up_reraStatus: Completed
CASE ID: 0901126010062020

Appellant / Complainant

Prateek Realtors India Pvt. Ltd.

VS

Respondent

Atul Kumar Gupta

Developer Firm

prateek realtors india pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

17 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126010062020 by Prateek Realtors India Pvt. Ltd. against Atul Kumar Gupta before up_rera.

Non-Compliance & Execution
2
Stage 120/12/2022

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay due to lack of sufficient cause and consequently dismissed the appeal. The Tribunal further directed that the pre-deposited amount under Section 43(5) be transferred to the Regulatory Authority for disposal.

3
Stage 208/03/2022

Further Order

The Tribunal heard arguments regarding the appellant's application for condonation of delay and reserved judgment on the point of limitation.

4
Stage 305/01/2022

Delay condonation

The Tribunal adjourned the matter to 25.01.2022 for the disposal of a limitation application and its corresponding objection.

5
Stage 422/12/2021

Delay condonation

The Tribunal granted an adjournment requested by both counsels and rescheduled the case to 05.01.2022 for the disposal of a limitation application.

6
Stage 502/12/2021

Delay condonation

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the case to 22.12.2021 for the disposal of a limitation application.

7
Stage 616/11/2021

Final Hearing

The Tribunal granted a one-week extension for the appellant to file a better affidavit regarding the application for condonation of delay and scheduled the matter for hearing on 02.12.2021.

8
Stage 725/10/2021

Hearing

The Tribunal granted the applicant a final 10-day extension to file a better affidavit for condonation of delay, subject to a cost of Rs. 5,000 payable to the respondent.

9
Stage 813/09/2021

Hearing

The Tribunal allowed the appellant's request to file a better affidavit for condonation of delay and directed both parties to exchange written objections and replies via email before the next hearing.

10
Stage 907/05/2021

Hearing

No text available.

11
Stage 1012/04/2021

Hearing

No text available.

12
Stage 1116/03/2021

Hearing

No text available.

13
Stage 1221/01/2021

Compliance of section 43(5)

The Tribunal granted an adjournment requested by the appellant's counsel and extended the existing interim order until the next hearing date of 16.03.2021.

14
Stage 1317/11/2020

Compliance of section 43(5)

No text available.

15
Stage 14Interim Order

Tribunal Order #0901126010062020-25-10-2021

The Tribunal granted the applicant a final 10-day extension to file a better affidavit for condonation of delay, subject to a cost of Rs. 5,000 payable to the respondent.

16
Stage 15Final Ruling Order

Tribunal Order #0901126010062020-20-12-2022

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay due to lack of sufficient cause and consequently dismissed the appeal. The Tribunal further directed that the pre-deposited amount under Section 43(5) be transferred to the Regulatory Authority for disposal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay due to lack of sufficient cause and consequently dismissed the appeal. The Tribunal further directed that the pre-deposited amount under Section 43(5) be transferred to the Regulatory Authority for disposal. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay due to lack of sufficient cause and consequently dismissed the appeal. The Tribunal further directed that the pre-deposited amount under Section 43(5) be transferred to the Regulatory Authority for disposal.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Azhar Ikram
  • Manish Singh

Respondent Advocate(s)

  • Amit Yadav

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126010062020-25-10-2021

The Tribunal granted the applicant a final 10-day extension to file a better affidavit for condonation of delay, subject to a cost of Rs. 5,000 payable to the respondent.

FINAL_ORDEROrder ID: 0901126010062020-20-12-2022

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay due to lack of sufficient cause and consequently dismissed the appeal. The Tribunal further directed that the pre-deposited amount under Section 43(5) be transferred to the Regulatory Authority for disposal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for prateek realtors india pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →