up_reraStatus: Completed
CASE ID: 0901126038362023

Appellant / Complainant

Avp Reality Limited

VS

Respondent

Shakil Ahmed, Ajnara India Limited, Uttar Pradesh Real Estate Regulatory Authority Gautam Buddha Nagar

Developer Firm

ajnara india limited

Disputed Amount

95,68,493

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestNon-Compliance & ExecutionJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

17 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126038362023 by Avp Reality Limited against Shakil Ahmed, Ajnara India Limited, Uttar Pradesh Real Estate Regulatory Authority Gautam Buddha Nagar before up_rera.

Delay in PossessionDelay Compensation / InterestNon-Compliance & ExecutionJurisdiction & Maintainability
2
Stage 107/05/2024

for delivery of Judgment/Order

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal, subsequently directing that the pre-deposited amount be transferred to U.P. RERA for distribution to the allottee in accordance with existing execution proceedings.

3
Stage 227/02/2024

Defect Removal

The Tribunal heard arguments regarding an application for condonation of delay in filing an appeal against an ex-parte order and a recovery certificate, but has reserved its judgment.

4
Stage 316/02/2024

Defect Removal

The Tribunal granted a request to list the defective appeal for consideration of an application for condonation of delay on 27.02.2024.

5
Stage 407/02/2024

Defect Removal

No text available.

6
Stage 530/01/2024

Defect Removal

The Tribunal has granted a request from the counsel for both parties to list the appeal for orders on 07.02.2024.

7
Stage 618/01/2024

Defect Removal

The Tribunal granted an adjournment requested by the respondent's counsel on health grounds and rescheduled the hearing for the defective appeal to 30.01.2024.

8
Stage 709/01/2024

Defect Removal

The Tribunal granted the respondent three days to provide evidence regarding their video conferencing appearance on 15.01.2021 and directed the filing of objections to the appeal within three days to comply with the statutory mandate for timely disposal.

9
Stage 803/10/2023

Defect Removal

No text available.

10
Stage 925/09/2023

Defect Removal

The Tribunal granted the respondent a one-week extension to obtain a certified copy of an order from the Regulatory Authority and scheduled the defective appeal for hearing on 03.10.2023.

11
Stage 1018/09/2023

Defect Removal

The Tribunal granted the respondent one week to place on record evidence regarding the issuance of a show cause notice and the communication of the order dated 15.01.2021, and scheduled the matter for consideration of the condonation of delay application on 25.09.2023.

12
Stage 1111/09/2023

Defect Removal

The Tribunal adjourned the proceedings due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh and rescheduled the defective appeal for 18.09.2023.

13
Stage 1204/09/2023

Defect Removal

The Tribunal adjourned the matter to 11.09.2023 in consideration of a resolution by the Bar Council of Uttar Pradesh regarding lawyers abstaining from judicial work.

14
Stage 13Interim Order

Tribunal Order #0901126038362023-09-01-2024

The Tribunal granted the respondent three days to provide evidence regarding their video conferencing appearance on 15.01.2021 and directed the filing of objections to the appeal within three days to comply with the statutory mandate for timely disposal.

15
Stage 14Final Ruling Order

Tribunal Order #0901126038362023-07-05-2024

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal, subsequently directing that the pre-deposited amount be transferred to U.P. RERA for distribution to the allottee in accordance with existing execution proceedings.

16
Stage 15Interim Order

Tribunal Order #0901126038362023-27-02-2024

The Tribunal heard arguments regarding an application for condonation of delay in filing an appeal against an ex-parte order and a recovery certificate, but has reserved its judgment.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal, subsequently directing that the pre-deposited amount be transferred to U.P. RERA for distribution to the allottee in accordance with existing execution proceedings. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal, subsequently directing that the pre-deposited amount be transferred to U.P. RERA for distribution to the allottee in accordance with existing execution proceedings.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

till 01.05.2016

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 40Section 63Section 64Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare
  • Aahuti Agarwal

Respondent Advocate(s)

  • Amit Yadav

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126038362023-09-01-2024

The Tribunal granted the respondent three days to provide evidence regarding their video conferencing appearance on 15.01.2021 and directed the filing of objections to the appeal within three days to comply with the statutory mandate for timely disposal.

FINAL_ORDEROrder ID: 0901126038362023-07-05-2024

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal, subsequently directing that the pre-deposited amount be transferred to U.P. RERA for distribution to the allottee in accordance with existing execution proceedings.

INTERIM_ORDEROrder ID: 0901126038362023-27-02-2024

The Tribunal heard arguments regarding an application for condonation of delay in filing an appeal against an ex-parte order and a recovery certificate, but has reserved its judgment.