delete undocumented annexures within one week.

TathyaGrid RERA Intelligence AI

Need to research all rulings for mr proview realtech private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →