up_reraStatus: Completed
CASE ID: 0901126003692025

Appellant / Complainant

Suncity Hi-Tech Infrastructures Private Limited

VS

Respondent

Arvind Overseas Project Services Private Limited

Developer Firm

suncity hi-tech infrastructures private limited

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126003692025 by Suncity Hi-Tech Infrastructures Private Limited against Arvind Overseas Project Services Private Limited before up_rera.

Non-Compliance & Execution
2
Stage 114/05/2025

For Order

The Tribunal allowed the appellant's application to release funds previously deposited under Section 43(5) of the Act, directing the Registry to refund the amount to Suncity Hi-Tech Infrastructures Private Limited following proof of payment to the respondent.

3
Stage 222/04/2025

For Order

The Tribunal adjourned the proceedings due to the absence of both parties and rescheduled the hearing for IA-129/2025 to 14.05.2025.

4
Stage 303/04/2025

For Order

No text available.

5
Stage 428/03/2025

Notice

No text available.

6
Stage 520/03/2025

Notice

No text available.

7
Stage 625/02/2025

Notice

The Tribunal noted that counsels are abstaining from judicial work due to a U.P. Bar Council resolution and adjourned the matter to 28.03.2025.

8
Stage 704/02/2025

For Order

The Tribunal issued a notice to the respondent regarding IA-129/2025 and outlined the procedural steps for service of notice and filing of objections, scheduling the matter for consideration on 25.02.2025.

9
Stage 8Final Ruling Order

Tribunal Order #0901126003692025-14-05-2025

The Tribunal allowed the appellant's application to release funds previously deposited under Section 43(5) of the Act, directing the Registry to refund the amount to Suncity Hi-Tech Infrastructures Private Limited following proof of payment to the respondent.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appellant's application to release funds previously deposited under Section 43(5) of the Act, directing the Registry to refund the amount to Suncity Hi-Tech Infrastructures Private Limited following proof of payment to the respondent. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appellant's application to release funds previously deposited under Section 43(5) of the Act, directing the Registry to refund the amount to Suncity Hi-Tech Infrastructures Private Limited following proof of payment to the respondent.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126003692025-14-05-2025

The Tribunal allowed the appellant's application to release funds previously deposited under Section 43(5) of the Act, directing the Registry to refund the amount to Suncity Hi-Tech Infrastructures Private Limited following proof of payment to the respondent.

TathyaGrid RERA Intelligence AI

Need to research all rulings for suncity hi-tech infrastructures private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →