up_reraStatus: Completed
CASE ID: 0901126058792022

Appellant / Complainant

Rajiv Sharma, Gauri Sharma

VS

Respondent

Vxl Realtors Pvt Ltd, Red Cee Constructions Pvt. Ltd. Vxl Realtors Pvt Ltd

Developer Firm

vxl realtors pvt. ltd.

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

21 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126058792022 by Rajiv Sharma, Gauri Sharma against Vxl Realtors Pvt Ltd, Red Cee Constructions Pvt. Ltd. Vxl Realtors Pvt Ltd before up_rera.

Delay Compensation / Interest
2
Stage 110/03/2025

Re-Hearing

The Tribunal modified the Adjudicating Officer's order to rule that after the enforcement of the Real Estate (Regulation and Development) Act 2016, the interest rate for defaults by either the promoter or the allottee must be the prescribed rate of MCLR+1%, superseding any higher contractual rates.

3
Stage 228/08/2024

For Order

The Tribunal heard arguments from both counsels regarding Appeal-798/2022 and has reserved the judgment for further consideration.

4
Stage 313/08/2024

For Order

The Tribunal granted an adjournment to both counsels to allow them time to refer to supporting judgments and listed the appeal for further hearing on 28.08.2024.

5
Stage 415/07/2024

For Order

No text available.

6
Stage 515/05/2024

For Order

No text available.

7
Stage 615/04/2024

For Order

This is a procedural order directing the parties to refer to previous orders passed in Appeal No. 794/2022.

8
Stage 711/03/2024

For Order

The Tribunal granted an adjournment requested by the appellant's counsel to examine specific directions from the Adjudicating Officer and rescheduled the hearing for 15.04.2024.

9
Stage 802/02/2024

For Order

The Tribunal noted that pleadings have been exchanged and, due to the respondent's counsel being on leave, adjourned the matter for hearing to 11.03.2024.

10
Stage 903/11/2023

For Order

No text available.

11
Stage 1021/09/2023

For Order

The Tribunal has ordered the appeal to be listed for orders or hearing on November 3, 2023.

12
Stage 1104/08/2023

For Order

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the next hearing for September 21, 2023.

13
Stage 1224/05/2023

For Order

No text available.

14
Stage 1312/04/2023

For Order

The Tribunal has listed Appeal-798/2022 for orders or hearing on 24.05.2023, referencing a previous order passed in Appeal No. 794/2022.

15
Stage 1428/02/2023

For Order

The Tribunal granted the appellant's request to issue fresh notice to the respondent and directed the appellant to serve the notice via speed post and email, with the matter listed for 12.04.2023.

16
Stage 1513/02/2023

For Order

The Tribunal granted a 10-day extension to the appellant's counsel to file an affidavit of service, warning that failure to comply will result in heavy costs.

17
Stage 1611/01/2023

For Order

No text available.

18
Stage 1723/12/2022

Notice

The Tribunal granted a one-week extension to the appellant's counsel to file an affidavit of service and adjourned the matter to 11.01.2023 following a request for adjournment.

19
Stage 1801/12/2022

Admission

The Tribunal issued a notice to the respondent and established a procedural timeline for service of appeal documents and the filing of objections/replies via e-mail and the e-portal.

20
Stage 19Final Ruling Order

Tribunal Order #0901126058792022-10-03-2025

The Tribunal modified the Adjudicating Officer's order to rule that after the enforcement of the Real Estate (Regulation and Development) Act 2016, the interest rate for defaults by either the promoter or the allottee must be the prescribed rate of MCLR+1%, superseding any higher contractual rates.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal modified the Adjudicating Officer's order to rule that after the enforcement of the Real Estate (Regulation and Development) Act 2016, the interest rate for defaults by either the promoter or the allottee must be the prescribed rate of MCLR+1%, superseding any higher contractual rates. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal modified the Adjudicating Officer's order to rule that after the enforcement of the Real Estate (Regulation and Development) Act 2016, the interest rate for defaults by either the promoter or the allottee must be the prescribed rate of MCLR+1%, superseding any higher contractual rates.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav
  • Bal Kishor Verma

Respondent Advocate(s)

  • Azhar Ikram
  • Manish Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126058792022-10-03-2025

The Tribunal modified the Adjudicating Officer's order to rule that after the enforcement of the Real Estate (Regulation and Development) Act 2016, the interest rate for defaults by either the promoter or the allottee must be the prescribed rate of MCLR+1%, superseding any higher contractual rates.