Appellant / Complainant
Bikram Chatterji
Respondent
Royal Home Town Planners Pvt. Ltd.
royal home town planners pvt. ltd.
₹23,30,125
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126012482021 by Bikram Chatterji against Royal Home Town Planners Pvt. Ltd. before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal dismissed the appeals, ruling that the appellant failed to file a valid counter-claim according to RERA procedural requirements and finding no illegality in the Regulatory Authority's order regarding possession and interest.
Hearing
The Tribunal directed the parties to file physical copies of their pleadings in the Registry within 7 days due to missing records for this pre-2022 case, and reserved the judgment.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to illness and scheduled the matter for final hearing on 09.01.2023, noting that no further adjournments will be permitted on that date.
Hearing
The proceeding is adjourned because the appellant's counsel is suffering from dengue fever; the matter is rescheduled for hearing on 22.12.2022.
Hearing
The Tribunal adjourned the matter due to lack of time and rescheduled the hearing for November 25, 2022.
Hearing
The matter was adjourned due to lack of time, with the case scheduled to be heard again on 24.11.2022.
Hearing
The Tribunal granted an adjournment due to the respondent's counsel's illness but issued a warning that if no alternative arrangement is made for the next hearing, the matter will be decided based on available records.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to health reasons and scheduled the matter for orders on 18.10.2022.
Hearing
The Tribunal granted the appellant 24 hours to file a reply to the respondent's objection and scheduled the appeal for a hearing on September 20, 2022.
Hearing
The Tribunal granted the appellant a final opportunity to file a replication/rejoinder to the respondent's reply and adjourned the matter to 28.07.2022.
to file objections and its reply
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the next hearing for May 18, 2022.
Further Order
The Tribunal granted the appellant one week to file a reply to the respondent's objections and directed the respondent to upload their objections on the e-portal within a week. The matter is scheduled for hearing on 29.04.2022.
Further Order
The U.P. Real Estate Appellate Tribunal adjourned the appeal in the interest of justice and scheduled it for further orders on 12.04.2022.
Hearing
The Tribunal granted an adjournment requested by the respondent and scheduled the case for further orders on 11.01.2022, while maintaining the existing interim order.
For Order
The Tribunal granted interim relief restraining the respondent from cancelling the appellant's allotment of Flat No. A-407 in the Beetle Lap Housing Project until the next hearing.
Hearing
The Tribunal directed the parties to exchange copies of the appeal memo, objections, and replies via email and set a timeline for filing documents on the e-portal before the next hearing on 22.04.2021.
Hearing on Appeal
The Tribunal issued notice to the respondent for March 4, 2021, and directed the appellant to serve summons and provide copies of the appeal memo via email.
Tribunal Order #0901126012482021-29-05-2023
The Appellate Tribunal dismissed the appeals, ruling that the appellant failed to file a valid counter-claim according to RERA procedural requirements and finding no illegality in the Regulatory Authority's order regarding possession and interest.
Tribunal Order #0901126012482021-18-10-2022
The Tribunal granted an adjournment due to the respondent's counsel's illness but issued a warning that if no alternative arrangement is made for the next hearing, the matter will be decided based on available records.
Tribunal Order #0901126012482021-07-10-2021
The Tribunal granted interim relief restraining the respondent from cancelling the appellant's allotment of Flat No. A-407 in the Beetle Lap Housing Project until the next hearing.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal dismissed the appeals, ruling that the appellant failed to file a valid counter-claim according to RERA procedural requirements and finding no illegality in the Regulatory Authority's order regarding possession and interest. Awarded in favor of Respondent. Awarded interest rate: MCLR+1% p.a.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal dismissed the appeals, ruling that the appellant failed to file a valid counter-claim according to RERA procedural requirements and finding no illegality in the Regulatory Authority's order regarding possession and interest.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1% p.a
Interest Period
for the delayed period till the OC/CC is received or the possession is offered, whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Bikram Chatterji
Respondent Advocate(s)
- Inderpreet Singh Chaddha
Official RERA Tribunal Orders (3)
The Appellate Tribunal dismissed the appeals, ruling that the appellant failed to file a valid counter-claim according to RERA procedural requirements and finding no illegality in the Regulatory Authority's order regarding possession and interest.
The Tribunal granted an adjournment due to the respondent's counsel's illness but issued a warning that if no alternative arrangement is made for the next hearing, the matter will be decided based on available records.
The Tribunal granted interim relief restraining the respondent from cancelling the appellant's allotment of Flat No. A-407 in the Beetle Lap Housing Project until the next hearing.
Need to research all rulings for royal home town planners pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.