up_reraStatus: Active
CASE ID: 0901126004212020

Appellant / Complainant

Rudra Buildwell Infra P Ltd

VS

Respondent

Deepak Sharma, Chairperson UP Real Estate Regulation Authority

Developer Firm

rudra buildwell infra p ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

8 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126004212020 by Rudra Buildwell Infra P Ltd against Deepak Sharma, Chairperson UP Real Estate Regulation Authority before up_rera.

2
Stage 104/02/2021

For Order

No text available.

3
Stage 203/02/2021

For Order

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by M/S Rudra Buildwell Infra P Ltd due to the non-appearance of the appellant or their counsel and the absence of any request for adjournment.

4
Stage 322/01/2021

For Order

The Tribunal granted the appellant a final one-week extension to comply with Section 43(5) of the Act, warning that failure to achieve complete compliance by the next hearing on 03.02.2021 will result in the dismissal of the appeal.

5
Stage 405/01/2021

Admission

No text available.

6
Stage 5Interim Order

Tribunal Order #0901126004212020-22-01-2021

The Tribunal granted the appellant a final one-week extension to comply with Section 43(5) of the Act, warning that failure to achieve complete compliance by the next hearing on 03.02.2021 will result in the dismissal of the appeal.

7
Stage 6Final Ruling Order

Tribunal Order #0901126004212020-03-02-2021

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by M/S Rudra Buildwell Infra P Ltd due to the non-appearance of the appellant or their counsel and the absence of any request for adjournment.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by M/S Rudra Buildwell Infra P Ltd due to the non-appearance of the appellant or their counsel and the absence of any request for adjournment. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Active

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by M/S Rudra Buildwell Infra P Ltd due to the non-appearance of the appellant or their counsel and the absence of any request for adjournment.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Applicant/Appellant In-Person

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126004212020-22-01-2021

The Tribunal granted the appellant a final one-week extension to comply with Section 43(5) of the Act, warning that failure to achieve complete compliance by the next hearing on 03.02.2021 will result in the dismissal of the appeal.

FINAL_ORDEROrder ID: 0901126004212020-03-02-2021

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by M/S Rudra Buildwell Infra P Ltd due to the non-appearance of the appellant or their counsel and the absence of any request for adjournment.

TathyaGrid RERA Intelligence AI

Need to research all rulings for rudra buildwell infra p ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →