up_reraStatus: Completed
CASE ID: 0901126050732022

Appellant / Complainant

Bandana Umar

VS

Respondent

Abhisht Developers & Builders Pvt. Ltd.

Developer Firm

abhisht developers & builders pvt. ltd.

Disputed Amount

35,46,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

6 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126050732022 by Bandana Umar against Abhisht Developers & Builders Pvt. Ltd. before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 106/09/2022

Part Heard

The Appellate Tribunal set aside the RERA Authority's order for being beyond the pleadings and directed the respondent to deliver possession of the flat within 12 months along with interest for the delay period.

3
Stage 231/08/2022

For Order

The Tribunal re-heard the matter and scheduled the appeal for the delivery of judgment on September 6, 2022.

4
Stage 326/08/2022

For Order

The Tribunal granted the respondent counsel two days to file his Vakalatnama and scheduled the matter for further orders on 31.08.2022.

5
Stage 4Final Ruling Order

Tribunal Order #0901126050732022-06-09-2022

The Appellate Tribunal set aside the RERA Authority's order for being beyond the pleadings and directed the respondent to deliver possession of the flat within 12 months along with interest for the delay period.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal set aside the RERA Authority's order for being beyond the pleadings and directed the respondent to deliver possession of the flat within 12 months along with interest for the delay period. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1% per annum.

Disposal Winner: AppellantInterest Rate: MCLR + 1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal set aside the RERA Authority's order for being beyond the pleadings and directed the respondent to deliver possession of the flat within 12 months along with interest for the delay period.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1% per annum

Interest Period

from the date of possession mentioned in BBA (36 months from the date of sanction plan) till the date of handing over lawful possession of the flat

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126050732022-06-09-2022

The Appellate Tribunal set aside the RERA Authority's order for being beyond the pleadings and directed the respondent to deliver possession of the flat within 12 months along with interest for the delay period.

TathyaGrid RERA Intelligence AI

Need to research all rulings for abhisht developers & builders pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →