up_reraStatus: Completed
CASE ID: 0901126033372024

Appellant / Complainant

Vikas Singhal

VS

Respondent

Eureka Builders Private Limited

Developer Firm

eureka builders private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

15 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126033372024 by Vikas Singhal against Eureka Builders Private Limited before up_rera.

2
Stage 112/09/2025

Hearing

The appeal was dismissed as withdrawn following an amicable out-of-court settlement between the appellant and the respondent.

3
Stage 201/09/2025

Hearing

The Tribunal granted a request to list the appeal for orders or hearing on 12.09.2025.

4
Stage 306/08/2025

Hearing

The Tribunal noted that settlement processes are ongoing between the parties and adjourned the appeal to 01.09.2025, directing the filing of an affidavit of compliance by the next date.

5
Stage 416/07/2025

Hearing

The Tribunal granted the respondent ten days to file objections and scheduled the next hearing for August 6, 2025.

6
Stage 526/05/2025

Hearing

The Tribunal adjourned the matter to 16.07.2025 for orders and directed the parties to exchange pleadings in the interim.

7
Stage 630/04/2025

Delay condonation

The Tribunal condoned the delay in filing the appeal, accepting the appellant's explanation that lack of local resources in Lucknow caused the delay, and directed the respondent to file objections within ten days.

8
Stage 703/04/2025

Delay condonation

The Tribunal granted the respondent a 10-day extension to file objections and scheduled the appeal for consideration of the delay application on 30.04.2025.

9
Stage 804/03/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the grounds of appeal, with the appellant permitted to file a rejoinder within one week thereafter, and scheduled the case for orders on 03.04.2025.

10
Stage 905/02/2025

Delay condonation

The Tribunal granted the respondent a final 10-day extension to file objections and serve a soft copy to the appellant, scheduling the next hearing for March 4, 2025.

11
Stage 1017/01/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections and directed that any reply be filed within one week thereafter, scheduling the next hearing for February 5, 2025.

12
Stage 1109/12/2024

Delay condonation

The Tribunal granted the respondent 10 days to file a vakalatnama and objections to the appeal, with a subsequent timeline provided for the appellant to file a reply.

13
Stage 1218/11/2024

Delay condonation

The Tribunal issued notice to the respondent and provided specific procedural directions for the service of the appeal and the application for condonation of delay, scheduling the next hearing for 09.12.2024.

14
Stage 13Interim Order

Tribunal Order #0901126033372024-30-04-2025

The Tribunal condoned the delay in filing the appeal, accepting the appellant's explanation that lack of local resources in Lucknow caused the delay, and directed the respondent to file objections within ten days.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as withdrawn Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as withdrawn

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Harish Pandey
  • Raghav Singhal

Respondent Advocate(s)

  • Siddharth Nandwani

Official RERA Tribunal Orders (1)

INTERIM_ORDEROrder ID: 0901126033372024-30-04-2025

The Tribunal condoned the delay in filing the appeal, accepting the appellant's explanation that lack of local resources in Lucknow caused the delay, and directed the respondent to file objections within ten days.

TathyaGrid RERA Intelligence AI

Need to research all rulings for eureka builders private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →