up_reraStatus: Completed
CASE ID: 0901126042162024

Appellant / Complainant

Arjit Gupta

VS

Respondent

Ametek Buildtech India Private Limited

Developer Firm

ametek buildtech india private limited

Disputed Amount

38,99,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestUnfair Cancellation & ForfeitureJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

26 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126042162024 by Arjit Gupta against Ametek Buildtech India Private Limited before up_rera.

Delay in PossessionDelay Compensation / InterestUnfair Cancellation & ForfeitureJurisdiction & Maintainability
2
Stage 131/03/2026

Part Heard

The Tribunal set aside the Regulatory Authority's order, quashed the respondent's cancellation of the appellant's unit, restored the allotment, and awarded interest for delay and litigation costs due to the promoter's fraudulent practices and violation of Section 13 of the Act.

3
Stage 220/03/2026

Hearing

The Tribunal adjourned the appeal to 31.03.2026, directed parties to submit a list of dates and events, and ordered a correction to the appellant's counsel's name in the registry.

4
Stage 325/02/2026

Hearing

The Tribunal granted the respondent a final 10-day extension to remove registry defects and adjourned the appeal to 20.03.2026.

5
Stage 405/02/2026

Hearing

The Tribunal granted the respondent a final opportunity to comply with the previous order dated 16.12.2025 and extended the existing interim relief until the next hearing on 25.02.2026.

6
Stage 512/01/2026

Hearing

The Tribunal granted an adjournment application filed by the appellant and rescheduled the appeal for hearing on 05.02.2026.

7
Stage 616/12/2025

Hearing

The Tribunal directed the respondent to rectify registry defects in their supplementary objections within seven days and scheduled the appeal for hearing on 12.01.2026, extending any existing interim orders.

8
Stage 703/12/2025

Admission

The Tribunal granted the respondent three days to upload an application for permission to file supplementary objections due to a technical glitch and scheduled the next hearing for 16.12.2025.

9
Stage 814/11/2025

Admission

The Tribunal granted the respondent 7 days to file an application seeking permission to file supplementary objections and adjourned the matter to 03.12.2025.

10
Stage 915/10/2025

Admission

The Tribunal granted the respondent time to file supplementary objections due to a technical glitch and extended any existing interim relief until the next hearing date on 14.11.2025.

11
Stage 1003/09/2025

Admission

The Tribunal has scheduled the appeal for the next hearing on 15.10.2025 and extended any existing interim orders until that date.

12
Stage 1119/08/2025

Admission

The Tribunal has scheduled the appeal for a hearing on September 3, 2025, and directed the parties to exchange their pleadings in the interim.

13
Stage 1230/07/2025

Admission

The Tribunal granted the appellant 10 days to file a rejoinder affidavit and scheduled the next hearing for August 19, 2025.

14
Stage 1309/07/2025

Admission

The Tribunal has scheduled the case for hearing on 30.07.2025 and issued a warning that the matter will proceed ex parte against the respondent if objections are not filed.

15
Stage 1415/05/2025

Admission

The Tribunal granted the respondent 10 days to file objections to the memo of appeal and extended any existing interim orders until the next hearing date on 09.07.2025.

16
Stage 1521/04/2025

Admission

The Tribunal granted the respondent a final opportunity to file objections and extended the existing interim order until the next hearing date of 15.05.2025.

17
Stage 1621/03/2025

Admission

The Tribunal adjourned the matter to 21.04.2025 and directed the respondent to file objections in the meantime, while maintaining any existing interim orders.

18
Stage 1727/02/2025

Admission

The Tribunal granted the respondent 10 days to file objections to the appeal and interim relief prayer, with the appellant permitted to reply within one week thereafter. The matter is listed for hearing on 21.03.2025, and any existing interim relief is extended until the next date.

19
Stage 1804/02/2025

Admission

The Tribunal adjourned the matter to 27.02.2025, directed the parties to exchange pleadings, and extended any existing interim orders until the next hearing.

20
Stage 1916/01/2025

Admission

The Tribunal granted interim relief restraining the respondent promoter from creating any third-party interests, including allotment or execution of conveyance deeds, regarding the unit bearing plot No. 46, Block P1.

21
Stage 2009/12/2024

Admission

The Tribunal issued notice to the respondent and established a procedural timeline for the service of appeal documents and the filing of objections and replies.

22
Stage 21Final Ruling Order

Tribunal Order #0901126042162024-31-03-2026

The Tribunal set aside the Regulatory Authority's order, quashed the respondent's cancellation of the appellant's unit, restored the allotment, and awarded interest for delay and litigation costs due to the promoter's fraudulent practices and violation of Section 13 of the Act.

23
Stage 22Interim Order

Tribunal Order #0901126042162024-05-02-2026

The Tribunal granted the respondent a final opportunity to comply with the previous order dated 16.12.2025 and extended the existing interim relief until the next hearing on 25.02.2026.

24
Stage 23Interim Order

Tribunal Order #0901126042162024-09-07-2025

The Tribunal has scheduled the case for hearing on 30.07.2025 and issued a warning that the matter will proceed ex parte against the respondent if objections are not filed.

25
Stage 24Interim Order

Tribunal Order #0901126042162024-16-01-2025

The Tribunal granted interim relief restraining the respondent promoter from creating any third-party interests, including allotment or execution of conveyance deeds, regarding the unit bearing plot No. 46, Block P1.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order, quashed the respondent's cancellation of the appellant's unit, restored the allotment, and awarded interest for delay and litigation costs due to the promoter's fraudulent practices and violation of Section 13 of the Act. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order, quashed the respondent's cancellation of the appellant's unit, restored the allotment, and awarded interest for delay and litigation costs due to the promoter's fraudulent practices and violation of Section 13 of the Act.

Ruling Awarded To

Appellant

Interest Period

with effect from 01.05.2023 till the date of handing over physical possession of the unit

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(5)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Fuhar Gupta
  • Avinash Chnadra
  • Siddhartha Singh

Respondent Advocate(s)

  • Amit Sharma

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126042162024-31-03-2026

The Tribunal set aside the Regulatory Authority's order, quashed the respondent's cancellation of the appellant's unit, restored the allotment, and awarded interest for delay and litigation costs due to the promoter's fraudulent practices and violation of Section 13 of the Act.

INTERIM_ORDEROrder ID: 0901126042162024-05-02-2026

The Tribunal granted the respondent a final opportunity to comply with the previous order dated 16.12.2025 and extended the existing interim relief until the next hearing on 25.02.2026.

INTERIM_ORDEROrder ID: 0901126042162024-09-07-2025

The Tribunal has scheduled the case for hearing on 30.07.2025 and issued a warning that the matter will proceed ex parte against the respondent if objections are not filed.

INTERIM_ORDEROrder ID: 0901126042162024-16-01-2025

The Tribunal granted interim relief restraining the respondent promoter from creating any third-party interests, including allotment or execution of conveyance deeds, regarding the unit bearing plot No. 46, Block P1.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ametek buildtech india private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →