Appellant / Complainant
Ranjeet Prasad
Respondent
Hawelia Builders Pvt. Ltd
hawelia builders pvt. ltd
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126008672021 by Ranjeet Prasad against Hawelia Builders Pvt. Ltd before up_rera.
Hearing
The appeal was dismissed as not pressed following the appellant's submission that the dispute had been resolved amicably and possession had been taken.
Hearing
Upon the joint request of the learned counsel for both parties, the appeal has been adjourned and rescheduled for hearing on 18.08.2023.
Hearing
The Tribunal granted a request for adjournment from the respondent's counsel and scheduled the appeal for hearing on 10.08.2023, while maintaining any existing interim orders.
Hearing
The Tribunal granted a one-week extension to the counsel for U.P. RERA to review the appellant's execution application and scheduled the matter for hearing on 30.05.2023.
Hearing
The Tribunal ordered the appeal to be listed alongside similar matters challenging orders passed under Section 63 of the Act, 2016, on April 19, 2023.
Part Heard
The Tribunal granted a request for adjournment made by the appellant's counsel and rescheduled the hearing of the appeal to 15.03.2023 with the consent of both parties.
Part Heard
The Tribunal adjourned the matter due to lack of time and scheduled the appeal for further orders on 17.01.2023.
Part Heard
The Tribunal directed both parties to exchange interest calculations based on a settlement framework where the temporary OC date serves as the cutoff and interest is payable for the delay period between possession and appeal filing.
Part Heard
The Tribunal granted an adjournment following a request from the respondent's counsel and rescheduled the matter for 18.10.2022, noting potential settlement between the parties.
For Order
The parties expressed an intent to settle the dispute, with the appellant proposing that the Temporary Occupancy Certificate (TOC) date serve as the cutoff for interest calculations. The Tribunal directed both parties to appear on the next scheduled date of 14.09.2022.
For Order
The court adjourned the case upon a joint request from the counsels of both parties and scheduled the matter for hearing on 30.08.2022.
Hearing
The Tribunal adjourned the appeal to 22.08.2022 to allow counsel for both parties time to prepare arguments.
Hearing
The Tribunal noted the filing of an objection by the Regulatory Authority and, upon joint request from both parties' counsel, adjourned the matter to 12.07.2022.
For Order
The Tribunal granted UP RERA one week to file its response and directed all parties to exchange responses via email and upload them to the e-portal before the next hearing on 27.04.2022.
For Order
The Tribunal directs the Secretary of U.P. RERA to explain the legal provisions under which they modified a previous order and mandates that a response be filed within 10 days.
to file objections and its reply
The Tribunal issued a notice to U.P. RERA to explain the legal basis upon which the Regulatory Authority modified an original order dated 28.02.2020, questioning whether such action exceeded its jurisdiction under Section 63.
Hearing
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the appeal for hearing on January 20, 2022.
Hearing
The Tribunal granted the respondent two weeks to file a Vakalatnama and objections to the grounds of appeal, with subsequent timelines set for replies and document filing.
Hearing
The Tribunal directed the Registry to verify and upload the affidavit of service and scheduled the appeal for hearing on 09.12.2021.
Hearing
The Tribunal granted the appellant one week to file an affidavit of service and rescheduled the appeal hearing to 23.11.2021.
Hearing on Appeal
The Tribunal issued a notice to the respondent and directed the appellant to serve the memo of appeal via speed post and email, setting a timeline for filing objections and replies.
Defect Removal
The Tribunal ordered that Appeal-119/2021 be listed alongside defective appeal no. 445/2020 on 19.02.2021.
Defect Removal
The Tribunal granted the appellant's counsel one week to file a supplementary affidavit clarifying the appellant's financial liabilities and expenses related to the execution of the conveyance deed, with the matter listed for 17.02.2021.
Tribunal Order #0901126008672021-10-03-2022
The Tribunal issued a notice to U.P. RERA to explain the legal basis upon which the Regulatory Authority modified an original order dated 28.02.2020, questioning whether such action exceeded its jurisdiction under Section 63.
Tribunal Order #0901126008672021-20-09-2023
The appeal was dismissed as not pressed following the appellant's submission that the dispute had been resolved amicably and possession had been taken.
Tribunal Order #0901126008672021-18-10-2022
The Tribunal directed both parties to exchange interest calculations based on a settlement framework where the temporary OC date serves as the cutoff and interest is payable for the delay period between possession and appeal filing.
Tribunal Order #0901126008672021-30-08-2022
The parties expressed an intent to settle the dispute, with the appellant proposing that the Temporary Occupancy Certificate (TOC) date serve as the cutoff for interest calculations. The Tribunal directed both parties to appear on the next scheduled date of 14.09.2022.
Tribunal Order #0901126008672021-29-03-2022
The Tribunal directs the Secretary of U.P. RERA to explain the legal provisions under which they modified a previous order and mandates that a response be filed within 10 days.
Tribunal Disposal & Final Award Ruling
The appeal was dismissed as not pressed following the appellant's submission that the dispute had been resolved amicably and possession had been taken. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The appeal was dismissed as not pressed following the appellant's submission that the dispute had been resolved amicably and possession had been taken.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Nirmit Srivastava
Respondent Advocate(s)
- Shobhit Mohan Shukla
- Yash Tandon
- Tushar Bahadur
Official RERA Tribunal Orders (5)
The Tribunal issued a notice to U.P. RERA to explain the legal basis upon which the Regulatory Authority modified an original order dated 28.02.2020, questioning whether such action exceeded its jurisdiction under Section 63.
The appeal was dismissed as not pressed following the appellant's submission that the dispute had been resolved amicably and possession had been taken.
The Tribunal directed both parties to exchange interest calculations based on a settlement framework where the temporary OC date serves as the cutoff and interest is payable for the delay period between possession and appeal filing.
The parties expressed an intent to settle the dispute, with the appellant proposing that the Temporary Occupancy Certificate (TOC) date serve as the cutoff for interest calculations. The Tribunal directed both parties to appear on the next scheduled date of 14.09.2022.
The Tribunal directs the Secretary of U.P. RERA to explain the legal provisions under which they modified a previous order and mandates that a response be filed within 10 days.
Need to research all rulings for hawelia builders pvt. ltd?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.