up_reraStatus: Completed
CASE ID: 0901126008672021

Appellant / Complainant

Ranjeet Prasad

VS

Respondent

Hawelia Builders Pvt. Ltd

Developer Firm

hawelia builders pvt. ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in Possession

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

35 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126008672021 by Ranjeet Prasad against Hawelia Builders Pvt. Ltd before up_rera.

Delay in Possession
2
Stage 120/09/2023

Hearing

The appeal was dismissed as not pressed following the appellant's submission that the dispute had been resolved amicably and possession had been taken.

3
Stage 210/08/2023

Hearing

Upon the joint request of the learned counsel for both parties, the appeal has been adjourned and rescheduled for hearing on 18.08.2023.

4
Stage 330/05/2023

Hearing

The Tribunal granted a request for adjournment from the respondent's counsel and scheduled the appeal for hearing on 10.08.2023, while maintaining any existing interim orders.

5
Stage 419/04/2023

Hearing

The Tribunal granted a one-week extension to the counsel for U.P. RERA to review the appellant's execution application and scheduled the matter for hearing on 30.05.2023.

6
Stage 515/03/2023

Hearing

The Tribunal ordered the appeal to be listed alongside similar matters challenging orders passed under Section 63 of the Act, 2016, on April 19, 2023.

7
Stage 617/02/2023

Part Heard

The Tribunal granted a request for adjournment made by the appellant's counsel and rescheduled the hearing of the appeal to 15.03.2023 with the consent of both parties.

8
Stage 717/01/2023

Part Heard

No text available.

9
Stage 808/12/2022

Part Heard

The Tribunal adjourned the matter due to lack of time and scheduled the appeal for further orders on 17.01.2023.

10
Stage 914/11/2022

Part Heard

No text available.

11
Stage 1018/10/2022

Part Heard

The Tribunal directed both parties to exchange interest calculations based on a settlement framework where the temporary OC date serves as the cutoff and interest is payable for the delay period between possession and appeal filing.

12
Stage 1114/09/2022

Part Heard

The Tribunal granted an adjournment following a request from the respondent's counsel and rescheduled the matter for 18.10.2022, noting potential settlement between the parties.

13
Stage 1230/08/2022

For Order

The parties expressed an intent to settle the dispute, with the appellant proposing that the Temporary Occupancy Certificate (TOC) date serve as the cutoff for interest calculations. The Tribunal directed both parties to appear on the next scheduled date of 14.09.2022.

14
Stage 1322/08/2022

For Order

The court adjourned the case upon a joint request from the counsels of both parties and scheduled the matter for hearing on 30.08.2022.

15
Stage 1412/07/2022

Hearing

The Tribunal adjourned the appeal to 22.08.2022 to allow counsel for both parties time to prepare arguments.

16
Stage 1527/04/2022

Hearing

The Tribunal noted the filing of an objection by the Regulatory Authority and, upon joint request from both parties' counsel, adjourned the matter to 12.07.2022.

17
Stage 1619/04/2022

For Order

The Tribunal granted UP RERA one week to file its response and directed all parties to exchange responses via email and upload them to the e-portal before the next hearing on 27.04.2022.

18
Stage 1729/03/2022

For Order

The Tribunal directs the Secretary of U.P. RERA to explain the legal provisions under which they modified a previous order and mandates that a response be filed within 10 days.

19
Stage 1810/03/2022

to file objections and its reply

The Tribunal issued a notice to U.P. RERA to explain the legal basis upon which the Regulatory Authority modified an original order dated 28.02.2020, questioning whether such action exceeded its jurisdiction under Section 63.

20
Stage 1907/01/2022

Hearing

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the appeal for hearing on January 20, 2022.

21
Stage 2009/12/2021

Hearing

The Tribunal granted the respondent two weeks to file a Vakalatnama and objections to the grounds of appeal, with subsequent timelines set for replies and document filing.

22
Stage 2123/11/2021

Hearing

The Tribunal directed the Registry to verify and upload the affidavit of service and scheduled the appeal for hearing on 09.12.2021.

23
Stage 2212/11/2021

Hearing

The Tribunal granted the appellant one week to file an affidavit of service and rescheduled the appeal hearing to 23.11.2021.

24
Stage 2307/10/2021

Hearing on Appeal

The Tribunal issued a notice to the respondent and directed the appellant to serve the memo of appeal via speed post and email, setting a timeline for filing objections and replies.

25
Stage 2422/04/2021

Hearing

No text available.

26
Stage 2505/04/2021

Hearing

No text available.

27
Stage 2615/03/2021

For Order

No text available.

28
Stage 2717/02/2021

Defect Removal

The Tribunal ordered that Appeal-119/2021 be listed alongside defective appeal no. 445/2020 on 19.02.2021.

29
Stage 2808/02/2021

Defect Removal

The Tribunal granted the appellant's counsel one week to file a supplementary affidavit clarifying the appellant's financial liabilities and expenses related to the execution of the conveyance deed, with the matter listed for 17.02.2021.

30
Stage 29Interim Order

Tribunal Order #0901126008672021-10-03-2022

The Tribunal issued a notice to U.P. RERA to explain the legal basis upon which the Regulatory Authority modified an original order dated 28.02.2020, questioning whether such action exceeded its jurisdiction under Section 63.

31
Stage 30Final Ruling Order

Tribunal Order #0901126008672021-20-09-2023

The appeal was dismissed as not pressed following the appellant's submission that the dispute had been resolved amicably and possession had been taken.

32
Stage 31Interim Order

Tribunal Order #0901126008672021-18-10-2022

The Tribunal directed both parties to exchange interest calculations based on a settlement framework where the temporary OC date serves as the cutoff and interest is payable for the delay period between possession and appeal filing.

33
Stage 32Interim Order

Tribunal Order #0901126008672021-30-08-2022

The parties expressed an intent to settle the dispute, with the appellant proposing that the Temporary Occupancy Certificate (TOC) date serve as the cutoff for interest calculations. The Tribunal directed both parties to appear on the next scheduled date of 14.09.2022.

34
Stage 33Interim Order

Tribunal Order #0901126008672021-29-03-2022

The Tribunal directs the Secretary of U.P. RERA to explain the legal provisions under which they modified a previous order and mandates that a response be filed within 10 days.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The appeal was dismissed as not pressed following the appellant's submission that the dispute had been resolved amicably and possession had been taken. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The appeal was dismissed as not pressed following the appellant's submission that the dispute had been resolved amicably and possession had been taken.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Nirmit Srivastava

Respondent Advocate(s)

  • Shobhit Mohan Shukla
  • Yash Tandon
  • Tushar Bahadur

Official RERA Tribunal Orders (5)

INTERIM_ORDEROrder ID: 0901126008672021-10-03-2022

The Tribunal issued a notice to U.P. RERA to explain the legal basis upon which the Regulatory Authority modified an original order dated 28.02.2020, questioning whether such action exceeded its jurisdiction under Section 63.

FINAL_ORDEROrder ID: 0901126008672021-20-09-2023

The appeal was dismissed as not pressed following the appellant's submission that the dispute had been resolved amicably and possession had been taken.

INTERIM_ORDEROrder ID: 0901126008672021-18-10-2022

The Tribunal directed both parties to exchange interest calculations based on a settlement framework where the temporary OC date serves as the cutoff and interest is payable for the delay period between possession and appeal filing.

INTERIM_ORDEROrder ID: 0901126008672021-30-08-2022

The parties expressed an intent to settle the dispute, with the appellant proposing that the Temporary Occupancy Certificate (TOC) date serve as the cutoff for interest calculations. The Tribunal directed both parties to appear on the next scheduled date of 14.09.2022.

INTERIM_ORDEROrder ID: 0901126008672021-29-03-2022

The Tribunal directs the Secretary of U.P. RERA to explain the legal provisions under which they modified a previous order and mandates that a response be filed within 10 days.