up_reraStatus: Completed
CASE ID: 0901126002852019

Appellant / Complainant

Yogesh Kapoor

VS

Respondent

Gayatri Hospitality and Realcon Limited

Developer Firm

gayatri hospitality and realcon limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

40 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126002852019 by Yogesh Kapoor against Gayatri Hospitality and Realcon Limited before up_rera.

2
Stage 124/01/2024

Final Hearing

The appeal was dismissed for want of prosecution because the appellant's counsel failed to provide instructions or file a reply to the respondent's objections.

3
Stage 226/10/2023

Final Hearing

No text available.

4
Stage 314/09/2023

Final Hearing

The Tribunal adjourned the proceedings due to a call by the Bar Council of Uttar Pradesh for lawyers to abstain from judicial work, rescheduling the matter for 26.10.2023.

5
Stage 426/07/2023

Final Hearing

No text available.

6
Stage 519/05/2023

Final Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and allowed the appellant 10 days to file a reply to objections, scheduling the next hearing for 26.07.2023.

7
Stage 607/04/2023

Final Hearing

No text available.

8
Stage 727/02/2023

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and directed both parties to upload their respective pleadings into the digital folders within one week.

9
Stage 825/01/2023

Final Hearing

No text available.

10
Stage 919/12/2022

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to a conflicting hearing in the High Court and rescheduled the matter for 25.01.2023.

11
Stage 1025/11/2022

Final Hearing

The Tribunal adjourned the proceedings to 19.12.2022 due to the respondent's counsel's illness and directed the appellant's counsel to examine the recently uploaded audited balance sheet.

12
Stage 1119/11/2022

Hearing

The Tribunal has adjourned the matter and scheduled it for a subsequent hearing on 25.11.2022.

13
Stage 1216/11/2022

Hearing

The Tribunal granted the parties 24 hours to ensure compliance with a previous order and directed them to be prepared for a final hearing on 19.11.2022, noting that no further adjournments will be permitted.

14
Stage 1312/10/2022

Hearing

The Tribunal directed the appellant to submit bank statements proving fund transfers and ordered the respondent to file audited accounts regarding commission adjustments made to their agent, M/s Suprabhat Promoters and Associates.

15
Stage 1414/09/2022

Extension of Time

The Tribunal granted an adjournment requested by the respondent's counsel due to personal difficulties and rescheduled the hearing for 12.10.2022.

16
Stage 1530/08/2022

Final Hearing

The Tribunal granted the appellant a one-week extension to comply with a previous order dated 26.07.2022, warning of appropriate action if compliance is not met, and scheduled the matter for 14.09.2022.

17
Stage 1611/08/2022

Final Hearing

The Tribunal granted the appellant's counsel a one-week extension to ensure compliance with the previous order dated 26.07.2022 and scheduled the next hearing for 30.08.2022.

18
Stage 1726/07/2022

Final Hearing

The Tribunal directed the parties to place bank statements on record to verify disputed payment amounts and scheduled the appeal for a hearing on 11.08.2022.

19
Stage 1818/05/2022

Final Hearing

The Tribunal granted the appellant a final opportunity to file a replication/rejoinder and directed both parties to submit lists of dates and relied-upon judgments within 20 days.

20
Stage 1913/04/2022

Final Hearing

The Tribunal directed both parties to exchange and submit a list of dates, events, and relied-upon judgments within 20 days and scheduled the next hearing for May 17, 2022.

21
Stage 2024/02/2022

Final Hearing

The court granted an adjournment requested by the respondent's counsel and rescheduled the hearing for April 13, 2022.

22
Stage 2113/01/2022

Final Hearing

No text available.

23
Stage 2224/12/2021

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to his father's illness and rescheduled the hearing for 13.01.2022.

24
Stage 2308/12/2021

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to personal illness and scheduled the appeal for a final hearing on 24.12.2021.

25
Stage 2417/11/2021

Hearing

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the appeal for final hearing on 08.12.2021.

26
Stage 2524/09/2021

Hearing

The Tribunal issued a final opportunity to the respondent to pay the previously imposed cost of Rs. 2000/- within 10 days and directed the summoning of lower court records from the Regulatory Authority.

