Appellant / Complainant
Sahara Prime City Ltd
Respondent
Santosh Kumar Gangey
sahara prime city ltd
₹47,75,405
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126020512021 by Sahara Prime City Ltd against Santosh Kumar Gangey before up_rera.
For Order
The Tribunal directs that the amount deposited by M/S Sahara Prime City Ltd. under Section 43(5) of the Act, along with all relevant records, must be transmitted to the Regulatory Authority for immediate release to the applicant, Santosh Kumar Gangey.
Further Order
The Tribunal directed that the deposited amount of Rs. 47,75,405/- be released to the respondent, Mr. Santosh Kumar Gangey, and ordered the case file to be remitted to the Regulatory Authority to facilitate final calculations and payment.
Hearing
The Tribunal noted the respondent's request to release funds deposited under Section 43(5) of the Act and adjourned the matter to May 3, 2021, at the respondent's request.
Tribunal Order #0901126020512021-17-12-2021
The Tribunal directs that the amount deposited by M/S Sahara Prime City Ltd. under Section 43(5) of the Act, along with all relevant records, must be transmitted to the Regulatory Authority for immediate release to the applicant, Santosh Kumar Gangey.
Tribunal Order #0901126020512021-28-10-2021
The Tribunal directed that the deposited amount of Rs. 47,75,405/- be released to the respondent, Mr. Santosh Kumar Gangey, and ordered the case file to be remitted to the Regulatory Authority to facilitate final calculations and payment.
Tribunal Disposal & Final Award Ruling
The Tribunal directed that the deposited amount of Rs. 47,75,405/- be released to the respondent, Mr. Santosh Kumar Gangey, and ordered the case file to be remitted to the Regulatory Authority to facilitate final calculations and payment. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal directed that the deposited amount of Rs. 47,75,405/- be released to the respondent, Mr. Santosh Kumar Gangey, and ordered the case file to be remitted to the Regulatory Authority to facilitate final calculations and payment.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Official RERA Tribunal Orders (2)
The Tribunal directs that the amount deposited by M/S Sahara Prime City Ltd. under Section 43(5) of the Act, along with all relevant records, must be transmitted to the Regulatory Authority for immediate release to the applicant, Santosh Kumar Gangey.
The Tribunal directed that the deposited amount of Rs. 47,75,405/- be released to the respondent, Mr. Santosh Kumar Gangey, and ordered the case file to be remitted to the Regulatory Authority to facilitate final calculations and payment.
Need to research all rulings for sahara prime city ltd?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.