up_reraStatus: Completed
CASE ID: 0901126049442022

Appellant / Complainant

Man Singh

VS

Respondent

Paarth Infrabuild Private Ltd

Developer Firm

paarth infrabuild private ltd

Disputed Amount

16,43,084

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestUnfair Cancellation & Forfeiture

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

28 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126049442022 by Man Singh against Paarth Infrabuild Private Ltd before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestUnfair Cancellation & Forfeiture
2
Stage 104/07/2025

Re-Hearing

The Tribunal allowed the appeal and set aside the Regulatory Authority's order, directing the respondent promoter to refund the full amount of Rs. 16,43,084/- plus interest at MCLR+1% due to the promoter's failure to deliver the agreed unit and the project's inordinate delay.

3
Stage 207/05/2025

Re-Hearing

The Tribunal noted the absence of both parties and adjourned the appeal for hearing to 04.07.2025.

4
Stage 321/04/2025

Re-Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the case for orders on 07.05.2025.

5
Stage 421/03/2025

Re-Hearing

The Tribunal has adjourned the matter to 21.04.2025 and directed the respondent to show cause on the next date as to why the impugned judgment and order has not yet been complied with.

6
Stage 524/02/2025

Re-Hearing

Upon the joint request of the counsel for both parties, the Tribunal has adjourned the appeal to be listed on 21.03.2025.

7
Stage 614/02/2025

Re-Hearing

The Tribunal granted a request from the respondent's counsel to reschedule the hearing of the appeal to 24.02.2025.

8
Stage 709/08/2024

For Order

The Tribunal heard arguments from both counsels regarding the appeal and subsequently reserved the judgment for further deliberation.

9
Stage 811/07/2024

For Order

The Tribunal noted that pleadings have been exchanged and, upon the respondent's counsel's request, adjourned the matter for orders/hearing to 09.08.2024.

10
Stage 914/05/2024

For Order

The Tribunal granted an adjournment requested by both counsels and rescheduled the hearing for July 11, 2024.

11
Stage 1012/04/2024

For Order

The Tribunal noted the respondent's request for adjournment due to counsel being out of station and rescheduled the hearing for 14.05.2024.

12
Stage 1107/03/2024

For Order

The Tribunal noted that the appeal is ripe for hearing and adjourned the matter to 12.04.2024 following an adjournment request by the respondent's counsel.

13
Stage 1209/02/2024

For Order

The Tribunal noted that the respondent's counsel needs to register his name in the proceedings and scheduled the appeal for a hearing on 07.03.2024.

14
Stage 1309/10/2023

For Order

No text available.

15
Stage 1429/08/2023

For Order

No text available.

16
Stage 1511/07/2023

For Order

No text available.

17
Stage 1601/05/2023

For Order

No text available.

18
Stage 1723/03/2023

For Order

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the matter for hearing on 01.05.2022.

19
Stage 1815/02/2023

For Order

The Tribunal directed the appellant's counsel to verify the respondent's representation and ensure the filing of objections and vakalatnama, noting that the matter will proceed based on available records if no one appears for the respondent.

20
Stage 1913/01/2023

For Order

No text available.

21
Stage 2012/12/2022

For Order

No text available.

22
Stage 2123/11/2022

For Order

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for 12.12.2022.

23
Stage 2218/10/2022

For Order

The Tribunal granted the respondent one week to file an application for condonation of delay regarding their objections and granted the appellant 10 days to file a reply.

24
Stage 2316/09/2022

For Order

The Tribunal deemed service upon the respondent sufficient and granted the respondent 10 days to file objections to the appeal, scheduling the next hearing for 18.10.2022.

25
Stage 2422/08/2022

Admission

The Tribunal issued a notice to the respondent and outlined the procedural timeline for service of notice, filing of objections, and subsequent replies before the next hearing on 16.09.2022.

26
Stage 25Interim Order

Tribunal Order #0901126049442022-21-03-2025

The Tribunal has adjourned the matter to 21.04.2025 and directed the respondent to show cause on the next date as to why the impugned judgment and order has not yet been complied with.

27
Stage 26Final Ruling Order

Tribunal Order #0901126049442022-04-07-2025

The Tribunal allowed the appeal and set aside the Regulatory Authority's order, directing the respondent promoter to refund the full amount of Rs. 16,43,084/- plus interest at MCLR+1% due to the promoter's failure to deliver the agreed unit and the project's inordinate delay.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appeal and set aside the Regulatory Authority's order, directing the respondent promoter to refund the full amount of Rs. 16,43,084/- plus interest at MCLR+1% due to the promoter's failure to deliver the agreed unit and the project's inordinate delay. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appeal and set aside the Regulatory Authority's order, directing the respondent promoter to refund the full amount of Rs. 16,43,084/- plus interest at MCLR+1% due to the promoter's failure to deliver the agreed unit and the project's inordinate delay.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Interest Period

from the date of deposit till the date of payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rachit Sondhi

Respondent Advocate(s)

  • Saurabh Misra
  • Krishna Kumar Singh

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126049442022-21-03-2025

The Tribunal has adjourned the matter to 21.04.2025 and directed the respondent to show cause on the next date as to why the impugned judgment and order has not yet been complied with.

FINAL_ORDEROrder ID: 0901126049442022-04-07-2025

The Tribunal allowed the appeal and set aside the Regulatory Authority's order, directing the respondent promoter to refund the full amount of Rs. 16,43,084/- plus interest at MCLR+1% due to the promoter's failure to deliver the agreed unit and the project's inordinate delay.

TathyaGrid RERA Intelligence AI

Need to research all rulings for paarth infrabuild private ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →