up_reraStatus: Completed
CASE ID: 0901126005562021

Appellant / Complainant

Nitin Srivastava

VS

Respondent

Sikka Infrastructure Private Limited

Developer Firm

sikka infrastructure private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126005562021 by Nitin Srivastava against Sikka Infrastructure Private Limited before up_rera.

Delay in PossessionDelay Compensation / InterestNon-Compliance & Execution
2
Stage 127/10/2021

Hearing

The Appellant withdrew the appeal because the Respondent failed to comply with previous RERA directions regarding alternative unit provision, allowing the Appellant to instead proceed with the execution of interest payments as per direction no. 5 of the original order.

3
Stage 227/09/2021

Hearing

The Tribunal granted the respondent one week to file objections to the application for condonation of delay and the grounds of appeal, directing parties to upload pleadings on the e-portal before the next hearing on 27.10.2021.

4
Stage 313/04/2021

Hearing

No text available.

5
Stage 423/03/2021

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the appeal and directed the appellant to file a reply within one week thereafter, scheduling the next hearing for April 13, 2021.

6
Stage 502/03/2021

For Order

The Tribunal adjourned the defective appeal due to a lawyers' strike called by the Oudh Bar Association and rescheduled the matter for 23.03.2021.

7
Stage 603/02/2021

For Order

The Tribunal converted the defective appeal into a regular appeal and directed the issuance of notice to the respondent, setting a timeline for the exchange of pleadings via email and the e-portal.

8
Stage 725/01/2021

Defect Removal

No text available.

9
Stage 8Final Ruling Order

Tribunal Order #0901126005562021-27-10-2021

The Appellant withdrew the appeal because the Respondent failed to comply with previous RERA directions regarding alternative unit provision, allowing the Appellant to instead proceed with the execution of interest payments as per direction no. 5 of the original order.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellant withdrew the appeal because the Respondent failed to comply with previous RERA directions regarding alternative unit provision, allowing the Appellant to instead proceed with the execution of interest payments as per direction no. 5 of the original order. Awarded in favor of Respondent. Awarded interest rate: Rs. 5/- per sq. feet per month and MCLR+1%.

Disposal Winner: RespondentInterest Rate: Rs. 5/- per sq. feet per month and MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellant withdrew the appeal because the Respondent failed to comply with previous RERA directions regarding alternative unit provision, allowing the Appellant to instead proceed with the execution of interest payments as per direction no. 5 of the original order.

Ruling Awarded To

Respondent

Awarded Interest Rate

Rs. 5/- per sq. feet per month and MCLR+1%

Interest Period

from 03.12.2015 to 30.04.2016 and from 01.05.2016 till CC/OC received

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Shishir Srivastava

Respondent Advocate(s)

  • Sunendra Kumar

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126005562021-27-10-2021

The Appellant withdrew the appeal because the Respondent failed to comply with previous RERA directions regarding alternative unit provision, allowing the Appellant to instead proceed with the execution of interest payments as per direction no. 5 of the original order.

TathyaGrid RERA Intelligence AI

Need to research all rulings for sikka infrastructure private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →