up_reraStatus: Completed
CASE ID: 0901126073062022

Appellant / Complainant

Chetan Manohar Shashtri

VS

Respondent

Alpine Infraprojects Pvt Ltd

Developer Firm

alpine infraprojects pvt ltd

Disputed Amount

39,12,195

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Sale Deed & Title TransferUnfair Cancellation & Forfeiture

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

34 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126073062022 by Chetan Manohar Shashtri against Alpine Infraprojects Pvt Ltd before up_rera.

Sale Deed & Title TransferUnfair Cancellation & Forfeiture
2
Stage 130/10/2025

for delivery of Judgment/Order

The Tribunal set aside the RERA Authority's order and quashed the cancellation of three allottees' units, directing the promoter to issue fresh offers of possession with valid OC/CC and restore the units. Additionally, the Tribunal ruled that any third-party transfers made during pendency are subject to this decision under the doctrine of lis pendens and directed RERA to proceed with penalties against the promoter.

3
Stage 231/07/2025

Final Hearing

The Tribunal heard arguments from both the appellant and respondent and has reserved its judgment for a later date.

4
Stage 314/07/2025

Final Hearing

The Tribunal has ordered the matter to be listed for orders before the appropriate Bench (Bench No. 2) on July 31, 2025.

5
Stage 421/05/2025

Final Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the next hearing for July 14, 2025, noting that no further adjournments will be permitted.

6
Stage 509/05/2025

Hearing

The Tribunal heard arguments from both parties and directed the appellant to file a reply to the supplementary affidavit within five days, adjourning the matter for further arguments on 21.05.2025.

7
Stage 623/04/2025

Hearing

The Tribunal noted the respondent's filing of supplementary objections and the appellant's refusal to file an additional rejoinder, subsequently scheduling the matter for final hearing on 09.05.2025.

8
Stage 704/04/2025

Hearing

The Tribunal granted a request from the respondent's counsel to adjourn the appeal and scheduled the next hearing for April 23, 2025, noting that no further adjournments will be permitted.

9
Stage 811/03/2025

Hearing

The Tribunal directed the appellant to file a rejoinder to the respondent's supplementary objections within 10 days and scheduled the next hearing for April 4, 2025.

10
Stage 913/02/2025

Hearing

The Tribunal has adjourned the appeal to 11.03.2025 upon the joint request of the parties and directed that pleadings be completed in the interim.

11
Stage 1027/01/2025

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for orders/hearing on 13.02.2025.

12
Stage 1119/12/2024

Hearing

The Tribunal granted a request from the respondent's counsel to reschedule the hearing of Appeal-13/2023 to 27.01.2025, noting that no further adjournments will be permitted.

13
Stage 1226/11/2024

Hearing

The Tribunal granted an adjournment request from the respondent's counsel and rescheduled the hearing for December 19, 2024, noting that no further adjournments will be permitted.

14
Stage 1321/10/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the hearing for 26.11.2024, with a clarification that no further adjournments will be permitted.

15
Stage 1409/09/2024

Hearing

The Tribunal has adjourned the matter to 21.10.2024 to be heard alongside other appeals of a similar nature.

16
Stage 1505/08/2024

Hearing

The Tribunal granted the appellant seven days to file a Vakalatnama and scheduled the appeal for a final hearing on September 9, 2024.

17
Stage 1605/07/2024

Hearing

No text available.

18
Stage 1708/05/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel on health grounds and rescheduled the hearing for July 5, 2024.

19
Stage 1805/04/2024

Hearing

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing/orders on 08.05.2024.

20
Stage 1901/03/2024

Hearing

The Tribunal adjourned the matter to 05.04.2024 to align with similar cases and directed the appellant to file replies to the respondent's supplementary affidavit within one week.

21
Stage 2022/02/2024

Hearing

The Tribunal directed that Appeal-13/2023 be clubbed with Appeal No. 3/2023 for a joint hearing on 01.03.2024 and ordered the parties to exchange pleadings in the interim.

22
Stage 2119/01/2024

Hearing

The Tribunal rejected the appellant's application to recall an order dated 03.07.2023 due to delays and lack of cooperation, and imposed a nominal cost of Rs. 1/- on the appellant's counsel for appearing without preparation.

23
Stage 2217/10/2023

Hearing

No text available.

24
Stage 2311/09/2023

Hearing

The Tribunal adjourned the proceedings and rescheduled the hearing for October 17, 2023, due to a lawyer strike called by the Bar Council of Uttar Pradesh.

25
Stage 2418/08/2023

Hearing

The Tribunal directed that the appeal be listed for a hearing on 11.09.2023.

26
Stage 2503/07/2023

Hearing

The Tribunal granted an adjournment due to the appellant's health but closed the appellant's opportunity to file a reply to the respondent's objections due to previous delays and failure to comply with prior timelines.

27
Stage 2624/04/2023

Hearing

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the appeal for hearing on 03.07.2023.

28
Stage 2716/03/2023

Hearing

The Tribunal has scheduled the case for a hearing or orders on 24.04.2023, referencing a previous order passed in Appeal No. 11/2023.

29
Stage 2813/02/2023

For Order

The Tribunal granted the respondent 10 days to file objections to the grounds of appeal and scheduled the matter for hearing on March 16, 2023.

30
Stage 2910/01/2023

Admission

The Tribunal granted the respondent 10 days to file objections to the grounds of appeal and directed the parties to exchange replies and upload documents to the e-portal before the next hearing on 13.02.2023.

31
Stage 30Interim Order

Tribunal Order #0901126073062022-03-07-2023

The Tribunal granted an adjournment due to the appellant's health but closed the appellant's opportunity to file a reply to the respondent's objections due to previous delays and failure to comply with prior timelines.

32
Stage 31Final Ruling Order

Tribunal Order #0901126073062022-30-10-2025

The Tribunal set aside the RERA Authority's order and quashed the cancellation of three allottees' units, directing the promoter to issue fresh offers of possession with valid OC/CC and restore the units. Additionally, the Tribunal ruled that any third-party transfers made during pendency are subject to this decision under the doctrine of lis pendens and directed RERA to proceed with penalties against the promoter.

33
Stage 32Interim Order

Tribunal Order #0901126073062022-19-01-2024

The Tribunal rejected the appellant's application to recall an order dated 03.07.2023 due to delays and lack of cooperation, and imposed a nominal cost of Rs. 1/- on the appellant's counsel for appearing without preparation.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the RERA Authority's order and quashed the cancellation of three allottees' units, directing the promoter to issue fresh offers of possession with valid OC/CC and restore the units. Additionally, the Tribunal ruled that any third-party transfers made during pendency are subject to this decision under the doctrine of lis pendens and directed RERA to proceed with penalties against the promoter. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the RERA Authority's order and quashed the cancellation of three allottees' units, directing the promoter to issue fresh offers of possession with valid OC/CC and restore the units. Additionally, the Tribunal ruled that any third-party transfers made during pendency are subject to this decision under the doctrine of lis pendens and directed RERA to proceed with penalties against the promoter.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 11(4)(f)Section 17Section 11(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anurag Misra
  • Santosh Yadav

Respondent Advocate(s)

  • Anurag Singh

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126073062022-03-07-2023

The Tribunal granted an adjournment due to the appellant's health but closed the appellant's opportunity to file a reply to the respondent's objections due to previous delays and failure to comply with prior timelines.

FINAL_ORDEROrder ID: 0901126073062022-30-10-2025

The Tribunal set aside the RERA Authority's order and quashed the cancellation of three allottees' units, directing the promoter to issue fresh offers of possession with valid OC/CC and restore the units. Additionally, the Tribunal ruled that any third-party transfers made during pendency are subject to this decision under the doctrine of lis pendens and directed RERA to proceed with penalties against the promoter.

INTERIM_ORDEROrder ID: 0901126073062022-19-01-2024

The Tribunal rejected the appellant's application to recall an order dated 03.07.2023 due to delays and lack of cooperation, and imposed a nominal cost of Rs. 1/- on the appellant's counsel for appearing without preparation.

TathyaGrid RERA Intelligence AI

Need to research all rulings for alpine infraprojects pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →