CASE ID: 0901126004252020

Appellant / Complainant

Rudra Buildwell Infra P Ltd

VS

Respondent

Amit Kulshreshtha, Khushboo Kulshreshtha, Chairperson UP Real Estate Regulation Authority

Developer Firm

rudra buildwell infra p ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

7 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126004252020 by Rudra Buildwell Infra P Ltd against Amit Kulshreshtha, Khushboo Kulshreshtha, Chairperson UP Real Estate Regulation Authority before up_rera.

2
Stage 104/02/2021

For Order

No text available.

3
Stage 203/02/2021

For Order

The appeal was dismissed for want of prosecution because no one appeared on behalf of the appellant despite their counsel being listed in the cause list.

4
Stage 322/01/2021

For Order

The Tribunal granted the appellant a one-week extension to comply with Section 43(5) of the Act, warning that failure to achieve complete compliance by the next hearing on 03.02.2021 will result in the dismissal of the appeal.

5
Stage 405/01/2021

Admission

No text available.

6
Stage 5Interim Order

Tribunal Order #0901126004252020-22-01-2021

The Tribunal granted the appellant a one-week extension to comply with Section 43(5) of the Act, warning that failure to achieve complete compliance by the next hearing on 03.02.2021 will result in the dismissal of the appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Active

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Avdhesh Kumar Pandey

Official RERA Tribunal Orders (1)

INTERIM_ORDEROrder ID: 0901126004252020-22-01-2021

The Tribunal granted the appellant a one-week extension to comply with Section 43(5) of the Act, warning that failure to achieve complete compliance by the next hearing on 03.02.2021 will result in the dismissal of the appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for rudra buildwell infra p ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →