Appellant / Complainant
Floral Realcon Pvt Ltd
Respondent
Subhrakant Sahoo
floral realcon pvt ltd
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126012692024 by Floral Realcon Pvt Ltd against Subhrakant Sahoo before up_rera.
Compliance of section 43(5)
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Floral Realcon Pvt Ltd due to the appellant's failure to comply with the mandatory requirements of Section 43(5) of the RERA Act.
Compliance of section 43(5)
The Tribunal granted a 10-day extension to the appellant to comply with the mandate of Section 43 (5) of the Act 2016 and scheduled the matter for orders on 24.10.2024.
Compliance of section 43(5)
The Tribunal granted the applicant's counsel 10 days to seek instructions from the appellant and scheduled the appeal for orders on 15.10.2024.
Compliance of section 43(5)
The Appellate Tribunal rejected the appellant's application for waiver of compliance with Section 43(5) of the Act, directing the promoter to deposit the required amount and file a CA certificate within 10 days as a prerequisite for hearing the appeal.
Compliance of section 43(5)
The Tribunal granted the appellant three days to file an application for exemption from compliance with Section 43(5) of the Act and scheduled the matter for orders on September 6, 2024.
Compliance of section 43(5)
The Tribunal granted an adjournment at the request of the appellant's counsel to argue on the compliance of Section 43(5) of the Act, rescheduling the hearing to 02.09.2024.
Defect Removal
The Tribunal granted the appellant one week to file an application seeking exemption from depositing funds under Section 43(5) of the Act and scheduled the matter for orders on August 21, 2024.
Defect Removal
The Tribunal directed the Appellant's counsel to file the RERA notification regarding deemed completion certificates and address compliance with Section 43(5) of the Act by July 5, 2024.
Defect Removal
The Tribunal granted the appellant a one-week extension to comply with Section 43 (5) of the Act 2016 and scheduled the matter for further orders on 01.05.2024.
Tribunal Order #0901126012692024-24-10-2024
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Floral Realcon Pvt Ltd due to the appellant's failure to comply with the mandatory requirements of Section 43(5) of the RERA Act.
Tribunal Order #0901126012692024-06-09-2024
The Appellate Tribunal rejected the appellant's application for waiver of compliance with Section 43(5) of the Act, directing the promoter to deposit the required amount and file a CA certificate within 10 days as a prerequisite for hearing the appeal.
Tribunal Order #0901126012692024-01-07-2024
The Tribunal directed the Appellant's counsel to file the RERA notification regarding deemed completion certificates and address compliance with Section 43(5) of the Act by July 5, 2024.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Floral Realcon Pvt Ltd due to the appellant's failure to comply with the mandatory requirements of Section 43(5) of the RERA Act. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Floral Realcon Pvt Ltd due to the appellant's failure to comply with the mandatory requirements of Section 43(5) of the RERA Act.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Harish Pandey
- Anshuman Tripathi
Official RERA Tribunal Orders (3)
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Floral Realcon Pvt Ltd due to the appellant's failure to comply with the mandatory requirements of Section 43(5) of the RERA Act.
The Appellate Tribunal rejected the appellant's application for waiver of compliance with Section 43(5) of the Act, directing the promoter to deposit the required amount and file a CA certificate within 10 days as a prerequisite for hearing the appeal.
The Tribunal directed the Appellant's counsel to file the RERA notification regarding deemed completion certificates and address compliance with Section 43(5) of the Act by July 5, 2024.