Legal Issues & Claims Raised

Delay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015522024 by Prateek Realtors India Private Limited against Piyush Tyagi before up_rera.

Delay Compensation / Interest
2
Stage 104/04/2025

Delay condonation

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal because the appellant failed to provide a sufficient cause for the delay in filing.

3
Stage 212/03/2025

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for orders/hearing on 04.04.2025.

4
Stage 314/02/2025

Delay condonation

The Tribunal has granted a request from the counsel for both parties to adjourn the hearing of the appeal to 12.03.2025.

5
Stage 422/01/2025

Delay condonation

The Tribunal adjourned the proceedings following an application by the appellant's counsel and scheduled the hearing for the application for condonation of delay on 14.02.2025.

6
Stage 517/12/2024

Delay condonation

The Tribunal granted a request for adjournment on behalf of the appellant's counsel and rescheduled the appeal for hearing on 22.01.2025.

7
Stage 629/11/2024

Delay condonation

No text available.

8
Stage 705/11/2024

Delay condonation

Both counsel for the appellant and respondent requested an adjournment; consequently, the matter has been rescheduled for orders on 29.11.2024.

9
Stage 825/09/2024

Delay condonation

The Tribunal granted an adjournment application filed by the appellant and directed the appellant to file a rejoinder to the respondent's objections within one week.

10
Stage 923/08/2024

Delay condonation

The Tribunal granted the respondent three days to serve a soft copy of their objections and directed the appellant to file a reply within one week thereafter. The matter is scheduled for hearing on 25.09.2024 regarding the application for condonation of delay.

11
Stage 1022/07/2024

Delay condonation

The Tribunal granted the respondent 10 days to file objections regarding the application for condonation of delay and grounds of appeal, scheduling the next hearing for August 23, 2024.

12
Stage 1122/05/2024

Defect Removal

The Tribunal noted the appellant's compliance with Section 43(5) of the Act via a deposit of Rs. 7,67,728/- and issued notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 22.07.2024.

13
Stage 1215/05/2024

Defect Removal

No text available.

14
Stage 13Final Ruling Order

Tribunal Order #0901126015522024-04-04-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal because the appellant failed to provide a sufficient cause for the delay in filing.

15
Stage 14Interim Order

Tribunal Order #0901126015522024-22-05-2024

The Tribunal noted the appellant's compliance with Section 43(5) of the Act via a deposit of Rs. 7,67,728/- and issued notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 22.07.2024.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal because the appellant failed to provide a sufficient cause for the delay in filing. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal because the appellant failed to provide a sufficient cause for the delay in filing.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • A
  • Azhar Ikram
  • Sachin Kumar Pandey

Respondent Advocate(s)

  • Devansh Bhardwaj

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126015522024-04-04-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal because the appellant failed to provide a sufficient cause for the delay in filing.

INTERIM_ORDEROrder ID: 0901126015522024-22-05-2024

The Tribunal noted the appellant's compliance with Section 43(5) of the Act via a deposit of Rs. 7,67,728/- and issued notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 22.07.2024.

TathyaGrid RERA Intelligence AI

Need to research all rulings for prateek realtors india private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →