Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

18 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126014092021 by Paramount Propbuild Pvt. Ltd. against Pashupati Prasad, Kanchan Lata, U.P. Real Estate Regulatory Authority Lucknow before up_rera.

Non-Compliance & Execution
2
Stage 122/04/2022

Delay condonation

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal; it further directed that the pre-deposited amount be transferred to U.P. RERA for distribution to the respondent during execution proceedings.

3
Stage 221/04/2022

Delay condonation

The Tribunal granted the appellant's request for an adjournment to prepare arguments and citations regarding the application for condonation of delay, scheduling the next hearing for 22.04.2022.

4
Stage 303/03/2022

to file objections and its reply

The Tribunal noted a discrepancy regarding the filing of the power of attorney by the respondent's representative and scheduled the matter for 21.04.2022 to address the application for condonation of delay and its objections.

5
Stage 424/12/2021

Hearing

The Tribunal directed the appellant to provide copies of the appeal and condonation application to the respondent and granted the respondent two weeks to file objections.

6
Stage 526/11/2021

Defect Removal

The Tribunal noted compliance with Section 43(5) of the Act and directed that notice be issued to the respondent via email and registered post, scheduling the next hearing for December 24, 2021.

7
Stage 602/11/2021

Defect Removal

The Tribunal adjourned the case to 26.11.2021 and directed the parties to exchange pleadings and file originals with the Registry at least one week before the next hearing.

8
Stage 701/10/2021

Defect Removal

The Tribunal granted the appellant's counsel one week's time to ensure compliance with the previous order dated 13.09.2021 and rescheduled the appeal for hearing on 02.11.2021.

9
Stage 813/09/2021

Defect Removal

The Tribunal directed the appellant to rectify deficiencies regarding Section 43(5) compliance by submitting a fresh CA certificate with the correct SBI interest rate and depositing any remaining amounts.

10
Stage 929/04/2021

Defect Removal

No text available.

11
Stage 1006/04/2021

Defect Removal

No text available.

12
Stage 1112/03/2021

Defect Removal

The Tribunal granted an adjournment requested by the appellant's counsel and directed the removal of registry defects and compliance with Section 43(5) of the Act by the next hearing, warning of potential dismissal for non-compliance.

13
Stage 1201/03/2021

Defect Removal

The Tribunal granted the appellant a one-week extension to remove registry defects, noting that failure to do so may result in dismissal of the appeal.

14
Stage 1323/02/2021

Admission

The Tribunal granted the appellant three days to rectify registry defects and scheduled the appeal for a hearing on March 1, 2021.

15
Stage 14Final Ruling Order

Tribunal Order #0901126014092021-22-04-2022

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal; it further directed that the pre-deposited amount be transferred to U.P. RERA for distribution to the respondent during execution proceedings.

16
Stage 15Interim Order

Tribunal Order #0901126014092021-12-03-2021

The Tribunal granted an adjournment requested by the appellant's counsel and directed the removal of registry defects and compliance with Section 43(5) of the Act by the next hearing, warning of potential dismissal for non-compliance.

17
Stage 16Interim Order

Tribunal Order #0901126014092021-13-09-2021

The Tribunal directed the appellant to rectify deficiencies regarding Section 43(5) compliance by submitting a fresh CA certificate with the correct SBI interest rate and depositing any remaining amounts.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal; it further directed that the pre-deposited amount be transferred to U.P. RERA for distribution to the respondent during execution proceedings. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal; it further directed that the pre-deposited amount be transferred to U.P. RERA for distribution to the respondent during execution proceedings.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Swapnil Yadav
  • Shashank Kumar
  • Saurabh Misra

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126014092021-22-04-2022

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal; it further directed that the pre-deposited amount be transferred to U.P. RERA for distribution to the respondent during execution proceedings.

INTERIM_ORDEROrder ID: 0901126014092021-12-03-2021

The Tribunal granted an adjournment requested by the appellant's counsel and directed the removal of registry defects and compliance with Section 43(5) of the Act by the next hearing, warning of potential dismissal for non-compliance.

INTERIM_ORDEROrder ID: 0901126014092021-13-09-2021

The Tribunal directed the appellant to rectify deficiencies regarding Section 43(5) compliance by submitting a fresh CA certificate with the correct SBI interest rate and depositing any remaining amounts.

TathyaGrid RERA Intelligence AI

Need to research all rulings for paramount propbuild pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →