Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

18 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126003052019 by Arvind Srivastava against Mittal Infratech Pvt. Ltd. before up_rera.

2
Stage 125/08/2022

Hearing

The appeal was dismissed as withdrawn following an amicable settlement reached between the appellant and the respondent.

3
Stage 229/07/2022

Hearing

No text available.

4
Stage 304/07/2022

Further Order

The Tribunal granted an adjournment to allow the parties to pursue an amicable settlement and scheduled the next hearing for July 29, 2022.

5
Stage 426/04/2022

Further Order

The Tribunal directed the parties to negotiate a settlement regarding possession and delay interest within 15 days and submit a settlement deed by the next hearing date.

6
Stage 516/03/2022

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal allowed the application for condonation of delay in filing the appeal, subject to a cost of Rs. 6,000, and directed the registry to register the defective appeal as a regular appeal.

7
Stage 615/11/2021

Further Order

The court noted that the case was mistakenly listed for hearing when it was actually reserved for an order on a limitation application.

8
Stage 722/09/2021

Delay condonation

The Tribunal heard arguments regarding the limitation application and scheduled the matter for an order on the point of limitation on 15.11.2021.

9
Stage 806/09/2021

Delay condonation

The Tribunal directed both parties to appear on the next scheduled date for the disposal of the pending limitation application.

10
Stage 930/04/2021

Delay condonation

No text available.

11
Stage 1005/04/2021

For Order

No text available.

12
Stage 1115/03/2021

Delay condonation

The Tribunal granted an adjournment requested by the counsel for the applicant and scheduled the case for hearing on the limitation application and its objections on 05.04.2021.

13
Stage 1217/02/2021

For Order

No text available.

14
Stage 1313/01/2021

Further Order

No text available.

15
Stage 1419/11/2020

Further Order

No text available.

16
Stage 15Interim Order

Tribunal Order #0901126003052019-16-03-2022

The U.P. Real Estate Appellate Tribunal allowed the application for condonation of delay in filing the appeal, subject to a cost of Rs. 6,000, and directed the registry to register the defective appeal as a regular appeal.

17
Stage 16Interim Order

Tribunal Order #0901126003052019-26-04-2022

The Tribunal directed the parties to negotiate a settlement regarding possession and delay interest within 15 days and submit a settlement deed by the next hearing date.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as withdrawn Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as withdrawn

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Syed Zulfiqar Naqvi

Respondent Advocate(s)

  • Siddharth Nandwani

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126003052019-16-03-2022

The U.P. Real Estate Appellate Tribunal allowed the application for condonation of delay in filing the appeal, subject to a cost of Rs. 6,000, and directed the registry to register the defective appeal as a regular appeal.

INTERIM_ORDEROrder ID: 0901126003052019-26-04-2022

The Tribunal directed the parties to negotiate a settlement regarding possession and delay interest within 15 days and submit a settlement deed by the next hearing date.

TathyaGrid RERA Intelligence AI

Need to research all rulings for mittal infratech pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →