up_reraStatus: Completed
CASE ID: 0901126005772022

Appellant / Complainant

Chail Bihari Saxena

VS

Respondent

Aftek Developers Private Limited, U.P. Real Estate Regulatory Authority, Mohd. Arif Farooquia

Developer Firm

aftek developers private limited

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferStructural Defects & QualityPromotional MisrepresentationNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

25 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126005772022 by Chail Bihari Saxena against Aftek Developers Private Limited, U.P. Real Estate Regulatory Authority, Mohd. Arif Farooquia before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferStructural Defects & QualityPromotional MisrepresentationNon-Compliance & Execution
2
Stage 102/04/2024

Hearing

The Tribunal set aside the rejection of execution proceedings, ruling that a legal offer of possession cannot be made without an Occupancy Certificate (OC/CC) and remanded the matter back to the Regulatory Authority for fresh processing.

3
Stage 205/03/2024

Hearing

Upon the joint request of the counsels for both parties, the Tribunal has adjourned the appeal and scheduled it for a hearing on 02.04.2024.

4
Stage 307/02/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the hearing for March 5, 2024.

5
Stage 418/01/2024

Hearing

The Tribunal directed the appellant to rectify procedural defects by serially numbering annexures with descriptions and filing a fresh folder of documents due to repeated uploads of a single document. The matter is listed for hearing on 07.02.2024.

6
Stage 516/10/2023

Hearing

No text available.

7
Stage 606/09/2023

Hearing

The Tribunal adjourned the proceedings due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh and rescheduled the hearing for 16.10.2023.

8
Stage 718/08/2023

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to a High Court engagement and scheduled the next hearing for 06.09.2023, noting that no further adjournments will be permitted.

9
Stage 820/07/2023

Hearing

The Tribunal scheduled the appeal for a hearing on 18.08.2023 and directed that no further adjournments will be granted, noting that the case may be decided based on available records if parties fail to appear.

10
Stage 909/05/2023

Hearing

No text available.

11
Stage 1028/03/2023

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to a bereavement in the family and rescheduled the matter for hearing on 09.05.2023.

12
Stage 1117/02/2023

Exchange of pleadings

The Tribunal noted that pleadings have been exchanged and the case is ripe for hearing, subsequently scheduling the matter for orders/hearing on 28.03.2023.

13
Stage 1217/01/2023

Exchange of pleadings

No text available.

14
Stage 1308/12/2022

Exchange of pleadings

The U.P. Real Estate Appellate Tribunal has adjourned Appeal-112/2022 and scheduled the matter for a further order on January 17, 2023.

15
Stage 1414/11/2022

Exchange of pleadings

No text available.

16
Stage 1514/10/2022

Exchange of pleadings

No text available.

17
Stage 1612/09/2022

Exchange of pleadings

The Tribunal directed the appellant to file a replication/rejoinder against the respondent's reply and scheduled the case for hearing on 14.10.2022.

18
Stage 1711/08/2022

Exchange of pleadings

This is a procedural entry recording that the case was called for hearing on August 11, 2022, with counsel present.

19
Stage 1804/07/2022

Hearing

The Tribunal granted the respondent a final opportunity to file a reply against the grounds of appeal and directed them to serve a copy to the appellant via email. The case is scheduled for hearing on 11.08.2022.

20
Stage 1926/04/2022

Hearing

The Tribunal directed the respondent to file a reply to the memo of appeal within 20 days and allowed the appellant the opportunity to file a replication thereafter.

21
Stage 2015/03/2022

Hearing on Appeal

The Tribunal noted the respondent's appearance and counsel's intent to file a reply to the grounds of appeal, adjourning the matter to 26.04.2022.

22
Stage 2121/02/2022

Hearing on Appeal

The Tribunal issued a notice to the respondent and directed the appellant to serve the notice and appeal documents via speed-post and email, with the matter listed for 15.03.2022.

23
Stage 22Final Ruling Order

Tribunal Order #0901126005772022-02-04-2024

The Tribunal set aside the rejection of execution proceedings, ruling that a legal offer of possession cannot be made without an Occupancy Certificate (OC/CC) and remanded the matter back to the Regulatory Authority for fresh processing.

24
Stage 23Interim Order

Tribunal Order #0901126005772022-18-01-2024

The Tribunal directed the appellant to rectify procedural defects by serially numbering annexures with descriptions and filing a fresh folder of documents due to repeated uploads of a single document. The matter is listed for hearing on 07.02.2024.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the rejection of execution proceedings, ruling that a legal offer of possession cannot be made without an Occupancy Certificate (OC/CC) and remanded the matter back to the Regulatory Authority for fresh processing. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the rejection of execution proceedings, ruling that a legal offer of possession cannot be made without an Occupancy Certificate (OC/CC) and remanded the matter back to the Regulatory Authority for fresh processing.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.11.2016 till actual physical possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 14(3)Section 12Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Applicant/Appellant In-Person

Respondent Advocate(s)

  • Anurag Singh

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126005772022-02-04-2024

The Tribunal set aside the rejection of execution proceedings, ruling that a legal offer of possession cannot be made without an Occupancy Certificate (OC/CC) and remanded the matter back to the Regulatory Authority for fresh processing.

INTERIM_ORDEROrder ID: 0901126005772022-18-01-2024

The Tribunal directed the appellant to rectify procedural defects by serially numbering annexures with descriptions and filing a fresh folder of documents due to repeated uploads of a single document. The matter is listed for hearing on 07.02.2024.

TathyaGrid RERA Intelligence AI

Need to research all rulings for aftek developers private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →