CASE ID: 0901126032682022

Appellant / Complainant

Atul Chhabra

VS

Respondent

Strategic Developers Private Limited

Developer Firm

strategic developers private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

20 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126032682022 by Atul Chhabra against Strategic Developers Private Limited before up_rera.

2
Stage 128/03/2024

Hearing

The appeal was dismissed as withdrawn following an application by the appellant stating that the matter has been amicably settled between the parties.

3
Stage 222/02/2024

Hearing

The Tribunal noted the appellant's failure to file a reply to the respondent's objections and adjourned the matter for hearing on 28.03.2024.

4
Stage 316/01/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel on health grounds and rescheduled the hearing for 22.02.2024.

5
Stage 412/10/2023

Hearing

No text available.

6
Stage 504/09/2023

Delay condonation

The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the hearing for 12.10.2023.

7
Stage 609/08/2023

Delay condonation

The Tribunal granted the appellant's counsel one week to prepare his brief following the uploading of an online complaint and rescheduled the hearing for 04.09.2023.

8
Stage 729/05/2023

Delay condonation

This text represents the header/caption of an appeal (APPEAL-467/2022) before the U.P. Real Estate Appellate Tribunal, identifying the parties Atul Chhabra versus Strategic Developers Private Limited.

9
Stage 821/04/2023

Delay condonation

The parties requested an adjournment, and the Tribunal has rescheduled the case for hearing/orders on 29.05.2023.

10
Stage 913/03/2023

Delay condonation

The Tribunal noted the appellant's counsel was out of station and that no reply to objections had been filed; consequently, the appeal was scheduled for hearing on 21.04.2023.

11
Stage 1002/02/2023

Delay condonation

No text available.

12
Stage 1116/12/2022

Delay condonation

The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the hearing for February 2, 2023.

13
Stage 1222/11/2022

Further Order

The Tribunal directed the appellant to file a replication/rejoinder against the respondent's reply and scheduled the defective appeal for further orders on 14.12.2022.

14
Stage 1331/10/2022

Delay condonation

The Tribunal allowed the delay condonation application for the appeal, subject to a cost of Rs. 500/- to be deposited in the Tribunal's fund, and directed the Registry to register the defective appeal as a regular appeal.

15
Stage 1421/09/2022

Delay condonation

The Tribunal directed the respondent to file an objection against the appellant's delay condonation application and scheduled the matter for 31.10.2022 for disposal of said application.

16
Stage 1526/08/2022

Delay condonation

The Tribunal granted the appellant's request for fresh notice to be issued to the respondent and established a procedural timeline for service of documents and filing of objections.

17
Stage 1625/07/2022

Defect Removal

The Tribunal issued a notice to the respondent regarding an application for condonation of delay and directed specific procedural steps for service of documents via e-mail and speed-post.

18
Stage 1714/07/2022

Defect Removal

The Tribunal granted the appellant three days to upload an application for condonation of delay and rescheduled the defective appeal for hearing on 25.07.2022.

19
Stage 18Interim Order

Tribunal Order #0901126032682022-31-10-2022

The Tribunal allowed the delay condonation application for the appeal, subject to a cost of Rs. 500/- to be deposited in the Tribunal's fund, and directed the Registry to register the defective appeal as a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as withdrawn Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as withdrawn

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Shukla
  • Anuruddha Singh

Respondent Advocate(s)

  • Gautam Johri

Official RERA Tribunal Orders (1)

INTERIM_ORDEROrder ID: 0901126032682022-31-10-2022

The Tribunal allowed the delay condonation application for the appeal, subject to a cost of Rs. 500/- to be deposited in the Tribunal's fund, and directed the Registry to register the defective appeal as a regular appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for strategic developers private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →