CASE ID: 0901126052952023

Appellant / Complainant

Ats Realty Private Limited

VS

Respondent

Vishal Singh

Developer Firm

ats realty private limited

Disputed Amount

5,73,105

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Refund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

25 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126052952023 by Ats Realty Private Limited against Vishal Singh before up_rera.

Refund of InvestmentDelay Compensation / Interest
2
Stage 109/05/2025

Hearing

The Tribunal disposed of the appeal following a settlement between the parties, directing the remittance of Rs. 5,73,105 to the respondent allottee and the refund of the remaining deposited amount to the appellant promoter.

3
Stage 225/04/2025

Delay condonation

The Tribunal condoned a 256-day delay in filing the appeal, recalled a previous order imposing a ₹20,000 cost for adjournment due to counsel's illness, and noted that the respondent has received possession of the unit.

4
Stage 304/04/2025

Delay condonation

The Tribunal granted an adjournment requested by the appellant, subject to a cost of Rs. 20,000/- to be paid by the appellant promoter to the respondent by the next hearing date on 25.04.2025.

5
Stage 407/03/2025

Delay condonation

The Tribunal has adjourned the appeal to 04.04.2025 following a joint request from the counsel for both parties.

6
Stage 514/02/2025

Delay condonation

The Tribunal accepted the appellant's undertaking to pay delay interest to the respondent for 597 days, accounting for deductions due to the COVID-19 pandemic and NGT injunctions, and directed the appellant to provide the interest computation within 10 days.

7
Stage 617/01/2025

Delay condonation

Upon the joint request of the counsel for both parties, the tribunal has adjourned the appeal to be listed on 14.02.2025 at 1:30 pm.

8
Stage 717/12/2024

Delay condonation

The Tribunal has granted a request from the respondent's counsel to list the appeal for orders on 17.01.2025 at 1:30 p.m.

9
Stage 829/11/2024

Delay condonation

No text available.

10
Stage 925/10/2024

Delay condonation

The Tribunal has adjourned the matter to 29.11.2024 for orders, following a request from the counsel for the appellant.

11
Stage 1027/09/2024

Delay condonation

The Tribunal granted the respondent 7 days to file objections to the delay condonation application and the appeal, with the appellant permitted to file a reply within 7 days thereafter. The matter is listed for hearing on 25.10.2024.

12
Stage 1129/08/2024

Delay condonation

The Tribunal granted the respondent 7 days to file objections to the appeal and directed the applicant to file a reply within 7 days of receiving the objections, with the matter listed for hearing on 27.09.2024.

13
Stage 1205/08/2024

Defect Removal

The Tribunal granted the respondent one week to file objections to the grounds of appeal and directed the appellant to file a reply upon receipt of said objections. The matter is scheduled for hearing on 29.08.2024.

14
Stage 1305/07/2024

Defect Removal

No text available.

15
Stage 1408/05/2024

Defect Removal

The Tribunal directed the parties to file replies to objections regarding the condonation of delay and the grounds of appeal within one week and scheduled the matter for hearing on 05.07.2024.

16
Stage 1505/04/2024

Defect Removal

The Tribunal granted the respondent ten days to file objections and directed the exchange of soft copies, scheduling the next hearing for May 8, 2024, to consider the application for condonation of delay.

17
Stage 1601/03/2024

Defect Removal

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with the matter scheduled for hearing on 05.04.2024.

18
Stage 1719/02/2024

Defect Removal

The Tribunal granted an adjournment requested by the appellant's counsel and provided one week to file the required affidavit of service, rescheduling the matter for March 1, 2024.

19
Stage 1819/01/2024

Defect Removal

The Tribunal held that the appellant has complied with Section 43(5) of the Act by depositing Rs. 10,94,107/- and issued notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 19.02.2024.

20
Stage 19Final Ruling Order

Tribunal Order #0901126052952023-09-05-2025

The Tribunal disposed of the appeal following a settlement between the parties, directing the remittance of Rs. 5,73,105 to the respondent allottee and the refund of the remaining deposited amount to the appellant promoter.

21
Stage 20Interim Order

Tribunal Order #0901126052952023-25-04-2025

The Tribunal condoned a 256-day delay in filing the appeal, recalled a previous order imposing a ₹20,000 cost for adjournment due to counsel's illness, and noted that the respondent has received possession of the unit.

22
Stage 21Interim Order

Tribunal Order #0901126052952023-14-02-2025

The Tribunal accepted the appellant's undertaking to pay delay interest to the respondent for 597 days, accounting for deductions due to the COVID-19 pandemic and NGT injunctions, and directed the appellant to provide the interest computation within 10 days.

23
Stage 22Interim Order

Tribunal Order #0901126052952023-19-01-2024

The Tribunal held that the appellant has complied with Section 43(5) of the Act by depositing Rs. 10,94,107/- and issued notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 19.02.2024.

24
Stage 23Interim Order

Tribunal Order #0901126052952023-04-04-2025

The Tribunal granted an adjournment requested by the appellant, subject to a cost of Rs. 20,000/- to be paid by the appellant promoter to the respondent by the next hearing date on 25.04.2025.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal disposed of the appeal following a settlement between the parties, directing the remittance of Rs. 5,73,105 to the respondent allottee and the refund of the remaining deposited amount to the appellant promoter. Awarded in favor of Partial.

Disposal Winner: PartialStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal disposed of the appeal following a settlement between the parties, directing the remittance of Rs. 5,73,105 to the respondent allottee and the refund of the remaining deposited amount to the appellant promoter.

Ruling Awarded To

Partial

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Kumar Singh

Respondent Advocate(s)

  • Aahuti Agarwal

Official RERA Tribunal Orders (5)

FINAL_ORDEROrder ID: 0901126052952023-09-05-2025

The Tribunal disposed of the appeal following a settlement between the parties, directing the remittance of Rs. 5,73,105 to the respondent allottee and the refund of the remaining deposited amount to the appellant promoter.

INTERIM_ORDEROrder ID: 0901126052952023-25-04-2025

The Tribunal condoned a 256-day delay in filing the appeal, recalled a previous order imposing a ₹20,000 cost for adjournment due to counsel's illness, and noted that the respondent has received possession of the unit.

INTERIM_ORDEROrder ID: 0901126052952023-14-02-2025

The Tribunal accepted the appellant's undertaking to pay delay interest to the respondent for 597 days, accounting for deductions due to the COVID-19 pandemic and NGT injunctions, and directed the appellant to provide the interest computation within 10 days.

INTERIM_ORDEROrder ID: 0901126052952023-19-01-2024

The Tribunal held that the appellant has complied with Section 43(5) of the Act by depositing Rs. 10,94,107/- and issued notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 19.02.2024.

INTERIM_ORDEROrder ID: 0901126052952023-04-04-2025

The Tribunal granted an adjournment requested by the appellant, subject to a cost of Rs. 20,000/- to be paid by the appellant promoter to the respondent by the next hearing date on 25.04.2025.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ats realty private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →