Appellant / Complainant
Jss Buildcon Private Limited
Respondent
Rupali Sethi
jss buildcon private limited
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126008142023 by Jss Buildcon Private Limited against Rupali Sethi before up_rera.
Delay condonation
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed the appeal due to a failure to provide sufficient cause for the 263-day delay.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 30.07.2025, noting that no further adjournments will be permitted.
Delay condonation
The Tribunal granted the appellant ten days to file a rejoinder affidavit and scheduled the next hearing for July 9, 2025.
Delay condonation
The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the matter for hearing on May 14, 2025.
Delay condonation
The Tribunal granted the appellant one week to file a rejoinder and scheduled the hearing for April 22, 2025, to consider the application for condonation of delay.
Delay condonation
The Tribunal granted the appellant 10 days to file a rejoinder affidavit to the respondent's objections and scheduled the next hearing for March 26, 2025.
Delay condonation
The Tribunal granted a request to list the appeal for orders/hearing on 03.03.2025 and directed the parties to exchange pleadings in the interim.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with a subsequent one-week window for the appellant to reply.
Delay condonation
The Tribunal adjourned the appeal to 09.01.2025 and granted the respondent 10 days to file objections, with the appellant permitted to reply within one week thereafter.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for a hearing on 27.11.2024.
Delay condonation
The Tribunal noted that the respondent has received Rs. 6,83,256/- through RERA and no longer objects to compliance with Section 43(5) of the Act; the respondent is granted 10 days to file objections against the appeal.
Delay condonation
The Tribunal granted the appellant 10 days to file documents proving that recovered funds have been deposited with RERA and scheduled the matter for orders on 12.09.2024.
Delay condonation
The Tribunal granted the appellant a final opportunity to comply with its previous order dated 21.02.2024 by filing the High Court order and proof of payment for Rs 6,83,256/- within one week.
Delay condonation
The Tribunal noted the absence of both parties and rescheduled the appeal for hearing/orders to 25.07.2024.
Delay condonation
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the defective appeal for orders or hearing on May 27, 2024.
Delay condonation
The Tribunal noted the illness of the appellant's counsel and ordered the defective appeal to be listed for orders or hearing on 26.04.2024.
Delay condonation
The Tribunal addressed objections regarding incomplete compliance with Section 43(5) of the Act, noting that a sum of Rs 6,83,256/- was adjusted following High Court directions, and granted the appellant two days to file supporting documentation.
Delay condonation
The Tribunal granted the appellant one week to file a reply to the respondent's objections regarding the application for condonation of delay and scheduled the matter for hearing on 21.02.2024.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with the matter scheduled for hearing on July 10, 2023.
Defect Removal
The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and directed the parties to follow specific service procedures before the next hearing on 28.04.2023.
Tribunal Order #0901126008142023-30-07-2025
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed the appeal due to a failure to provide sufficient cause for the 263-day delay.
Tribunal Order #0901126008142023-12-09-2024
The Tribunal noted that the respondent has received Rs. 6,83,256/- through RERA and no longer objects to compliance with Section 43(5) of the Act; the respondent is granted 10 days to file objections against the appeal.
Tribunal Order #0901126008142023-25-07-2024
The Tribunal granted the appellant a final opportunity to comply with its previous order dated 21.02.2024 by filing the High Court order and proof of payment for Rs 6,83,256/- within one week.
Tribunal Order #0901126008142023-21-02-2024
The Tribunal addressed objections regarding incomplete compliance with Section 43(5) of the Act, noting that a sum of Rs 6,83,256/- was adjusted following High Court directions, and granted the appellant two days to file supporting documentation.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed the appeal due to a failure to provide sufficient cause for the 263-day delay. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed the appeal due to a failure to provide sufficient cause for the 263-day delay.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Anurag Singh
Respondent Advocate(s)
- Mandeep Singh
- Rohit Jaiswal
- Jayant Gupta
- Anjali Singh
Official RERA Tribunal Orders (4)
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed the appeal due to a failure to provide sufficient cause for the 263-day delay.
The Tribunal noted that the respondent has received Rs. 6,83,256/- through RERA and no longer objects to compliance with Section 43(5) of the Act; the respondent is granted 10 days to file objections against the appeal.
The Tribunal granted the appellant a final opportunity to comply with its previous order dated 21.02.2024 by filing the High Court order and proof of payment for Rs 6,83,256/- within one week.
The Tribunal addressed objections regarding incomplete compliance with Section 43(5) of the Act, noting that a sum of Rs 6,83,256/- was adjusted following High Court directions, and granted the appellant two days to file supporting documentation.
Need to research all rulings for jss buildcon private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.