up_reraStatus: Completed
CASE ID: 0901126047892022

Appellant / Complainant

Pawan Kumar Pandey

VS

Respondent

Super City Developers Pvt. Ltd.

Developer Firm

super city developers pvt. ltd.

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionStructural Defects & QualityPromotional MisrepresentationMaintenance & Utility DisputesJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126047892022 by Pawan Kumar Pandey against Super City Developers Pvt. Ltd. before up_rera.

Delay in PossessionStructural Defects & QualityPromotional MisrepresentationMaintenance & Utility DisputesJurisdiction & Maintainability
2
Stage 123/08/2023

Hearing

The Tribunal set aside the Regulatory Authority's order that had rejected complaints on the grounds that allottees lose their status after taking possession; it ruled that 'allottee' status remains intact under the Act 2016 and remanded the matter for a substantive examination of grievances regarding missing amenities and lack of Occupancy Certificate.

3
Stage 202/08/2023

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel on health grounds and scheduled the appeal for hearing on 23.08.2023, noting that no further adjournments will be permitted.

4
Stage 322/05/2023

Hearing

The Tribunal granted the appellant a one-week extension to file a reply against the respondent's objections and scheduled the next hearing for August 2, 2023.

5
Stage 403/05/2023

Delay condonation

The Tribunal condoned a 10-minute delay in uploading the appeal and directed the respondent to file documentation regarding basic facilities and amenities as per the allotment letter/BBA within one week.

6
Stage 522/03/2023

Delay condonation

No text available.

7
Stage 614/02/2023

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for 22.03.2023.

8
Stage 712/01/2023

Delay condonation

No text available.

9
Stage 816/12/2022

Delay condonation

The Tribunal noted that pleadings are complete and, upon the joint request of both parties' counsel, adjourned the matter for a hearing on 12.01.2023.

10
Stage 922/11/2022

Delay condonation

No text available.

11
Stage 1017/10/2022

Notice

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for 22.11.2022.

12
Stage 1119/09/2022

For Order

The Tribunal permitted the appellant to serve notice to the respondent via dasti summons after postal service failed, and scheduled the matter for 17.10.2022 to consider the application for condonation of delay.

13
Stage 1222/08/2022

Delay condonation

The Tribunal issued notice to the respondent and established a procedural timeline for service of documents, filing objections regarding the condonation of delay, and subsequent replies before the next hearing on 19.09.2022.

14
Stage 13Interim Order

Tribunal Order #0901126047892022-03-05-2023

The Tribunal condoned a 10-minute delay in uploading the appeal and directed the respondent to file documentation regarding basic facilities and amenities as per the allotment letter/BBA within one week.

15
Stage 14Final Ruling Order

Tribunal Order #0901126047892022-23-08-2023

The Tribunal set aside the Regulatory Authority's order that had rejected complaints on the grounds that allottees lose their status after taking possession; it ruled that 'allottee' status remains intact under the Act 2016 and remanded the matter for a substantive examination of grievances regarding missing amenities and lack of Occupancy Certificate.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order that had rejected complaints on the grounds that allottees lose their status after taking possession; it ruled that 'allottee' status remains intact under the Act 2016 and remanded the matter for a substantive examination of grievances regarding missing amenities and lack of Occupancy Certificate. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order that had rejected complaints on the grounds that allottees lose their status after taking possession; it ruled that 'allottee' status remains intact under the Act 2016 and remanded the matter for a substantive examination of grievances regarding missing amenities and lack of Occupancy Certificate.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 14(3)Section 12Section 11(4)(d)Section 19(6)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Prashant Chandra
  • N A

Respondent Advocate(s)

  • Amit Yadav
  • Raj Singh

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126047892022-03-05-2023

The Tribunal condoned a 10-minute delay in uploading the appeal and directed the respondent to file documentation regarding basic facilities and amenities as per the allotment letter/BBA within one week.

FINAL_ORDEROrder ID: 0901126047892022-23-08-2023

The Tribunal set aside the Regulatory Authority's order that had rejected complaints on the grounds that allottees lose their status after taking possession; it ruled that 'allottee' status remains intact under the Act 2016 and remanded the matter for a substantive examination of grievances regarding missing amenities and lack of Occupancy Certificate.

TathyaGrid RERA Intelligence AI

Need to research all rulings for super city developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →