up_reraStatus: Completed
CASE ID: 0901126015592024

Appellant / Complainant

Mamta Gupta, Pravir Kumar Gupta

VS

Respondent

U.P. State Industrial Development Corporation Limited

Developer Firm

u.p. state industrial development corporation limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

22 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015592024 by Mamta Gupta, Pravir Kumar Gupta against U.P. State Industrial Development Corporation Limited before up_rera.

2
Stage 129/07/2025

Delay condonation

The U.P. Real Estate Appellate Tribunal rejected the application for condonation of delay (IA No. 1056/2024) due to lack of sufficient cause and consequently dismissed Appeal No. D115 of 2024.

3
Stage 208/07/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the better affidavit and adjourned the appeal to 29.07.2025.

4
Stage 308/05/2025

Delay condonation

The Tribunal granted the appellant additional time to file a better affidavit in support of their delay condonation application and scheduled the next hearing for July 8, 2025.

5
Stage 424/04/2025

Delay condonation

The Tribunal granted adjournment applications filed by both parties and rescheduled the appeal for hearing on 08.05.2025.

6
Stage 527/03/2025

Delay condonation

The Tribunal granted the appellant time to file a better affidavit in support of their application for condonation of delay and scheduled the matter for hearing on 24.04.2025.

7
Stage 621/02/2025

Delay condonation

The Tribunal granted the respondent time to file objections and scheduled the next hearing for March 27, 2025.

8
Stage 729/01/2025

Delay condonation

The Tribunal allowed the recall application and set aside the order dated 11.12.2024 which had imposed a cost of Rs. 5,000/- on the respondent due to counsel's non-appearance.

9
Stage 822/01/2025

Delay condonation

No text available.

10
Stage 915/01/2025

Delay condonation

No text available.

11
Stage 1011/12/2024

Delay condonation

The Tribunal granted a final adjournment to the respondent, subject to a cost of Rs. 5,000/- to be paid to the appellant, and scheduled the next hearing for 15.01.2025.

12
Stage 1113/11/2024

Delay condonation

This is a procedural order directing the parties to refer to a previously passed order dated in Appeal No. D 51/2024.

13
Stage 1216/10/2024

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for November 13, 2024.

14
Stage 1305/09/2024

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the delay condonation application and grounds of appeal, with a subsequent timeline set for the applicant to file a reply.

15
Stage 1429/07/2024

Delay condonation

The Tribunal granted a final 10-day extension to the respondent for filing their vakalatnama and objections, with the matter scheduled for further orders on September 5, 2024.

16
Stage 1501/07/2024

Delay condonation

The Tribunal granted the respondent one week to file objections to the application for condonation of delay and the grounds of appeal, and scheduled the matter for orders on 29.07.2024.

17
Stage 1601/05/2024

Delay condonation

No text available.

18
Stage 1708/04/2024

Delay condonation

The Tribunal issued notice to the respondent regarding the application for condonation of delay and scheduled the matter for hearing on 01.05.2024.

19
Stage 18Interim Order

Tribunal Order #0901126015592024-11-12-2024

The Tribunal granted a final adjournment to the respondent, subject to a cost of Rs. 5,000/- to be paid to the appellant, and scheduled the next hearing for 15.01.2025.

20
Stage 19Final Ruling Order

Tribunal Order #0901126015592024-29-07-2025

The U.P. Real Estate Appellate Tribunal rejected the application for condonation of delay (IA No. 1056/2024) due to lack of sufficient cause and consequently dismissed Appeal No. D115 of 2024.

21
Stage 20Interim Order

Tribunal Order #0901126015592024-29-01-2025

The Tribunal allowed the recall application and set aside the order dated 11.12.2024 which had imposed a cost of Rs. 5,000/- on the respondent due to counsel's non-appearance.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal rejected the application for condonation of delay (IA No. 1056/2024) due to lack of sufficient cause and consequently dismissed Appeal No. D115 of 2024. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal rejected the application for condonation of delay (IA No. 1056/2024) due to lack of sufficient cause and consequently dismissed Appeal No. D115 of 2024.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Deepak Dwivedi

Respondent Advocate(s)

  • Suchita Singh

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126015592024-11-12-2024

The Tribunal granted a final adjournment to the respondent, subject to a cost of Rs. 5,000/- to be paid to the appellant, and scheduled the next hearing for 15.01.2025.

FINAL_ORDEROrder ID: 0901126015592024-29-07-2025

The U.P. Real Estate Appellate Tribunal rejected the application for condonation of delay (IA No. 1056/2024) due to lack of sufficient cause and consequently dismissed Appeal No. D115 of 2024.

INTERIM_ORDEROrder ID: 0901126015592024-29-01-2025

The Tribunal allowed the recall application and set aside the order dated 11.12.2024 which had imposed a cost of Rs. 5,000/- on the respondent due to counsel's non-appearance.

TathyaGrid RERA Intelligence AI

Need to research all rulings for u.p. state industrial development corporation limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →