up_reraStatus: Completed
CASE ID: 0901126028292023

Appellant / Complainant

Abhay Kumar Khare

VS

Respondent

Omega Infrabuild Pvt. Ltd.

Developer Firm

omega infrabuild pvt. ltd.

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Refund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

18 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126028292023 by Abhay Kumar Khare against Omega Infrabuild Pvt. Ltd. before up_rera.

Refund of InvestmentDelay Compensation / Interest
2
Stage 105/11/2024

Hearing

The appeal was dismissed as withdrawn with liberty granted to the appellant to pursue their refund claim before the RERA Authority, which is encouraged to decide the matter on merit within three months.

3
Stage 223/10/2024

Hearing

The Tribunal noted that the matter has proceeded ex parte against the respondent and granted a request to list the appeal for hearing on 05.11.2024.

4
Stage 316/09/2024

Hearing

No text available.

5
Stage 421/08/2024

Delay condonation

The Tribunal adjourned the appeal to 16.09.2024 for orders/hearing due to a technical glitch preventing the respondent's appearance.

6
Stage 505/08/2024

Delay condonation

The Tribunal granted the respondent 7 days to file an objection after previously proceeding ex-parte, and directed the appellant to reply within a week of receiving said objection.

7
Stage 624/07/2024

Delay condonation

The Tribunal directed the Registry to comply with a previous order dated 10.05.2024 and submit a compliance report within three days, subsequently scheduling the appeal for hearing on 05.08.2024.

8
Stage 729/05/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel on health grounds and rescheduled the appeal for hearing on 24.07.2024.

9
Stage 810/05/2024

Delay condonation

The Tribunal deferred proceeding ex-parte against the respondent because the previous order had not been properly served via email by the Registry or the appellant's counsel. The matter is rescheduled for hearing on 29.05.2024.

10
Stage 909/04/2024

Delay condonation

The Tribunal treated the service of notice on the respondent as sufficient and granted a 10-day extension for filing objections, warning that the matter will proceed ex-parte if no response is received by the next hearing.

11
Stage 1005/03/2024

Delay condonation

The Tribunal condoned the 40-day delay in filing the appeal due to the appellant's health issues and directed the Registry to convert the defective appeal into a regular appeal.

12
Stage 1129/01/2024

Delay condonation

The Tribunal granted the appellant one week to submit an email dated 24.03.2023 as evidence regarding the receipt of the impugned order and scheduled the hearing for the condonation of delay application for 05.03.2024.

13
Stage 1230/10/2023

Delay condonation

No text available.

14
Stage 1318/09/2023

Delay condonation

The Tribunal deemed service of notice upon the respondent sufficient based on email and postal records and granted the respondent 10 days to file objections to the application for condonation of delay and the appeal.

15
Stage 1411/09/2023

Delay condonation

The Tribunal adjourned the proceedings due to a strike called by the Bar Council of Uttar Pradesh and rescheduled the hearing for 18.09.2023 to consider an application for condonation of delay.

16
Stage 1520/07/2023

Delay condonation

The Tribunal issued notice to the respondent regarding the application for condonation of delay and directed the applicant to serve the notice via speed-post and email, with the matter listed for hearing on 11.09.2023.

17
Stage 16Interim Order

Tribunal Order #0901126028292023-05-03-2024

The Tribunal condoned the 40-day delay in filing the appeal due to the appellant's health issues and directed the Registry to convert the defective appeal into a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as withdrawn with liberty to pursue before the RERA Authority Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as withdrawn with liberty to pursue before the RERA Authority

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Eshita Bhasin

Official RERA Tribunal Orders (1)

INTERIM_ORDEROrder ID: 0901126028292023-05-03-2024

The Tribunal condoned the 40-day delay in filing the appeal due to the appellant's health issues and directed the Registry to convert the defective appeal into a regular appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for omega infrabuild pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →