Appellant / Complainant
Syed Mohd Husain
Respondent
Nirala Project Private Limited
nirala project private limited
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126007932020 by Syed Mohd Husain against Nirala Project Private Limited before up_rera.
Final Hearing
The Tribunal disposed of the appeal after the appellant declined to press it, directing the appellant to file an execution application before the Regulatory Authority for the implementation of the order dated 07.09.2020.
Final Hearing
The Tribunal granted the appellant's counsel 10 days to prepare briefs and file documents, directing all parties to upload pleadings to the e-portal and scheduling the next hearing for January 27, 2022.
Final Hearing
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the next hearing for January 4, 2022.
Final Hearing
The Tribunal granted the respondent three days to file objections to the appeal and directed the parties to exchange replies via email and upload documents to the e-portal before the next hearing on 16.12.2021.
Hearing
The Tribunal condoned the delay in filing the appeal to ensure the appellant did not suffer due to counsel's error and directed the Registry to convert the defective appeal into a regular appeal.
Hearing
The Tribunal directed the respondent to file the Occupancy Certificate (OC) or Completion Certificate (CC) of the project and ordered the respondent's counsel to file their Vakalatnama within one week.
Delay condonation
The Tribunal directed the respondent to file a vakalatnama, required documents on the e-portal, and submit objections to the condonation of delay application within 15 days.
Notice
The appeal was adjourned due to a lawyers' strike called by the Oudh Bar Association and is scheduled for a new hearing on 23.03.2021.
Hearing
The Tribunal directed the appellant to take fresh steps for service on the respondent and provided a timeline for exchanging documents related to the application for condonation of delay and the memo of appeal.
Tribunal Order #0901126007932020-12-11-2021
The Tribunal condoned the delay in filing the appeal to ensure the appellant did not suffer due to counsel's error and directed the Registry to convert the defective appeal into a regular appeal.
Tribunal Order #0901126007932020-09-03-2022
The Tribunal disposed of the appeal after the appellant declined to press it, directing the appellant to file an execution application before the Regulatory Authority for the implementation of the order dated 07.09.2020.
Tribunal Order #0901126007932020-22-09-2021
The Tribunal directed the respondent to file the Occupancy Certificate (OC) or Completion Certificate (CC) of the project and ordered the respondent's counsel to file their Vakalatnama within one week.
Tribunal Disposal & Final Award Ruling
The Tribunal disposed of the appeal after the appellant declined to press it, directing the appellant to file an execution application before the Regulatory Authority for the implementation of the order dated 07.09.2020. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal disposed of the appeal after the appellant declined to press it, directing the appellant to file an execution application before the Regulatory Authority for the implementation of the order dated 07.09.2020.
Ruling Awarded To
Appellant
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Dhananjay Srivastava
Respondent Advocate(s)
- Suyash Gupta
Official RERA Tribunal Orders (3)
The Tribunal condoned the delay in filing the appeal to ensure the appellant did not suffer due to counsel's error and directed the Registry to convert the defective appeal into a regular appeal.
The Tribunal disposed of the appeal after the appellant declined to press it, directing the appellant to file an execution application before the Regulatory Authority for the implementation of the order dated 07.09.2020.
The Tribunal directed the respondent to file the Occupancy Certificate (OC) or Completion Certificate (CC) of the project and ordered the respondent's counsel to file their Vakalatnama within one week.
Need to research all rulings for nirala project private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.