up_reraStatus: Completed
CASE ID: 0901126074142022

Appellant / Complainant

Amrita Singh

VS

Respondent

Ats Homes Private Limited

Developer Firm

ats homes private limited

Disputed Amount

11,07,225

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Refund of InvestmentPromotional Misrepresentation

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

21 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126074142022 by Amrita Singh against Ats Homes Private Limited before up_rera.

Refund of InvestmentPromotional Misrepresentation
2
Stage 115/01/2025

For Order

The Tribunal set aside the RERA Authority's order and ruled that the appellant is entitled to a full refund of Rs. 11,07,225 plus interest due to the promoter's use of false/misleading statements regarding amenities in the allotment letter, which were later retracted in the Builder Buyer Agreement.

3
Stage 209/01/2025

For Order

The Tribunal has adjourned the appeal to 15.01.2025 for hearing following a joint request from the counsels for both the appellant and the respondent.

4
Stage 325/07/2024

Further Hearing

The Tribunal heard arguments from the counsel for both parties and reserved the judgment for a later date.

5
Stage 427/05/2024

Further Hearing

The Tribunal has rescheduled the hearing of Appeal-1/2023 to 25.07.2024 following a joint request from the counsels for both parties.

6
Stage 525/04/2024

Further Hearing

The Tribunal listed the defective appeal for consideration of a condonation of delay application and hearing on 27.05.2024.

7
Stage 615/04/2024

Further Hearing

The Tribunal granted an adjournment at the request of the respondent's counsel to seek further instructions and scheduled the case for orders on 25.04.2024.

8
Stage 702/04/2024

Further Hearing

The Tribunal granted a request from the respondent's counsel to seek instructions regarding the inclusion of promised concessions in the BBA and adjourned the matter to 15.04.2024.

9
Stage 827/02/2024

Further Hearing

The Tribunal has revised the list and scheduled a hearing for 02.04.2024 to consider the condonation of delay regarding this defective appeal.

10
Stage 917/01/2024

Further Hearing

The Tribunal granted an adjournment requested by the appellant's counsel on personal grounds and rescheduled the hearing for 27.02.2024.

11
Stage 1016/01/2024

Hearing

The Tribunal noted that this appeal is similar to Appeal No. 02/2023 and adjourned the matter for hearing on 17.01.2024.

12
Stage 1112/10/2023

Hearing

No text available.

13
Stage 1204/09/2023

Hearing

The Tribunal adjourned the proceedings to 12.10.2023 in response to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh.

14
Stage 1323/08/2023

Hearing

The Tribunal granted a joint request for adjournment from the counsels of both parties and rescheduled the hearing for September 4, 2023.

15
Stage 1405/07/2023

For Order

The Tribunal granted an adjournment requested by the appellant's counsel due to ongoing settlement negotiations between the parties. The matter is scheduled for further hearing on 23.08.2023.

16
Stage 1526/04/2023

For Order

The Tribunal noted the absence of the appellant's counsel due to sanctioned leave and adjourned the matter to 05.07.2023 for orders or hearing.

17
Stage 1616/03/2023

For Order

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the matter for orders on 26.04.2023.

18
Stage 1706/02/2023

For Order

The Tribunal treated the service of notice upon the respondent as sufficient due to postal and email delivery and granted the respondent 10 days to file objections before proceeding ex parte.

19
Stage 1803/01/2023

Admission

The Tribunal issued a notice to the respondent and outlined the procedural steps for service of the appeal memo and the timeline for filing objections and replies.

20
Stage 19Final Ruling Order

Tribunal Order #0901126074142022-15-01-2025

The Tribunal set aside the RERA Authority's order and ruled that the appellant is entitled to a full refund of Rs. 11,07,225 plus interest due to the promoter's use of false/misleading statements regarding amenities in the allotment letter, which were later retracted in the Builder Buyer Agreement.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the RERA Authority's order and ruled that the appellant is entitled to a full refund of Rs. 11,07,225 plus interest due to the promoter's use of false/misleading statements regarding amenities in the allotment letter, which were later retracted in the Builder Buyer Agreement. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the RERA Authority's order and ruled that the appellant is entitled to a full refund of Rs. 11,07,225 plus interest due to the promoter's use of false/misleading statements regarding amenities in the allotment letter, which were later retracted in the Builder Buyer Agreement.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Interest Period

from the date of deposit made by the appellant till the date of payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 12

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Harish Pandey
  • Aahuti Agarwal
  • Isha Asthana

Respondent Advocate(s)

  • Surangama Sharma

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126074142022-15-01-2025

The Tribunal set aside the RERA Authority's order and ruled that the appellant is entitled to a full refund of Rs. 11,07,225 plus interest due to the promoter's use of false/misleading statements regarding amenities in the allotment letter, which were later retracted in the Builder Buyer Agreement.