up_reraStatus: Completed
CASE ID: 0901126003982020

Appellant / Complainant

Nitasha Mehta

VS

Respondent

Jai Prakash Associates Limited

Developer Firm

jai prakash associates limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

20 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126003982020 by Nitasha Mehta against Jai Prakash Associates Limited before up_rera.

2
Stage 114/09/2022

Hearing

The Tribunal permitted the appellant to withdraw the appeal as 'not pressed,' following the appellant's decision to move an application before RERA to commence proceedings that were previously held in abeyance.

3
Stage 206/09/2022

Hearing

The Tribunal notes that since the High Court has stayed the land cancellation, RERA is now proceeding with the matters; the appellant is advised to move an application for revival of proceedings before RERA.

4
Stage 305/08/2022

Hearing

This is a formal record of appearance for the parties in Appeal-821/2020, noting the presence of counsel for both the appellant and the respondent on August 5, 2022.

5
Stage 426/07/2022

Hearing

The Tribunal adjourned the matter and rescheduled the appeal for hearing on 05.08.2022.

6
Stage 521/07/2022

Hearing

The Tribunal granted a request from the appellant's counsel to reschedule the hearing of Appeal-821/2020 to 26.07.2022.

7
Stage 630/05/2022

Hearing

No text available.

8
Stage 720/12/2021

Final Hearing

No text available.

9
Stage 826/11/2021

Final Hearing

No text available.

10
Stage 908/11/2021

Delay condonation

The Tribunal corrected a procedural error by converting the defective appeal into a Regular Appeal after finding that it had been filed within the prescribed time limit.

11
Stage 1006/10/2021

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel due to his unavailability and scheduled the matter for 08.11.2021 to consider the application for condonation of delay.

12
Stage 1120/04/2021

Delay condonation

No text available.

13
Stage 1226/03/2021

For Order

No text available.

14
Stage 1304/03/2021

For Order

The Tribunal granted a two-week extension for the respondent to file objections to the condonation of delay application and grounds of appeal, noting their failure to appear despite notice.

15
Stage 1411/02/2021

For Order

No text available.

16
Stage 1520/01/2021

Defect Removal

No text available.

17
Stage 1626/11/2020

Admission

No text available.

18
Stage 17Interim Order

Tribunal Order #0901126003982020-06-09-2022

The Tribunal notes that since the High Court has stayed the land cancellation, RERA is now proceeding with the matters; the appellant is advised to move an application for revival of proceedings before RERA.

19
Stage 18Interim Order

Tribunal Order #0901126003982020-08-11-2021

The Tribunal corrected a procedural error by converting the defective appeal into a Regular Appeal after finding that it had been filed within the prescribed time limit.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as not pressed Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as not pressed

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anuuj Taandon
  • Poornendra Kumar Awasthi

Respondent Advocate(s)

  • Altaf Mansoor

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126003982020-06-09-2022

The Tribunal notes that since the High Court has stayed the land cancellation, RERA is now proceeding with the matters; the appellant is advised to move an application for revival of proceedings before RERA.

INTERIM_ORDEROrder ID: 0901126003982020-08-11-2021

The Tribunal corrected a procedural error by converting the defective appeal into a Regular Appeal after finding that it had been filed within the prescribed time limit.

TathyaGrid RERA Intelligence AI

Need to research all rulings for jai prakash associates limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →