up_reraStatus: Completed
CASE ID: 0901126010462020

Appellant / Complainant

Ifci Infrastructure Development Limited Ifci Tower

VS

Respondent

Preeti Sharda

Developer Firm

ifci infrastructure development limited

Disputed Amount

33,27,773

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

37 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126010462020 by Ifci Infrastructure Development Limited Ifci Tower against Preeti Sharda before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 101/08/2025

Hearing

The Appellate Tribunal quashed the previous order for want of jurisdiction but, based on admitted facts, directed the appellant promoter to pay delay interest at MCLR+1% on the deposited amount from 01.04.2013 to 28.12.2017, along with Rs. 25,000 in litigation costs.

3
Stage 211/07/2025

Hearing

The Tribunal granted the appellant time to file a supplementary affidavit addressing specific construction and project timeline details and scheduled the next hearing for August 1, 2025.

4
Stage 317/02/2025

Notice

The appeal filed by IFCI Infrastructure Development Limited was dismissed due to the non-appearance of the appellant's counsel to press the matter.

5
Stage 420/01/2025

For Order

The Tribunal issued notices to the parties and scheduled the appeal for the next hearing on 17.02.2025.

6
Stage 519/09/2024

Hearing

The Tribunal heard arguments from both parties regarding the jurisdiction of the Adjudicating Officer and the legality of delay interest, subsequently reserving the judgment for future pronouncement.

7
Stage 612/09/2024

Hearing

The Tribunal scheduled the case for orders/hearing on 19.09.2024 and noted that the respondent was absent, providing them a final opportunity to argue.

8
Stage 706/09/2024

Hearing

The Tribunal granted the respondent a final opportunity to argue the matter and scheduled the next hearing for 12.09.2024 to consider the application for condonation of delay, noting that no further adjournments will be permitted.

9
Stage 821/08/2024

Hearing

The Tribunal adjourned the appeal to 06.09.2024 due to the absence of both parties and technical glitches with the portal.

10
Stage 908/08/2024

Hearing

The Tribunal granted the respondent a final opportunity to prepare their brief and rescheduled the appeal for a final hearing on 21.08.2024.

11
Stage 1009/07/2024

Hearing

The Tribunal granted an adjournment requested by the respondent on personal grounds and scheduled the interest appeal for hearing on 08.08.2024.

12
Stage 1101/07/2024

Hearing

The Tribunal directed the respondent's counsel to file an application regarding the respondent's intent not to contest the execution case and scheduled the matter for hearing on 09.07.2024.

13
Stage 1201/05/2024

Hearing

No text available.

14
Stage 1329/03/2024

Hearing

The Tribunal allowed the appellant's application to amend the memo of appeal to include a new ground regarding the lack of jurisdiction of the Adjudicating Officer. The parties were directed to exchange the amended memo and subsequent objections within specified timelines.

15
Stage 1405/03/2024

Hearing

The Tribunal granted the appellant one week to file an amendment application to incorporate grounds challenging the Adjudicating Officer's order and scheduled the matter for hearing on 29.03.2024.

16
Stage 1519/02/2024

Hearing

The Tribunal adjourned the proceedings at the request of the respondent's counsel to allow time for brief preparation and rescheduled the hearing for 05.03.2024.

17
Stage 1619/01/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to the unavailability of complete records and scheduled the next hearing for 19.02.2024, noting that no further adjournments will be permitted.

18
Stage 1717/10/2023

Hearing

No text available.

19
Stage 1811/09/2023

Hearing

The Tribunal adjourned the proceedings due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh, rescheduling the hearing to 17.10.2023.

20
Stage 1921/08/2023

Hearing

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on 11.09.2023.

21
Stage 2018/08/2023

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel but cautioned that no further adjournments will be permitted on the next hearing date, which is scheduled for 21.08.2023.

22
Stage 2110/04/2023

Hearing

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by IFCI Infrastructure Development Limited due to the non-appearance of the appellant's counsel.

23
Stage 2227/02/2023

Hearing

The Tribunal issued notice to the respondent for a hearing scheduled on 10.04.2023 and directed the applicant to serve the notice and appeal documents via email and speed-post.

24
Stage 2330/03/2022

Hearing

The Tribunal heard arguments from the appellant's counsel and noted the respondent's health condition, subsequently reserving the judgment for future pronouncement.

25
Stage 2422/11/2021

Hearing

The appeal was dismissed for want of prosecution due to the non-appearance of the appellant or their counsel.

26
Stage 2528/09/2021

Hearing

The Tribunal adjourned the matter due to the absence of both parties and rescheduled the hearing for 22.11.2021.

27
Stage 2629/04/2021

Hearing

No text available.

28
Stage 2702/04/2021

Hearing

The Tribunal directed the respondent to email their reply to the appellant and permitted the appellant to file a rejoinder, while ordering both parties to upload documents to the e-portal and file originals in the Registry before the next hearing on 29.04.2021.

29
Stage 2812/02/2021

Hearing

The Tribunal granted the respondent one final opportunity to file a reply to the grounds of appeal via email and the e-portal, adjourning the matter to 02.03.2021.

30
Stage 2902/02/2021

Hearing on Appeal

The Tribunal adjourned the matter to 12.02.2021 for further hearing, noting the respondent's absence and the appellant's counsel's submission that a settlement is likely.

31
Stage 3007/01/2021

Hearing

No text available.

32
Stage 3106/11/2020

Hearing

No text available.

33
Stage 32Final Ruling Order

Tribunal Order #0901126010462020-01-08-2025

The Appellate Tribunal quashed the previous order for want of jurisdiction but, based on admitted facts, directed the appellant promoter to pay delay interest at MCLR+1% on the deposited amount from 01.04.2013 to 28.12.2017, along with Rs. 25,000 in litigation costs.

34
Stage 33Final Ruling Order

Tribunal Order #0901126010462020-10-04-2023

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by IFCI Infrastructure Development Limited due to the non-appearance of the appellant's counsel.

35
Stage 34Final Ruling Order

Tribunal Order #0901126010462020-17-02-2025

The appeal filed by IFCI Infrastructure Development Limited was dismissed due to the non-appearance of the appellant's counsel to press the matter.

36
Stage 35Interim Order

Tribunal Order #0901126010462020-29-03-2024

The Tribunal allowed the appellant's application to amend the memo of appeal to include a new ground regarding the lack of jurisdiction of the Adjudicating Officer. The parties were directed to exchange the amended memo and subsequent objections within specified timelines.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal quashed the previous order for want of jurisdiction but, based on admitted facts, directed the appellant promoter to pay delay interest at MCLR+1% on the deposited amount from 01.04.2013 to 28.12.2017, along with Rs. 25,000 in litigation costs. The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by IFCI Infrastructure Development Limited due to the non-appearance of the appellant's counsel. The appeal filed by IFCI Infrastructure Development Limited was dismissed due to the non-appearance of the appellant's counsel to press the matter. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal quashed the previous order for want of jurisdiction but, based on admitted facts, directed the appellant promoter to pay delay interest at MCLR+1% on the deposited amount from 01.04.2013 to 28.12.2017, along with Rs. 25,000 in litigation costs. The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by IFCI Infrastructure Development Limited due to the non-appearance of the appellant's counsel. The appeal filed by IFCI Infrastructure Development Limited was dismissed due to the non-appearance of the appellant's counsel to press the matter.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

w.e.f. 01.04.2013 till 28.12.2017

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Siddharth Vikram Asthana

Respondent Advocate(s)

  • Shuchita Singh

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126010462020-01-08-2025

The Appellate Tribunal quashed the previous order for want of jurisdiction but, based on admitted facts, directed the appellant promoter to pay delay interest at MCLR+1% on the deposited amount from 01.04.2013 to 28.12.2017, along with Rs. 25,000 in litigation costs.

FINAL_ORDEROrder ID: 0901126010462020-10-04-2023

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by IFCI Infrastructure Development Limited due to the non-appearance of the appellant's counsel.

FINAL_ORDEROrder ID: 0901126010462020-17-02-2025

The appeal filed by IFCI Infrastructure Development Limited was dismissed due to the non-appearance of the appellant's counsel to press the matter.

INTERIM_ORDEROrder ID: 0901126010462020-29-03-2024

The Tribunal allowed the appellant's application to amend the memo of appeal to include a new ground regarding the lack of jurisdiction of the Adjudicating Officer. The parties were directed to exchange the amended memo and subsequent objections within specified timelines.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ifci infrastructure development limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →