Appellant / Complainant
Sanjay Bahadur Yadav
Respondent
Viraj Constructions Pvt. Ltd., Wealth Mantra Pvt. Ltd., Uttar Pradesh Real Estate Regulatory Authority
viraj constructions pvt. ltd.
₹31,98,000
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126052432021 by Sanjay Bahadur Yadav against Viraj Constructions Pvt. Ltd., Wealth Mantra Pvt. Ltd., Uttar Pradesh Real Estate Regulatory Authority before up_rera.
for delivery of Judgment/Order
The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by Sanjay Bahadur Yadav, upholding the Regulatory Authority's decision to deny relief because the appellant failed to execute a final allotment letter and concealed the cancellation of his booking due to non-payment of installments.
Hearing
The court heard arguments from the counsel for both the appellant and the respondent, subsequently reserving the judgment.
Exchange of pleadings
The Tribunal granted an adjournment because the appellant's counsel was out of station and rescheduled the hearing for 22.03.2023.
Exchange of pleadings
The Tribunal noted the repeated absence of the appellant's counsel and adjourned the matter to 13.12.2022 for hearing.
Exchange of pleadings
The Tribunal adjourned the appeal due to the non-appearance of the parties and scheduled the next hearing for 17.11.2022.
Hearing
The Tribunal directed the appellant to file a physical copy of their replication/rejoinder and ordered both parties to exchange lists of dates, events, and relied-upon judgments before the next hearing on 19.10.2022.
Hearing
The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the hearing for September 20, 2022.
Hearing
The Tribunal granted the appellant a final opportunity to file a replication/rejoinder and adjourned the matter to 24.08.2022 for hearing.
Hearing
The Tribunal granted the appellant permission to upload the missing memo of appeal and directed the filing of a replication/rejoinder within two weeks, scheduling the next hearing for 13.07.2022.
Hearing
The Tribunal granted the appellant a final opportunity to file a rejoinder/replication to the respondent's reply and directed that a copy be served via email before the next hearing on 04.05.2022.
Further Order
The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the next hearing for March 28, 2022.
Notice
The Tribunal directed the respondent to file their Vakalatnama within three days and submit a reply to the grounds of appeal within one week, ensuring a copy is sent to the appellant via email.
Hearing on Appeal
The Tribunal noted that defects were removed and the appeal was filed within time, subsequently issuing notice to the respondent and scheduling the matter for further orders on 15.12.2021.
Tribunal Order #0901126052432021-31-05-2023
The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by Sanjay Bahadur Yadav, upholding the Regulatory Authority's decision to deny relief because the appellant failed to execute a final allotment letter and concealed the cancellation of his booking due to non-payment of installments.
Tribunal Disposal & Final Award Ruling
The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by Sanjay Bahadur Yadav, upholding the Regulatory Authority's decision to deny relief because the appellant failed to execute a final allotment letter and concealed the cancellation of his booking due to non-payment of installments. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by Sanjay Bahadur Yadav, upholding the Regulatory Authority's decision to deny relief because the appellant failed to execute a final allotment letter and concealed the cancellation of his booking due to non-payment of installments.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Saghar Mehdi
Respondent Advocate(s)
- Sachin Garg
- Amit Kumar Kaushal
Official RERA Tribunal Orders (1)
The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by Sanjay Bahadur Yadav, upholding the Regulatory Authority's decision to deny relief because the appellant failed to execute a final allotment letter and concealed the cancellation of his booking due to non-payment of installments.