Appellant / Complainant
Ashok Kumar Agrawal, Deepti Agrawal
Respondent
Svp Builders India Ltd.
svp builders india ltd.
₹32,57,732
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126015032020 by Ashok Kumar Agrawal, Deepti Agrawal against Svp Builders India Ltd. before up_rera.
for delivery of Judgment/Order
The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the remaining deposited amount to the appellants with interest at the rate of SBI's MCLR + 1% per annum from the date of deposit until the date of refund.
Further Hearing
The Tribunal heard arguments regarding an appeal against a RERA order concerning the refund of deposited amounts and the disputed forfeiture of funds following the cancellation of a flat unit. The judgment has been reserved pending a final decision on whether the respondent's forfeiture of Rs. 11,91,832 was lawful.
Further Hearing
The matter was adjourned due to the absence of the appellant's counsel and is scheduled for further hearing on March 18, 2024.
Final Hearing
Upon the joint request of the counsel for both parties, the matter has been adjourned for further hearing scheduled for tomorrow, March 15, 2024.
Final Hearing
The Tribunal adjourned the proceedings due to a medical exigency involving the respondent's counsel and rescheduled the matter for 14.03.2024.
Final Hearing
The Tribunal noted the history of the cancellation request and loan closure, then adjourned the matter to 11.03.2024 to allow the respondent counsel time to seek instructions regarding the forfeiture of earnest money.
Final Hearing
The Tribunal directed the respondent to produce original records regarding the appellant's request for unit cancellation and the subsequent communication of that decision to the appellant.
Final Hearing
The Tribunal noted that the appeal is ready for hearing and scheduled it for a subsequent hearing on 04.03.2024.
Final Hearing
The Tribunal granted the appellant one week to clarify the construction start date under Clause 59 of the Agreement and permitted the respondent to file an affidavit to verify their claims regarding the project's completion timeline.
Final Hearing
This document appears to be a formal heading/caption of an appeal case (APPEAL-212/2021) before the U.P. Real Estate Appellate Tribunal, noting the presence of counsel and the presiding members, but contains no substantive ruling or directive.
Final Hearing
The Tribunal granted adjournment applications filed by the respondent's counsel and rescheduled the appeal for a final hearing on 05.12.2022.
Final Hearing
The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the hearing for November 10, 2022.
Final Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and directed the respondent to serve a copy of their recall application to the appellants before the next hearing date on 21.10.2022.
Final Hearing
The Tribunal directed the respondent to file an application within 10 days to recall the ex-parte proceedings initiated against them and scheduled the matter for hearing on the recall application on 30.09.2022.
Final Hearing
The Tribunal noted the respondent's failure to file a reply or appear, resulting in the case proceeding ex-parte against the respondent and listing the matter for 01.09.2022.
Final Hearing
The Tribunal granted an adjournment and directed the respondent to file a list of dates and events within 15 days, noting that the opportunity for the respondent to file a reply had previously been closed.
Final Hearing
The Tribunal adjourned the appeal to 27.05.2022 and issued a warning that future adjournment requests by the respondent must be made via formal application or face costs.
Final Hearing
The Tribunal noted the respondent's failure to file a reply despite previous opportunities and adjourned the matter to 25.04.2022 for hearing.
Final Hearing
The matter was adjourned to 21.03.2022 following a notice that the parties may reach a settlement.
Final Hearing
The Tribunal granted the respondent ten days to submit requested information and scheduled the appeal for a hearing on 24.01.2022.
Final Hearing
The Tribunal directed the respondent to produce information regarding the start date of construction within two weeks and share it with the appellant via email before the next hearing.
Final Hearing
The Tribunal directed the appellant to bring on record the specific date of commencement of construction and the subsequent expiry of the 30-month period as stipulated in the Builder Buyer Agreement dated 30.05.2013.
Hearing
The Tribunal closed the respondent's opportunity to file a reply/objection to the grounds of appeal due to failure to comply with previous directions and adjourned the matter for final hearing on 18.11.2021.
Further Order
The Tribunal granted the respondent one final opportunity to file a reply to the grounds of appeal, directing that a copy be sent to the appellant via email, and adjourned the matter to 26.10.2021.
Hearing
The Tribunal granted the respondent a final opportunity to file a reply to the grounds of appeal within 15 days and scheduled the next hearing for April 13, 2021.
