up_reraStatus: Completed
CASE ID: 0901126008072020

Appellant / Complainant

Pradeep Sharma

VS

Respondent

Tyagi Construction Company

Developer Firm

tyagi construction company

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

19 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126008072020 by Pradeep Sharma against Tyagi Construction Company before up_rera.

2
Stage 112/04/2022

to file objections and its reply

The U.P. Real Estate Appellate Tribunal dismissed Appeal-537/2020 by reference to a prior order dated 12.04.2022 passed in a related matter (Appeal No. 526/2020).

3
Stage 222/03/2022

to file objections and its reply

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and rescheduled the appeal hearing for 12.04.2022.

4
Stage 304/03/2022

Further Order

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the next hearing for March 22, 2022.

5
Stage 421/01/2022

Exchange of pleadings

No text available.

6
Stage 509/12/2021

Further Order

No text available.

7
Stage 611/11/2021

Further Order

No text available.

8
Stage 728/10/2021

Further Order

The Tribunal granted an adjournment requested by the respondent and directed both the applicant and the respondent's partner, Mr. Vijay Kumar Tyagi, to appear in person on 26.11.2021 to attempt an amicable settlement.

9
Stage 804/10/2021

Hearing

The Tribunal directed the parties to attempt an out-of-court settlement regarding the dispute over unpaid amounts and scheduled the matter for further orders on 28.10.2021.

10
Stage 909/09/2021

Hearing

The Tribunal noted a submitted compromise application but recorded the appellant's allegation that his signatures and photograph on the settlement papers were forged; the matter is listed for 29.09.2021 for further orders.

11
Stage 1005/05/2021

Hearing

No text available.

12
Stage 1108/04/2021

Hearing

No text available.

13
Stage 1212/03/2021

Further Order

The Tribunal granted an adjournment request from the appellant's counsel due to her being out of station and rescheduled the hearing for 08.04.2021.

14
Stage 1311/02/2021

Further Hearing

The Tribunal noted the respondent's claim of a settlement between the parties and, following the appellant's request for verification, adjourned the matter to 12.03.2021.

15
Stage 1406/01/2021

Further Order

No text available.

16
Stage 1525/11/2020

Further Order

No text available.

17
Stage 16Final Ruling Order

Tribunal Order #0901126008072020-12-04-2022

The U.P. Real Estate Appellate Tribunal dismissed Appeal-537/2020 by reference to a prior order dated 12.04.2022 passed in a related matter (Appeal No. 526/2020).

18
Stage 17Interim Order

Tribunal Order #0901126008072020-09-09-2021

The Tribunal noted a submitted compromise application but recorded the appellant's allegation that his signatures and photograph on the settlement papers were forged; the matter is listed for 29.09.2021 for further orders.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed Appeal-537/2020 by reference to a prior order dated 12.04.2022 passed in a related matter (Appeal No. 526/2020). Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed Appeal-537/2020 by reference to a prior order dated 12.04.2022 passed in a related matter (Appeal No. 526/2020).

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Fuhar Gupta
  • Prashant Kumar Singh

Respondent Advocate(s)

  • Sanjay Kumar Srivastava

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126008072020-12-04-2022

The U.P. Real Estate Appellate Tribunal dismissed Appeal-537/2020 by reference to a prior order dated 12.04.2022 passed in a related matter (Appeal No. 526/2020).

INTERIM_ORDEROrder ID: 0901126008072020-09-09-2021

The Tribunal noted a submitted compromise application but recorded the appellant's allegation that his signatures and photograph on the settlement papers were forged; the matter is listed for 29.09.2021 for further orders.

TathyaGrid RERA Intelligence AI

Need to research all rulings for tyagi construction company?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →