Appellant / Complainant
Kirti Singh
Respondent
Ansal Properties and Infrastructure Limited
ansal properties and infrastructure limited
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126019602021 by Kirti Singh against Ansal Properties and Infrastructure Limited before up_rera.
Delay condonation
The Tribunal disposed of the appeal after the appellant sought to withdraw it to pursue an execution application, granting the appellant liberty to move for execution before the Regulatory Authority regarding the respondent's failure to deliver possession.
Delay condonation
The Tribunal directed the respondent to file a physical Vakalatnama and submit objections within one week via email before the next hearing. The case is scheduled for 04.01.2021 to address the application for limitation and any filed objections.
Hearing
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with the matter scheduled for hearing on December 1, 2021.
Hearing
The Tribunal directed the appellant to take steps within 10 days to summon the respondent via registered post and email, following a delay caused by the COVID-19 pandemic.
Admission
The Tribunal noted that the applicant has rectified registry defects and ordered notice to be issued to the respondent via registered post and email, with the matter listed for 20.04.2021.
Tribunal Order #0901126019602021-04-01-2022
The Tribunal disposed of the appeal after the appellant sought to withdraw it to pursue an execution application, granting the appellant liberty to move for execution before the Regulatory Authority regarding the respondent's failure to deliver possession.
Tribunal Disposal & Final Award Ruling
The Tribunal disposed of the appeal after the appellant sought to withdraw it to pursue an execution application, granting the appellant liberty to move for execution before the Regulatory Authority regarding the respondent's failure to deliver possession. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal disposed of the appeal after the appellant sought to withdraw it to pursue an execution application, granting the appellant liberty to move for execution before the Regulatory Authority regarding the respondent's failure to deliver possession.
Ruling Awarded To
Appellant
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- V.K Singh
Respondent Advocate(s)
- Saurabh Misra
Official RERA Tribunal Orders (1)
The Tribunal disposed of the appeal after the appellant sought to withdraw it to pursue an execution application, granting the appellant liberty to move for execution before the Regulatory Authority regarding the respondent's failure to deliver possession.