CASE ID: 0901126018102022

Appellant / Complainant

Antriksh Realtech Pvt. Ltd.

VS

Respondent

Govind Porwal

Developer Firm

antriksh realtech pvt. ltd.

Disputed Amount

11,51,362

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Refund of InvestmentDelay Compensation / InterestNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

6 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126018102022 by Antriksh Realtech Pvt. Ltd. against Govind Porwal before up_rera.

Refund of InvestmentDelay Compensation / InterestNon-Compliance & Execution
2
Stage 130/06/2022

For Order

The Tribunal issued a corrective order to rectify typographical errors regarding the date of the impugned Regulatory Authority order in its previous order dated 31.05.2022.

3
Stage 231/05/2022

For Order

The Tribunal rejected the appellant's application for the release of pre-deposited funds and directed that the entire amount be transferred to the U.P. Real Estate Regulatory Authority to be distributed to the respondent in accordance with existing execution proceedings.

4
Stage 309/05/2022

For Order

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the application for hearing on 31.05.2022.

5
Stage 4Final Ruling Order

Tribunal Order #0901126018102022-31-05-2022

The Tribunal rejected the appellant's application for the release of pre-deposited funds and directed that the entire amount be transferred to the U.P. Real Estate Regulatory Authority to be distributed to the respondent in accordance with existing execution proceedings.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the appellant's application for the release of pre-deposited funds and directed that the entire amount be transferred to the U.P. Real Estate Regulatory Authority to be distributed to the respondent in accordance with existing execution proceedings. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Active

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the appellant's application for the release of pre-deposited funds and directed that the entire amount be transferred to the U.P. Real Estate Regulatory Authority to be distributed to the respondent in accordance with existing execution proceedings.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 40Section 63Section 64Section 43(5)

Appearing Legal Counsel & Advocates

Respondent Advocate(s)

  • Tushar Bahadur

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126018102022-31-05-2022

The Tribunal rejected the appellant's application for the release of pre-deposited funds and directed that the entire amount be transferred to the U.P. Real Estate Regulatory Authority to be distributed to the respondent in accordance with existing execution proceedings.

TathyaGrid RERA Intelligence AI

Need to research all rulings for antriksh realtech pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →