Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

4 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126043552023 by Anisha Marwah Bhargava against Supertech Township Project Ltd before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 120/09/2023

For Order

The Tribunal dismissed the appellant's appeal as 'not pressed' after the appellant expressed satisfaction with the Regulatory Authority's interest rates and sought to pursue execution of the original order instead. The court granted the appellant liberty to approach the Regulatory Authority for the execution of direction No. 5 regarding the refund of deposited amounts with interest.

3
Stage 2Final Ruling Order

Tribunal Order #0901126043552023-20-09-2023

The Tribunal dismissed the appellant's appeal as 'not pressed' after the appellant expressed satisfaction with the Regulatory Authority's interest rates and sought to pursue execution of the original order instead. The court granted the appellant liberty to approach the Regulatory Authority for the execution of direction No. 5 regarding the refund of deposited amounts with interest.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appellant's appeal as 'not pressed' after the appellant expressed satisfaction with the Regulatory Authority's interest rates and sought to pursue execution of the original order instead. The court granted the appellant liberty to approach the Regulatory Authority for the execution of direction No. 5 regarding the refund of deposited amounts with interest. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.

Disposal Winner: RespondentInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appellant's appeal as 'not pressed' after the appellant expressed satisfaction with the Regulatory Authority's interest rates and sought to pursue execution of the original order instead. The court granted the appellant liberty to approach the Regulatory Authority for the execution of direction No. 5 regarding the refund of deposited amounts with interest.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1%

Interest Period

from the period mentioned in the agreement after including the grace period upto 13.04.2016 and thereafter from 01.05.2016 till issuance of demand letter/receipt of the OC/CC

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Sunendra Kumar

Respondent Advocate(s)

  • Harish Pandey

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126043552023-20-09-2023

The Tribunal dismissed the appellant's appeal as 'not pressed' after the appellant expressed satisfaction with the Regulatory Authority's interest rates and sought to pursue execution of the original order instead. The court granted the appellant liberty to approach the Regulatory Authority for the execution of direction No. 5 regarding the refund of deposited amounts with interest.

TathyaGrid RERA Intelligence AI

Need to research all rulings for supertech township project ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →