Appellant / Complainant
Suman Lata Pandey, Shiv Kumar Pandey
Respondent
Ansal Properties and Infrastructure Ltd.
ansal properties and infrastructure ltd.
₹22,43,458
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126012262020 by Suman Lata Pandey, Shiv Kumar Pandey against Ansal Properties and Infrastructure Ltd. before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal set aside the Adjudicating Officer's order that had rejected a compensation claim, ruling that interest for delay and compensation for losses are distinct remedies under the RERA Act 2016. The matter is remanded to the Adjudicating Officer to decide the appellants' compensation claim afresh based on actual evidence of loss.
Final Hearing
The court has heard the arguments from both the appellant and the respondent and has reserved the judgment for a later date.
Final Hearing
The Tribunal adjourned the matter due to the non-appearance of the appellant and scheduled the case for a hearing on 17.08.2022.
Final Hearing
The Tribunal directed the parties to file and exchange legal authorities regarding an application for additional evidence and scheduled the matter for further orders on 07.07.2022.
Final Hearing
The Tribunal granted an adjournment requested by the appellant and rescheduled the hearing for April 15, 2022.
Final Hearing
The Tribunal granted a request by the second appellant to list the appeal on 17.01.2022 for the consideration of an application to bring additional documents on record.
Final Hearing
The appeal is adjourned following a request from the appellant's counsel due to health issues, with the matter rescheduled for hearing on 04.01.2022.
Final Hearing
The Tribunal has rescheduled the appeal for a final hearing on 16.12.2021 before Bench No. 1.
Final Hearing
The Tribunal granted the second appellant, Shiv Kumar Pandey, a two-week extension to prepare his brief and rescheduled the hearing for December 2, 2021.
Hearing
The Tribunal granted a request from the respondent's counsel for more time to prepare and adjourned the appeal for final hearing to 12.11.2021.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for final arguments on 27.10.2021.
Hearing
The Tribunal adjourned the appeal to 26.03.2021 because advocates were abstaining from judicial work in support of a call by the Oudh Bar Association, Lucknow.
For Order
The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the appeal for hearing on 04.03.2021.
Tribunal Order #0901126012262020-29-09-2022
The Appellate Tribunal set aside the Adjudicating Officer's order that had rejected a compensation claim, ruling that interest for delay and compensation for losses are distinct remedies under the RERA Act 2016. The matter is remanded to the Adjudicating Officer to decide the appellants' compensation claim afresh based on actual evidence of loss.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal set aside the Adjudicating Officer's order that had rejected a compensation claim, ruling that interest for delay and compensation for losses are distinct remedies under the RERA Act 2016. The matter is remanded to the Adjudicating Officer to decide the appellants' compensation claim afresh based on actual evidence of loss. Awarded in favor of Appellant. Awarded interest rate: MCLR+1% of SBI.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal set aside the Adjudicating Officer's order that had rejected a compensation claim, ruling that interest for delay and compensation for losses are distinct remedies under the RERA Act 2016. The matter is remanded to the Adjudicating Officer to decide the appellants' compensation claim afresh based on actual evidence of loss.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR+1% of SBI
Interest Period
from the date mentioned in the agreement till the date of actual possession
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Shiv Kumar Pandey
Respondent Advocate(s)
- Anurag Singh
Official RERA Tribunal Orders (1)
The Appellate Tribunal set aside the Adjudicating Officer's order that had rejected a compensation claim, ruling that interest for delay and compensation for losses are distinct remedies under the RERA Act 2016. The matter is remanded to the Adjudicating Officer to decide the appellants' compensation claim afresh based on actual evidence of loss.
Need to research all rulings for ansal properties and infrastructure ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.