Appellant / Complainant
Ramaprastha Builders Pvt. Ltd.
Respondent
Hari Mohan Singh
ramaprastha builders pvt. ltd.
₹30,72,780
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126012132020 by Ramaprastha Builders Pvt. Ltd. against Hari Mohan Singh before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal partially allowed the appeal, directing the appellant to refund only the amount of Rs. 20,72,780 received from the respondents with interest at MCLR+1%, while ruling that the appellant is not liable for payments made directly to respondent no. 3.
Further Hearing
The order provides a procedural reference, directing the parties to refer to the order passed in Appeal No. 54/2020.
Further Hearing
The Tribunal adjourned the matter due to lack of time and scheduled it for further hearing on 01.09.2022.
Further Hearing
The Tribunal adjourned the matter due to lack of time and scheduled it for further hearing on 31.08.2022.
Further Hearing
The tribunal adjourned the proceedings due to a request for adjournment from the respondent's counsel on medical grounds and rescheduled the hearing for 30.08.2022.
Hearing
The Tribunal granted the counsels for both parties one week to study the respondent's status as an allottee and the applicability of the Act and Rules, 2016, before rescheduling the hearing to 03.08.2022.
Hearing
The Tribunal adjourned the matter to 20.07.2022 due to a lawyers' strike/abstention from work by the Oudh Bar Association.
Hearing
The Tribunal directed both parties to exchange lists of dates, events, and relied-upon cases at least seven days before the next hearing, which is scheduled for 10.05.2022.
Hearing
The Tribunal directed the parties to submit a list of dates, events, and relied-upon judgments to the Registry and scheduled the appeal for hearing on 06.04.2022.
Final Hearing
The Tribunal adjourned the appeal to 24.01.2022 because the appellant requested a Senior Counsel and the current day's cause list was exhausted.
Hearing
The Tribunal granted the appellant's counsel two days to prepare her brief and rescheduled the hearing for January 7, 2022.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for January 5, 2022.
Hearing
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections, subject to a cost of Rs. 1,000/- to be used for legal library books.
Final Hearing
The appeal filed by M/S Ramaprastha Builders Pvt. Ltd. was dismissed for want of prosecution due to the non-appearance of the appellant or their counsel.
Tribunal Order #0901126012132020-22-11-2021
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections, subject to a cost of Rs. 1,000/- to be used for legal library books.
Tribunal Order #0901126012132020-30-09-2022
The Appellate Tribunal partially allowed the appeal, directing the appellant to refund only the amount of Rs. 20,72,780 received from the respondents with interest at MCLR+1%, while ruling that the appellant is not liable for payments made directly to respondent no. 3.
Tribunal Order #0901126012132020-22-01-2021
The appeal filed by M/S Ramaprastha Builders Pvt. Ltd. was dismissed for want of prosecution due to the non-appearance of the appellant or their counsel.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal partially allowed the appeal, directing the appellant to refund only the amount of Rs. 20,72,780 received from the respondents with interest at MCLR+1%, while ruling that the appellant is not liable for payments made directly to respondent no. 3. Awarded in favor of Partial. Awarded interest rate: MCLR + 1% per annum.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal partially allowed the appeal, directing the appellant to refund only the amount of Rs. 20,72,780 received from the respondents with interest at MCLR+1%, while ruling that the appellant is not liable for payments made directly to respondent no. 3.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR + 1% per annum
Interest Period
from the date of its receipt till the date of actual refund
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Pushpila Bisht
- Rahul Kapoor
Respondent Advocate(s)
- Divyam Krishna
Official RERA Tribunal Orders (3)
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections, subject to a cost of Rs. 1,000/- to be used for legal library books.
The Appellate Tribunal partially allowed the appeal, directing the appellant to refund only the amount of Rs. 20,72,780 received from the respondents with interest at MCLR+1%, while ruling that the appellant is not liable for payments made directly to respondent no. 3.
The appeal filed by M/S Ramaprastha Builders Pvt. Ltd. was dismissed for want of prosecution due to the non-appearance of the appellant or their counsel.