Appellant / Complainant
Man Singh
Respondent
Paarth Infrabuild Private Ltd
paarth infrabuild private ltd
₹16,43,084
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126049442022 by Man Singh against Paarth Infrabuild Private Ltd before up_rera.
Re-Hearing
The Tribunal allowed the appeal and set aside the Regulatory Authority's order, directing the respondent promoter to refund the full amount of Rs. 16,43,084/- plus interest at MCLR+1% due to the promoter's failure to deliver the agreed unit and the project's inordinate delay.
Re-Hearing
The Tribunal noted the absence of both parties and adjourned the appeal for hearing to 04.07.2025.
Re-Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the case for orders on 07.05.2025.
Re-Hearing
The Tribunal has adjourned the matter to 21.04.2025 and directed the respondent to show cause on the next date as to why the impugned judgment and order has not yet been complied with.
Re-Hearing
Upon the joint request of the counsel for both parties, the Tribunal has adjourned the appeal to be listed on 21.03.2025.
Re-Hearing
The Tribunal granted a request from the respondent's counsel to reschedule the hearing of the appeal to 24.02.2025.
For Order
The Tribunal heard arguments from both counsels regarding the appeal and subsequently reserved the judgment for further deliberation.
For Order
The Tribunal noted that pleadings have been exchanged and, upon the respondent's counsel's request, adjourned the matter for orders/hearing to 09.08.2024.
For Order
The Tribunal granted an adjournment requested by both counsels and rescheduled the hearing for July 11, 2024.
For Order
The Tribunal noted the respondent's request for adjournment due to counsel being out of station and rescheduled the hearing for 14.05.2024.
For Order
The Tribunal noted that the appeal is ripe for hearing and adjourned the matter to 12.04.2024 following an adjournment request by the respondent's counsel.
For Order
The Tribunal noted that the respondent's counsel needs to register his name in the proceedings and scheduled the appeal for a hearing on 07.03.2024.
For Order
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the matter for hearing on 01.05.2022.
For Order
The Tribunal directed the appellant's counsel to verify the respondent's representation and ensure the filing of objections and vakalatnama, noting that the matter will proceed based on available records if no one appears for the respondent.
For Order
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for 12.12.2022.
For Order
The Tribunal granted the respondent one week to file an application for condonation of delay regarding their objections and granted the appellant 10 days to file a reply.
For Order
The Tribunal deemed service upon the respondent sufficient and granted the respondent 10 days to file objections to the appeal, scheduling the next hearing for 18.10.2022.
Admission
The Tribunal issued a notice to the respondent and outlined the procedural timeline for service of notice, filing of objections, and subsequent replies before the next hearing on 16.09.2022.
Tribunal Order #0901126049442022-21-03-2025
The Tribunal has adjourned the matter to 21.04.2025 and directed the respondent to show cause on the next date as to why the impugned judgment and order has not yet been complied with.
Tribunal Order #0901126049442022-04-07-2025
The Tribunal allowed the appeal and set aside the Regulatory Authority's order, directing the respondent promoter to refund the full amount of Rs. 16,43,084/- plus interest at MCLR+1% due to the promoter's failure to deliver the agreed unit and the project's inordinate delay.
Tribunal Disposal & Final Award Ruling
The Tribunal allowed the appeal and set aside the Regulatory Authority's order, directing the respondent promoter to refund the full amount of Rs. 16,43,084/- plus interest at MCLR+1% due to the promoter's failure to deliver the agreed unit and the project's inordinate delay. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal allowed the appeal and set aside the Regulatory Authority's order, directing the respondent promoter to refund the full amount of Rs. 16,43,084/- plus interest at MCLR+1% due to the promoter's failure to deliver the agreed unit and the project's inordinate delay.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR+1%
Interest Period
from the date of deposit till the date of payment
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rachit Sondhi
Respondent Advocate(s)
- Saurabh Misra
- Krishna Kumar Singh
Official RERA Tribunal Orders (2)
The Tribunal has adjourned the matter to 21.04.2025 and directed the respondent to show cause on the next date as to why the impugned judgment and order has not yet been complied with.
The Tribunal allowed the appeal and set aside the Regulatory Authority's order, directing the respondent promoter to refund the full amount of Rs. 16,43,084/- plus interest at MCLR+1% due to the promoter's failure to deliver the agreed unit and the project's inordinate delay.
Need to research all rulings for paarth infrabuild private ltd?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.