Hearing
The case is adjourned to 18.03.2021 due to a lawyers' strike, with parties directed to exchange their pleadings in the interim.
Further Hearing
The Tribunal ruled that the appeal is within the limitation period and ordered it to be registered as a regular appeal, directing the respondent to file a reply within 15 days.
Tribunal Order #0901126015032020-30-05-2024
The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the remaining deposited amount to the appellants with interest at the rate of SBI's MCLR + 1% per annum from the date of deposit until the date of refund.
Tribunal Order #0901126015032020-18-03-2024
The Tribunal heard arguments regarding an appeal against a RERA order concerning the refund of deposited amounts and the disputed forfeiture of funds following the cancellation of a flat unit. The judgment has been reserved pending a final decision on whether the respondent's forfeiture of Rs. 11,91,832 was lawful.
Tribunal Order #0901126015032020-18-09-2023
The Tribunal granted the appellant one week to clarify the construction start date under Clause 59 of the Agreement and permitted the respondent to file an affidavit to verify their claims regarding the project's completion timeline.
Tribunal Order #0901126015032020-18-11-2021
The Tribunal directed the appellant to bring on record the specific date of commencement of construction and the subsequent expiry of the 30-month period as stipulated in the Builder Buyer Agreement dated 30.05.2013.
Tribunal Order #0901126015032020-09-02-2021
The Tribunal ruled that the appeal is within the limitation period and ordered it to be registered as a regular appeal, directing the respondent to file a reply within 15 days.
Tribunal Order #0901126015032020-04-03-2024
The Tribunal directed the respondent to produce original records regarding the appellant's request for unit cancellation and the subsequent communication of that decision to the appellant.
Tribunal Order #0901126015032020-09-12-2021
The Tribunal directed the respondent to produce information regarding the start date of construction within two weeks and share it with the appellant via email before the next hearing.
Tribunal Order #0901126015032020-26-10-2021
The Tribunal closed the respondent's opportunity to file a reply/objection to the grounds of appeal due to failure to comply with previous directions and adjourned the matter for final hearing on 18.11.2021.
Tribunal Disposal & Final Award Ruling
The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the remaining deposited amount to the appellants with interest at the rate of SBI's MCLR + 1% per annum from the date of deposit until the date of refund. Awarded in favor of Appellant. Awarded interest rate: State Bank of India's MCLR+1% per annum.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the remaining deposited amount to the appellants with interest at the rate of SBI's MCLR + 1% per annum from the date of deposit until the date of refund.
Ruling Awarded To
Appellant
Awarded Interest Rate
State Bank of India's MCLR+1% per annum
Interest Period
from the date of deposit till the refund of the amount
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Swapnil Yadav
- Rahul Kapoor
Respondent Advocate(s)
- Azhar Ikram
- Manish Singh
Official RERA Tribunal Orders (8)
The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the remaining deposited amount to the appellants with interest at the rate of SBI's MCLR + 1% per annum from the date of deposit until the date of refund.
The Tribunal heard arguments regarding an appeal against a RERA order concerning the refund of deposited amounts and the disputed forfeiture of funds following the cancellation of a flat unit. The judgment has been reserved pending a final decision on whether the respondent's forfeiture of Rs. 11,91,832 was lawful.
The Tribunal granted the appellant one week to clarify the construction start date under Clause 59 of the Agreement and permitted the respondent to file an affidavit to verify their claims regarding the project's completion timeline.
The Tribunal directed the appellant to bring on record the specific date of commencement of construction and the subsequent expiry of the 30-month period as stipulated in the Builder Buyer Agreement dated 30.05.2013.
The Tribunal ruled that the appeal is within the limitation period and ordered it to be registered as a regular appeal, directing the respondent to file a reply within 15 days.
The Tribunal directed the respondent to produce original records regarding the appellant's request for unit cancellation and the subsequent communication of that decision to the appellant.
The Tribunal directed the respondent to produce information regarding the start date of construction within two weeks and share it with the appellant via email before the next hearing.
The Tribunal closed the respondent's opportunity to file a reply/objection to the grounds of appeal due to failure to comply with previous directions and adjourned the matter for final hearing on 18.11.2021.
Need to research all rulings for svp builders india ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.