27
Stage 2607/09/2021

Hearing

The Tribunal granted the respondent a final opportunity to deposit previously imposed costs and directed the summoning of lower court records from the Regulatory Authority.

28
Stage 2730/04/2021

Hearing

No text available.

29
Stage 2805/04/2021

Hearing

No text available.

30
Stage 2916/03/2021

Hearing

The Tribunal granted the respondent a final one-week extension to file a reply to the grounds of appeal, subject to a cost of Rs. 2,000/- to be split between the appellant and the Tribunal fund.

31
Stage 3018/02/2021

Hearing

No text available.

32
Stage 3120/01/2021

Hearing on Appeal

The Tribunal remands the case back to the Regulatory Authority for a decision on its merits, finding that the previous dismissal based solely on the claim of pending NCLT proceedings was legally unsustainable.

33
Stage 3228/08/2020

Hearing on Appeal

No text available.

34
Stage 33Interim Order

Tribunal Order #0901126002852019-12-10-2022

The Tribunal directed the appellant to submit bank statements proving fund transfers and ordered the respondent to file audited accounts regarding commission adjustments made to their agent, M/s Suprabhat Promoters and Associates.

35
Stage 34Interim Order

Tribunal Order #0901126002852019-24-09-2021

The Tribunal issued a final opportunity to the respondent to pay the previously imposed cost of Rs. 2000/- within 10 days and directed the summoning of lower court records from the Regulatory Authority.

36
Stage 35Interim Order

Tribunal Order #0901126002852019-07-09-2021

The Tribunal granted the respondent a final opportunity to deposit previously imposed costs and directed the summoning of lower court records from the Regulatory Authority.

37
Stage 36Interim Order

Tribunal Order #0901126002852019-20-01-2021

The Tribunal remands the case back to the Regulatory Authority for a decision on its merits, finding that the previous dismissal based solely on the claim of pending NCLT proceedings was legally unsustainable.

38
Stage 37Interim Order

Tribunal Order #0901126002852019-26-07-2022

The Tribunal directed the parties to place bank statements on record to verify disputed payment amounts and scheduled the appeal for a hearing on 11.08.2022.

39
Stage 38Interim Order

Tribunal Order #0901126002852019-16-03-2021

The Tribunal granted the respondent a final one-week extension to file a reply to the grounds of appeal, subject to a cost of Rs. 2,000/- to be split between the appellant and the Tribunal fund.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare

Respondent Advocate(s)

  • Siddharth Nandwani

Official RERA Tribunal Orders (6)

INTERIM_ORDEROrder ID: 0901126002852019-12-10-2022

The Tribunal directed the appellant to submit bank statements proving fund transfers and ordered the respondent to file audited accounts regarding commission adjustments made to their agent, M/s Suprabhat Promoters and Associates.

INTERIM_ORDEROrder ID: 0901126002852019-24-09-2021

The Tribunal issued a final opportunity to the respondent to pay the previously imposed cost of Rs. 2000/- within 10 days and directed the summoning of lower court records from the Regulatory Authority.

INTERIM_ORDEROrder ID: 0901126002852019-07-09-2021

The Tribunal granted the respondent a final opportunity to deposit previously imposed costs and directed the summoning of lower court records from the Regulatory Authority.

INTERIM_ORDEROrder ID: 0901126002852019-20-01-2021

The Tribunal remands the case back to the Regulatory Authority for a decision on its merits, finding that the previous dismissal based solely on the claim of pending NCLT proceedings was legally unsustainable.

INTERIM_ORDEROrder ID: 0901126002852019-26-07-2022

The Tribunal directed the parties to place bank statements on record to verify disputed payment amounts and scheduled the appeal for a hearing on 11.08.2022.

INTERIM_ORDEROrder ID: 0901126002852019-16-03-2021

The Tribunal granted the respondent a final one-week extension to file a reply to the grounds of appeal, subject to a cost of Rs. 2,000/- to be split between the appellant and the Tribunal fund.

TathyaGrid RERA Intelligence AI

Need to research all rulings for gayatri hospitality and realcon limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →