up_reraStatus: Completed
CASE ID: 0901126020412023

Appellant / Complainant

Aims Promoters Private Limited

VS

Respondent

Sanjeev Malhotra

Developer Firm

aims promoters private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

39 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126020412023 by Aims Promoters Private Limited against Sanjeev Malhotra before up_rera.

Non-Compliance & Execution
2
Stage 128/07/2025

For Order

The appeal was dismissed as withdrawn following an out-of-court settlement between the parties, with the Tribunal directing the release of the amount deposited under Section 43(5) of the Act to U.P. RERA for disbursement in accordance with law.

3
Stage 207/07/2025

For Order

The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the hearing for July 28, 2025, while maintaining any existing interim relief orders.

4
Stage 326/05/2025

Delay condonation

The parties informed the Tribunal that the matter is under negotiation for an amicable settlement, and the appeal has been adjourned to 07.07.2025.

5
Stage 405/05/2025

Delay condonation

The Tribunal noted that an amicable settlement process is underway between the parties and adjourned the appeal to 26.05.2025, while extending any existing interim orders.

6
Stage 508/04/2025

Delay condonation

The Tribunal granted an adjournment application filed by the appellant's counsel due to personal difficulty and rescheduled the appeal for hearing on 05.05.2025.

7
Stage 606/03/2025

Delay condonation

The Tribunal has scheduled the case for orders/hearing on 08.04.2025 and ordered that any existing interim orders shall continue until the next listing date.

8
Stage 712/02/2025

Delay condonation

The appellant's counsel filed an application for adjournment, and the tribunal has rescheduled the appeal for hearing on 06.03.2025.

9
Stage 824/01/2025

Delay condonation

The Tribunal granted a request to list the appeal for hearing on 12.02.2025 and ordered that any existing interim orders shall continue until the next listing date.

10
Stage 920/01/2025

Delay condonation

The Tribunal adjourned the appeal to 24.01.2025 at the request of the respondent's counsel and ordered that any existing interim orders shall remain in effect until the next hearing.

11
Stage 1013/12/2024

Hearing

The Tribunal granted an interim stay on the operation and implementation of the impugned order dated 24.02.2023, passed in Complaint No. ADJ/NCR144/11/102015/2022, until the next hearing date.

12
Stage 1110/12/2024

Hearing

The Tribunal adjourned the matter to 13.12.2024 following a submission by the respondent's counsel that the sale deed for the unit is expected to be executed within a week.

13
Stage 1207/11/2024

Defect Removal

The Tribunal noted the appellant's compliance regarding Section 43(5) of the Act and adjourned the matter to 10-12-2024 for hearing at the request of the respondent's counsel.

14
Stage 1330/09/2024

Defect Removal

The appellant informs the Tribunal that a challan has been generated for the remaining outstanding amount required under Section 43(5) of the Act, 2016, to be deposited by the next hearing date.

15
Stage 1419/09/2024

Defect Removal

The Tribunal noted that the matter is pending compliance with Section 43(5) of the Act and scheduled the appeal for orders on 30.09.2024.

16
Stage 1516/08/2024

Defect Removal

No text available.

17
Stage 1618/07/2024

For Order

The Tribunal granted a final opportunity for the appellant's counsel to argue the appeal regarding compliance with Section 43(5) of the Act on the next scheduled date.

18
Stage 1717/05/2024

For Order

No text available.

19
Stage 1818/04/2024

For Order

The Tribunal has scheduled the appeal for a hearing on 17.05.2024 following notification from the respondent's counsel that the matter is ripe for hearing.

20
Stage 1913/03/2024

For Order

The Tribunal granted an adjournment requested by the appellant's counsel on health grounds and rescheduled the hearing for 18.04.2024.

21
Stage 2016/02/2024

For Order

The Tribunal granted the respondent's counsel one week's time to argue regarding compliance with Section 43(5) of the Act 2016 and scheduled the matter for orders on 13.03.2024.

22
Stage 2106/02/2024

For Order

The Tribunal noted a deficiency in the appellant's mandatory deposit under Section 43(5) of the Act 2016 and directed the matter to be listed on 16.02.2024 to address the shortfall in the required amount.

23
Stage 2231/01/2024

For Order

The Tribunal granted the appellant 24 hours to file a reply to the respondent's objections and adjourned the matter to 06.02.2024 for hearing.

24
Stage 2309/01/2024

Defect Removal

The Tribunal imposed a cost of Rs. 1,000/- on the respondent for failing to file objections in a timely manner and granted a final one-week extension for filing, while noting the appellant's partial compliance with Section 43(5) deposit requirements.

25
Stage 2403/10/2023

Defect Removal

No text available.

26
Stage 2521/08/2023

Defect Removal

The Tribunal granted the respondent 10 days to file objections to the appeal and directed the parties to exchange replies via email and upload them to the e-portal before the next hearing on 03.10.2023.

27
Stage 2603/07/2023

Defect Removal

The Tribunal directed the conversion of a defective appeal into a regular appeal following the appellant's compliance with Section 43(5) of the Act and ordered the issuance of notice to the respondent.

28
Stage 2721/06/2023

Defect Removal

The Tribunal granted a one-week extension to the appellant to comply with a previous order dated 07.06.2023 due to network issues and scheduled the matter for 03.07.2023.

29
Stage 2807/06/2023

Defect Removal

The Tribunal granted an extension for the deposit of fees under Section 43(5) due to a technical glitch in the e-filing system and scheduled the matter for hearing on 21.06.2023.

30
Stage 2929/05/2023

Defect Removal

The Tribunal noted the appellant's claim of a technical glitch preventing the Section 43(5) deposit and scheduled the defective appeal for orders on 07.06.2023.

31
Stage 3018/05/2023

Defect Removal

The Tribunal granted the Appellant a one-week extension to comply with the provisions of Section 43(5) of the Act, 2016, and scheduled the matter for hearing on 29.05.2023.

32
Stage 3115/05/2023

Defect Removal

The matter was adjourned due to lack of time and is scheduled to be listed again on 18.05.2023.

33
Stage 32Interim Order

Tribunal Order #0901126020412023-13-12-2024

The Tribunal granted an interim stay on the operation and implementation of the impugned order dated 24.02.2023, passed in Complaint No. ADJ/NCR144/11/102015/2022, until the next hearing date.

34
Stage 33Interim Order

Tribunal Order #0901126020412023-09-01-2024

The Tribunal imposed a cost of Rs. 1,000/- on the respondent for failing to file objections in a timely manner and granted a final one-week extension for filing, while noting the appellant's partial compliance with Section 43(5) deposit requirements.

35
Stage 34Final Ruling Order

Tribunal Order #0901126020412023-28-07-2025

The appeal was dismissed as withdrawn following an out-of-court settlement between the parties, with the Tribunal directing the release of the amount deposited under Section 43(5) of the Act to U.P. RERA for disbursement in accordance with law.

36
Stage 35Interim Order

Tribunal Order #0901126020412023-30-09-2024

The appellant informs the Tribunal that a challan has been generated for the remaining outstanding amount required under Section 43(5) of the Act, 2016, to be deposited by the next hearing date.

37
Stage 36Final Ruling Order

Tribunal Order #0901126020412023-06-02-2024

The Tribunal noted a deficiency in the appellant's mandatory deposit under Section 43(5) of the Act 2016 and directed the matter to be listed on 16.02.2024 to address the shortfall in the required amount.

38
Stage 37Interim Order

Tribunal Order #0901126020412023-03-07-2023

The Tribunal directed the conversion of a defective appeal into a regular appeal following the appellant's compliance with Section 43(5) of the Act and ordered the issuance of notice to the respondent.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The appeal was dismissed as withdrawn following an out-of-court settlement between the parties, with the Tribunal directing the release of the amount deposited under Section 43(5) of the Act to U.P. RERA for disbursement in accordance with law. The Tribunal noted a deficiency in the appellant's mandatory deposit under Section 43(5) of the Act 2016 and directed the matter to be listed on 16.02.2024 to address the shortfall in the required amount. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The appeal was dismissed as withdrawn following an out-of-court settlement between the parties, with the Tribunal directing the release of the amount deposited under Section 43(5) of the Act to U.P. RERA for disbursement in accordance with law. The Tribunal noted a deficiency in the appellant's mandatory deposit under Section 43(5) of the Act 2016 and directed the matter to be listed on 16.02.2024 to address the shortfall in the required amount.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Harish Pandey
  • Isha Asthana

Respondent Advocate(s)

  • Abhishek Shukla

Official RERA Tribunal Orders (6)

INTERIM_ORDEROrder ID: 0901126020412023-13-12-2024

The Tribunal granted an interim stay on the operation and implementation of the impugned order dated 24.02.2023, passed in Complaint No. ADJ/NCR144/11/102015/2022, until the next hearing date.

INTERIM_ORDEROrder ID: 0901126020412023-09-01-2024

The Tribunal imposed a cost of Rs. 1,000/- on the respondent for failing to file objections in a timely manner and granted a final one-week extension for filing, while noting the appellant's partial compliance with Section 43(5) deposit requirements.

FINAL_ORDEROrder ID: 0901126020412023-28-07-2025

The appeal was dismissed as withdrawn following an out-of-court settlement between the parties, with the Tribunal directing the release of the amount deposited under Section 43(5) of the Act to U.P. RERA for disbursement in accordance with law.

INTERIM_ORDEROrder ID: 0901126020412023-30-09-2024

The appellant informs the Tribunal that a challan has been generated for the remaining outstanding amount required under Section 43(5) of the Act, 2016, to be deposited by the next hearing date.

FINAL_ORDEROrder ID: 0901126020412023-06-02-2024

The Tribunal noted a deficiency in the appellant's mandatory deposit under Section 43(5) of the Act 2016 and directed the matter to be listed on 16.02.2024 to address the shortfall in the required amount.

INTERIM_ORDEROrder ID: 0901126020412023-03-07-2023

The Tribunal directed the conversion of a defective appeal into a regular appeal following the appellant's compliance with Section 43(5) of the Act and ordered the issuance of notice to the respondent.

TathyaGrid RERA Intelligence AI

Need to research all rulings for aims promoters private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →