Appellant / Complainant
Gunajan Sharma
Respondent
U.P. Township Infrastructure Pvt. Ltd.
u.p. township infrastructure pvt. ltd.
₹50,59,881
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126003472019 by Gunajan Sharma against U.P. Township Infrastructure Pvt. Ltd. before up_rera.
Final Hearing
The Tribunal permitted the appellant to withdraw the case following the respondent's payment of Rs. 50,59,881/- and interest, while reserving the applicant's right to seek corrections for any mathematical errors in interest calculation.
Final Hearing
The Tribunal recorded the appellant's agreement to a settlement proposal where the respondent will refund the amount based on SBI's MCLR plus 1% via RTGS, subject to TDS and 15% cancellation charges, with the appellant undertaking to withdraw the appeal upon receipt.
Hearing
The respondent offered to refund the applicant's deposit minus a 15% deduction with interest at MCLR+1%, and the matter is adjourned to allow the appellant to discuss this proposal.
Hearing
The Tribunal granted a request for adjournment and rescheduled the matter to 25.11.2021, directing that the CEO/MD/Director of the respondent must appear at the next hearing.
Hearing
The Tribunal directed the CEO/MD/Director of the respondent builder-company to appear in person following a dispute regarding the refund amount for an allotted unit that has already been sold.
Hearing
The Tribunal noted the respondent's offer to refund the applicant's deposit without interest and directed the authorized representatives of both parties to appear at the next hearing on 28.09.2021.
For Order
The Tribunal directed the parties to exchange settlement terms via email and ordered the respondent to appear through an authorized representative empowered to finalize a settlement at the next hearing.
For Order
The case was adjourned to 15.03.2021 following arguments regarding a potential settlement where the respondent expressed readiness to refund the amount deposited by the applicant.
Tribunal Order #0901126003472019-08-12-2021
The Tribunal permitted the appellant to withdraw the case following the respondent's payment of Rs. 50,59,881/- and interest, while reserving the applicant's right to seek corrections for any mathematical errors in interest calculation.
Tribunal Order #0901126003472019-07-12-2021
The Tribunal recorded the appellant's agreement to a settlement proposal where the respondent will refund the amount based on SBI's MCLR plus 1% via RTGS, subject to TDS and 15% cancellation charges, with the appellant undertaking to withdraw the appeal upon receipt.
Tribunal Order #0901126003472019-25-11-2021
The respondent offered to refund the applicant's deposit minus a 15% deduction with interest at MCLR+1%, and the matter is adjourned to allow the appellant to discuss this proposal.
Tribunal Order #0901126003472019-28-09-2021
The Tribunal directed the CEO/MD/Director of the respondent builder-company to appear in person following a dispute regarding the refund amount for an allotted unit that has already been sold.
Tribunal Disposal & Final Award Ruling
The Tribunal permitted the appellant to withdraw the case following the respondent's payment of Rs. 50,59,881/- and interest, while reserving the applicant's right to seek corrections for any mathematical errors in interest calculation. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal permitted the appellant to withdraw the case following the respondent's payment of Rs. 50,59,881/- and interest, while reserving the applicant's right to seek corrections for any mathematical errors in interest calculation.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rudra Kumar Tiwari
Respondent Advocate(s)
- D.N. Verma
- Samrat Vaish
Official RERA Tribunal Orders (4)
The Tribunal permitted the appellant to withdraw the case following the respondent's payment of Rs. 50,59,881/- and interest, while reserving the applicant's right to seek corrections for any mathematical errors in interest calculation.
The Tribunal recorded the appellant's agreement to a settlement proposal where the respondent will refund the amount based on SBI's MCLR plus 1% via RTGS, subject to TDS and 15% cancellation charges, with the appellant undertaking to withdraw the appeal upon receipt.
The respondent offered to refund the applicant's deposit minus a 15% deduction with interest at MCLR+1%, and the matter is adjourned to allow the appellant to discuss this proposal.
The Tribunal directed the CEO/MD/Director of the respondent builder-company to appear in person following a dispute regarding the refund amount for an allotted unit that has already been sold.
Need to research all rulings for u.p. township infrastructure pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.