Appellant / Complainant
Bandana Umar
Respondent
Abhisht Developers & Builders Pvt. Ltd.
abhisht developers & builders pvt. ltd.
₹35,46,000
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126050732022 by Bandana Umar against Abhisht Developers & Builders Pvt. Ltd. before up_rera.
Part Heard
The Appellate Tribunal set aside the RERA Authority's order for being beyond the pleadings and directed the respondent to deliver possession of the flat within 12 months along with interest for the delay period.
For Order
The Tribunal re-heard the matter and scheduled the appeal for the delivery of judgment on September 6, 2022.
For Order
The Tribunal granted the respondent counsel two days to file his Vakalatnama and scheduled the matter for further orders on 31.08.2022.
Tribunal Order #0901126050732022-06-09-2022
The Appellate Tribunal set aside the RERA Authority's order for being beyond the pleadings and directed the respondent to deliver possession of the flat within 12 months along with interest for the delay period.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal set aside the RERA Authority's order for being beyond the pleadings and directed the respondent to deliver possession of the flat within 12 months along with interest for the delay period. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1% per annum.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal set aside the RERA Authority's order for being beyond the pleadings and directed the respondent to deliver possession of the flat within 12 months along with interest for the delay period.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR + 1% per annum
Interest Period
from the date of possession mentioned in BBA (36 months from the date of sanction plan) till the date of handing over lawful possession of the flat
Statutory Sections Cited (RERA Act 2016)
Official RERA Tribunal Orders (1)
The Appellate Tribunal set aside the RERA Authority's order for being beyond the pleadings and directed the respondent to deliver possession of the flat within 12 months along with interest for the delay period.
Need to research all rulings for abhisht developers & builders pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.