Appellant / Complainant
Jaydev Infratech Private Limited
Respondent
Nipun Sharma
jaydev infratech private limited
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126014652021 by Jaydev Infratech Private Limited against Nipun Sharma before up_rera.
Delay condonation
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Jaydev Infratech Private Limited due to the appellant's failure to comply with the provisions of Section 43(5) of the Act, 2016.
Defect Removal
The Tribunal granted the appellant one week to rectify procedural defects and comply with Section 43(5) of the Act, warning that failure to do so will result in dismissal of the appeal.
Defect Removal
The Tribunal noted the absence of the appellant's counsel and ordered the defective appeal to be listed on 09.11.2021 for removal of defects.
Tribunal Order #0901126014652021-23-11-2021
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Jaydev Infratech Private Limited due to the appellant's failure to comply with the provisions of Section 43(5) of the Act, 2016.
Tribunal Order #0901126014652021-09-11-2021
The Tribunal granted the appellant one week to rectify procedural defects and comply with Section 43(5) of the Act, warning that failure to do so will result in dismissal of the appeal.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Jaydev Infratech Private Limited due to the appellant's failure to comply with the provisions of Section 43(5) of the Act, 2016. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Jaydev Infratech Private Limited due to the appellant's failure to comply with the provisions of Section 43(5) of the Act, 2016.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Aditya
Respondent Advocate(s)
- Harish Pandey
Official RERA Tribunal Orders (2)
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Jaydev Infratech Private Limited due to the appellant's failure to comply with the provisions of Section 43(5) of the Act, 2016.
The Tribunal granted the appellant one week to rectify procedural defects and comply with Section 43(5) of the Act, warning that failure to do so will result in dismissal of the appeal.
Need to research all rulings for jaydev infratech private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.