up_reraStatus: Completed
CASE ID: 0901126030162021

Appellant / Complainant

Arun Chauhan

VS

Respondent

Gaursons Hi-Tech Infrastructure Private Limited

Developer Firm

gaursons hi-tech infrastructure private limited

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

8 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126030162021 by Arun Chauhan against Gaursons Hi-Tech Infrastructure Private Limited before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 102/11/2021

for delivery of Judgment/Order

The Tribunal partly allowed the appeal, modifying the interest calculation for delayed possession by granting the allottee interest from 01.07.2019 until the date of offer of possession, while still exempting periods related to COVID-19 and environmental construction bans.

3
Stage 226/10/2021

Hearing

The Tribunal condoned a one-day delay in filing the appeal due to the COVID-19 pandemic and directed the Registry to convert the defective appeal into a Regular Appeal.

4
Stage 301/10/2021

Delay condonation

The hearing could not commence due to poor audio during video conferencing; the matter is rescheduled for 26.10.2021 to consider the application for condonation of delay.

5
Stage 431/08/2021

Delay condonation

The Tribunal issued a notice on the application for condonation of delay and directed the appellant to serve the respondent via speed post and email, with instructions for filing objections and replies.

6
Stage 5Final Ruling Order

Tribunal Order #0901126030162021-02-11-2021

The Tribunal partly allowed the appeal, modifying the interest calculation for delayed possession by granting the allottee interest from 01.07.2019 until the date of offer of possession, while still exempting periods related to COVID-19 and environmental construction bans.

7
Stage 6Interim Order

Tribunal Order #0901126030162021-26-10-2021

The Tribunal condoned a one-day delay in filing the appeal due to the COVID-19 pandemic and directed the Registry to convert the defective appeal into a Regular Appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal partly allowed the appeal, modifying the interest calculation for delayed possession by granting the allottee interest from 01.07.2019 until the date of offer of possession, while still exempting periods related to COVID-19 and environmental construction bans. Awarded in favor of Partial. Awarded interest rate: MCLR + 1%.

Disposal Winner: PartialInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal partly allowed the appeal, modifying the interest calculation for delayed possession by granting the allottee interest from 01.07.2019 until the date of offer of possession, while still exempting periods related to COVID-19 and environmental construction bans.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR + 1%

Interest Period

from 01.07.2019 till the date of offer of possession given in pursuance to Regulatory Authority's order dated 25.05.2021, excluding the period from 25.03.2020 to 25.09.2020 and 116 days on account of restriction/ban imposed by the Environment Pollution (Prevention & Control) Authority, as well as vide order of Hon'ble Supreme Court dated 14.11.2019

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Applicant/Appellant In-Person

Respondent Advocate(s)

  • D N Verma
  • Samrat Vaish

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126030162021-02-11-2021

The Tribunal partly allowed the appeal, modifying the interest calculation for delayed possession by granting the allottee interest from 01.07.2019 until the date of offer of possession, while still exempting periods related to COVID-19 and environmental construction bans.

INTERIM_ORDEROrder ID: 0901126030162021-26-10-2021

The Tribunal condoned a one-day delay in filing the appeal due to the COVID-19 pandemic and directed the Registry to convert the defective appeal into a Regular Appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for gaursons hi-tech infrastructure private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →