Appellant / Complainant
Than Singh, Suman Singh
Respondent
Paramount Propbuild Pvt. Ltd.
paramount propbuild pvt. ltd.
₹42,19,957
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126017772020 by Than Singh, Suman Singh against Paramount Propbuild Pvt. Ltd. before up_rera.
for delivery of Judgment/Order
The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by the appellants, upholding the Regulatory Authority's order for possession and interest payment, while ruling that non-compliance should be addressed through execution proceedings rather than a fresh appeal.
Final Hearing
The Tribunal heard arguments from the counsel for both parties and reserved the judgment for a later date.
Final Hearing
The Tribunal noted that pleadings have been exchanged and the appeal is ripe for hearing; consequently, the matter is scheduled for a hearing on 28.11.2022.
Final Hearing
The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on 21.10.2022.
Final Hearing
The Tribunal granted the appellant's counsel one week to prepare his brief and scheduled the appeal for a hearing on 10.10.2022.
Final Hearing
The Tribunal granted an adjournment requested by the respondent and rescheduled the case for further orders on 08.09.2022.
Final Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the hearing for August 10, 2022.
Final Hearing
The Tribunal directed the Respondent to file their Occupancy Certificate/Completion Certificate (OC/CC) along with written submissions and relied-upon judgments, scheduling the next hearing for July 1, 2022.
Final Hearing
The Tribunal granted a request from the respondent's counsel to file dates of events and relied-upon cases, subsequently adjourning the matter to 26.04.2022 for final hearing.
Final Hearing
The Tribunal directed the Registry to scrutinize the appellant's documents for e-portal uploading and granted the respondent one week to file a response to said documents.
Final Hearing
The Tribunal granted an adjournment request from the respondent's counsel due to a scheduling conflict and rescheduled the hearing for January 3, 2022.
Final Hearing
The Tribunal directed the appellants to produce their detailed complaint and ordered the Registry to summon the RERA records for Complaint No. NCR 144/04/0921/2019 to resolve inconsistencies in the appellants' claims.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to a pending judgment from the Supreme Court regarding a related SLP, rescheduling the matter for 22.11.2021.
Hearing
The Tribunal adjourned the matter to 28.10.2021 because litigation regarding the same subject matter is currently pending before the Supreme Court.
Hearing
The Tribunal noted the filing of High Court and Supreme Court orders by the respondent and adjourned the matter to 16.03.2021 for further hearing.
Tribunal Order #0901126017772020-31-05-2023
The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by the appellants, upholding the Regulatory Authority's order for possession and interest payment, while ruling that non-compliance should be addressed through execution proceedings rather than a fresh appeal.
Tribunal Order #0901126017772020-22-11-2021
The Tribunal directed the appellants to produce their detailed complaint and ordered the Registry to summon the RERA records for Complaint No. NCR 144/04/0921/2019 to resolve inconsistencies in the appellants' claims.
Tribunal Disposal & Final Award Ruling
The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by the appellants, upholding the Regulatory Authority's order for possession and interest payment, while ruling that non-compliance should be addressed through execution proceedings rather than a fresh appeal. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by the appellants, upholding the Regulatory Authority's order for possession and interest payment, while ruling that non-compliance should be addressed through execution proceedings rather than a fresh appeal.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
from 01.07.2016 till physical possession
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Vaibhav Krishna
Respondent Advocate(s)
- Shashank Kumar
Official RERA Tribunal Orders (2)
The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by the appellants, upholding the Regulatory Authority's order for possession and interest payment, while ruling that non-compliance should be addressed through execution proceedings rather than a fresh appeal.
The Tribunal directed the appellants to produce their detailed complaint and ordered the Registry to summon the RERA records for Complaint No. NCR 144/04/0921/2019 to resolve inconsistencies in the appellants' claims.