up_reraStatus: Completed
CASE ID: 0901126014152020

Appellant / Complainant

Ms Krishna Estate Developers Private Limited

VS

Respondent

P C Joshi

Developer Firm

krishna estate developers private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferMaintenance & Utility Disputes

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

14 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126014152020 by Ms Krishna Estate Developers Private Limited against P C Joshi before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferMaintenance & Utility Disputes
2
Stage 126/03/2021

Compliance of section 43(5)

The U.P. Real Estate Appellate Tribunal dismissed two defective appeals filed by M/s Krishna Estate Developers Pvt. Ltd. due to the promoter's failure to comply with the mandatory pre-deposit requirements under Section 43(5) of the RERA Act, 2016.

3
Stage 217/03/2021

Compliance of section 43(5)

The Tribunal adjourned the appeal due to counsel's illness but issued a final warning that failure to comply with Section 43(5) of the Act by the next hearing will result in dismissal for non-compliance.

4
Stage 325/02/2021

Compliance of section 43(5)

The Tribunal adjourned the defective appeal due to a bar strike and directed the applicant's counsel to ensure complete compliance with Section 43(5) of the Act.

5
Stage 415/02/2021

For Order

The Tribunal allowed the appellant's amendment application to challenge the entire order of the Regulatory Authority rather than just a specific paragraph, while directing compliance with Section 43(5) of the Act.

6
Stage 504/02/2021

For Order

The Tribunal granted the appellant a one-week extension to comply with the provisions of Section 43(5) of the Act due to existing defects in the appeal.

7
Stage 619/01/2021

Defect Removal

No text available.

8
Stage 707/01/2021

Defect Removal

No text available.

9
Stage 8Final Ruling Order

Tribunal Order #0901126014152020-26-03-2021

The U.P. Real Estate Appellate Tribunal dismissed two defective appeals filed by M/s Krishna Estate Developers Pvt. Ltd. due to the promoter's failure to comply with the mandatory pre-deposit requirements under Section 43(5) of the RERA Act, 2016.

10
Stage 9Interim Order

Tribunal Order #0901126014152020-17-03-2021

The Tribunal adjourned the appeal due to counsel's illness but issued a final warning that failure to comply with Section 43(5) of the Act by the next hearing will result in dismissal for non-compliance.

11
Stage 10Interim Order

Tribunal Order #0901126014152020-25-02-2021

The Tribunal adjourned the defective appeal due to a bar strike and directed the applicant's counsel to ensure complete compliance with Section 43(5) of the Act.

12
Stage 11Interim Order

Tribunal Order #0901126014152020-15-02-2021

The Tribunal allowed the appellant's amendment application to challenge the entire order of the Regulatory Authority rather than just a specific paragraph, while directing compliance with Section 43(5) of the Act.

13
Stage 12Interim Order

Tribunal Order #0901126014152020-04-02-2021

The Tribunal granted the appellant a one-week extension to comply with the provisions of Section 43(5) of the Act due to existing defects in the appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed two defective appeals filed by M/s Krishna Estate Developers Pvt. Ltd. due to the promoter's failure to comply with the mandatory pre-deposit requirements under Section 43(5) of the RERA Act, 2016. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed two defective appeals filed by M/s Krishna Estate Developers Pvt. Ltd. due to the promoter's failure to comply with the mandatory pre-deposit requirements under Section 43(5) of the RERA Act, 2016.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.05.2016 to the date of obtaining OC/CC or offering possession, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 11(4)(d)Section 19(6)Section 43(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Shuchita Singh

Official RERA Tribunal Orders (5)

FINAL_ORDEROrder ID: 0901126014152020-26-03-2021

The U.P. Real Estate Appellate Tribunal dismissed two defective appeals filed by M/s Krishna Estate Developers Pvt. Ltd. due to the promoter's failure to comply with the mandatory pre-deposit requirements under Section 43(5) of the RERA Act, 2016.

INTERIM_ORDEROrder ID: 0901126014152020-17-03-2021

The Tribunal adjourned the appeal due to counsel's illness but issued a final warning that failure to comply with Section 43(5) of the Act by the next hearing will result in dismissal for non-compliance.

INTERIM_ORDEROrder ID: 0901126014152020-25-02-2021

The Tribunal adjourned the defective appeal due to a bar strike and directed the applicant's counsel to ensure complete compliance with Section 43(5) of the Act.

INTERIM_ORDEROrder ID: 0901126014152020-15-02-2021

The Tribunal allowed the appellant's amendment application to challenge the entire order of the Regulatory Authority rather than just a specific paragraph, while directing compliance with Section 43(5) of the Act.

INTERIM_ORDEROrder ID: 0901126014152020-04-02-2021

The Tribunal granted the appellant a one-week extension to comply with the provisions of Section 43(5) of the Act due to existing defects in the appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for krishna estate developers private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →